Home Products Schedule Analyzer Overview

SA Pro Schedule Logger
By Ron Winter Consulting LLC, Copyright 2003
(770) 587-4903 or email at Ron@RonWinterConsulting.com.com

Schedule Logger reads your SA Pro Baseline Checker and SA Pro Update Checker reports and returns the findings back to your schedule in the activity log section. Brief summaries are automatically written into the appropriate activity's logs describing pertinent findings for each report. Used over time, you can re-create a complete summary of the SA Pro analysis for each activity throughout the history of your project!

Below is a sample log report as generated by P3 after Schedule Logger was used.



 -----------------------------------------------------------------------------------------------------------------------------------
 CARMICHAEL, CALIFORNIA                         PRIMAVERA PROJECT PLANNER                       HOSPITAL EXP / RENOV.           

 REPORT DATE  9DEC98  RUN NO. 2622                                                              START DATE  3MAR97  FIN DATE 16FEB00 
              14:36                                                                                                                
 LOG REPORT                                                                                     DATA DATE  28SEP98  PAGE NO.    1
                                                                                                                 
                                                 
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
    ACTIVITY   ORIG REM                                 ACTIVITY DESCRIPTION                LEVELED  LEVELED   LATE     LATE   TOTAL
       ID      DUR  DUR CAL  %                                                                ES       EF      START   FINISH  FLOAT
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
 SMUD REDESIGN                                   
   ELC100        10    0 1 100            REDESIGN PRIMARY & SECONDARY SERVICE (RULE 16)    8APR97A 13AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC102.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY COMPLETED THIS PERIOD ON PLAN.    
   ELC102         5    0 1 100            COORD/PROCURE PER REDESIGN SMUD SERVICE          13AUG97A 20AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC104.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTUAL DURATION MORE THAN PLANNED BY 1.    
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "COORD/PROCURE/PRICE PER REDESIGN SMUD SERV
                                               ACTIVITY STARTED 1 EARLY.                  
   ELC104         0    0 1 100            LOA - REDESIGN SMUD SERVICE                               19AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC106.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               PLANNED MILESTONE DATE ADVANCED BY 1.      
   ELC106        20    0 1 100            INSTALL U/G ELEC PER REDESIGN SMUD SERVICE(PROJ) 20AUG97A 19SEP97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC118.       
                                               FS RELATIONSHIP ADDED TO ACT STE204.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               EST. COMPLETION LESS THAN PLANNED BY 3.    
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "INSTALL U/G ELEC PER REDESIGN SMUD SERVICE
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               ACTUAL DURATION MORE THAN PLANNED BY 5.    
                                          1582 Project Review 11-16-1998 at 18:35:58      
                                               FS RELATIONSHIP ADDED TO ACT STE104.       
                                               FS RELATIONSHIP ADDED TO ACT STE203.       
                                               FS RELATIONSHIP ADDED TO ACT STE206.       
                                               FS RELATIONSHIP ADDED TO ACT STE212.       
                                               FS RELATIONSHIP ADDED TO ACT STE218.       
                                          1682 Project Review 11-16-1998 at 19:00:45      
                                               FS RELATIONSHIP ADDED TO ACT STE216.       
   ELC108        10    0 1 100            REDESIGN SMUD FEEDERS (SMUD WORK)                 8APR97A 13AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC110.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY COMPLETED THIS PERIOD ON PLAN.    
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "REDESIGN SMUD FEEDERS"                    
   ELC110        10    0 1 100            PREP/EVAL/APPRL VNDR PRICING-SMUD FEEDERS (PROJ) 15SEP97A 22SEP97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC112.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "PREP/EVALUATE/APPROVE VNDR PRICING-SMUD FE
                                               FS RELATIONSHIP DELETED TO ACT ELC112.     
                                               FS RELATIONSHIP ADDED TO ACT ELC116.       
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               ACTUAL DURATION LESS THAN PLANNED BY 4.    
   ELC112         0    0 1 100            LOA - REDESIGN SMUD FEEDERS (PROJ)                        22SEP97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC116.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "NTP - REDESIGN SMUD FEEDERS"              
                                               PLANNED MILESTONE DATE DELAYED BY 11.      
 

 -----------------------------------------------------------------------------------------------------------------------------------
 CARMICHAEL, CALIFORNIA                         PRIMAVERA PROJECT PLANNER                       HOSPITAL EXP / RENOV.           

 REPORT DATE  9DEC98  RUN NO. 2622                                                              START DATE  3MAR97  FIN DATE 16FEB00 
              14:36                                                                                                                
 LOG REPORT                                                                                     DATA DATE  28SEP98  PAGE NO.    2
                                                                                                                 
                                                 
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
    ACTIVITY   ORIG REM                                 ACTIVITY DESCRIPTION                LEVELED  LEVELED   LATE     LATE   TOTAL
       ID      DUR  DUR CAL  %                                                                ES       EF      START   FINISH  FLOAT
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
                                               FS RELATIONSHIP DELETED TO ACT ELC116.     
                                               FS RELATIONSHIP ADDED TO ACT ELC110.       
                                               CONSTRAINT ADDED SINCE LAST UPDATE:        
                                               FINISH NO EARLIER THAN 12SEP97.            
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               PLANNED MILESTONE DATE DELAYED BY 6.       
                                               CONSTRAINT DELETED SINCE LAST UPDATE:      
                                               FINISH NO EARLIER THAN 12SEP97.            
   ELC116        20    0 1 100            INSTALL U/G ELC FDRS PER SMUD FDR REDESIGN(PROJ) 22SEP97A 24OCT97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT ELC118.       
                                               FS RELATIONSHIP ADDED TO ACT STE200.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "INSTALL U/G ELC FEEDERS PER SMUD FEEDER RE
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               EST. COMPLETION LESS THAN PLANNED BY 5.    
                                               ACTIVITY STARTED 1 EARLY.                  
                                          0682 Project Review 11-12-1998 at 09:46:39      
                                               ACTUAL DURATION MORE THAN PLANNED BY 10.   
   ELC118        10    0 1 100            SMUD PULL CABLES-PRIMARY/2NDARY SRVCE (PROJ)      5JAN98A 12FEB98A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT EL2222.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "SMUD PULL CABLES FOR PRIMARY/2NDARY SERVIC
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               CONSTRAINT ADDED SINCE LAST UPDATE:        
                                               START NO EARLIER THAN 17NOV97.             
                                          0782 Project Review 11-12-1998 at 10:00:27      
                                               START NO EARLIER THAN CONST. DATE MODIFIED 
                                               FROM 17NOV97 TO 10DEC97.                   
                                          0882 Project Review 11-12-1998 at 10:15:39      
                                               CONSTRAINT DELETED SINCE LAST UPDATE:      
                                               START NO EARLIER THAN 10DEC97.             
                                               LATE START OF 45 WITH TF = 13.             
                                          0982 Project Review 11-12-1998 at 10:29:35      
                                               EST. COMPLETION MORE THAN PLANNED BY 15.   
                                               ACTIVITY ON MOST CRITICAL LIST.            
                                          1082 Project Review 11-16-1998 at 16:03:57      
                                               ACTUAL DURATION MORE THAN PLANNED BY 3.    
 PACIFIC BELL TELEPHONE                          
   TEL100        10    0 1 100            REDESIGN PAC BELL TELEPHONE                       8APR97A 11AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT TEL102.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTUAL DURATION MORE THAN PLANNED BY 1.    
                                               FS RELATIONSHIP DELETED TO ACT TEL102.     
                                               FS RELATIONSHIP ADDED TO ACT TEL104.       
   TEL102        10    0 1 100            COORD/PROCURE - TELEPHONE REDESIGN               14AUG97A 18AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT TEL104.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTUAL DURATION LESS THAN PLANNED BY 7.    
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "COORD/PROCURE/PRICE PAC BELL TELEPHONE RED
                                               FS RELATIONSHIP DELETED TO ACT TEL104.     
                                               FS RELATIONSHIP ADDED TO ACT D10005.       
   TEL104         0    0 1 100            LOA - PAC BELL TELEPHONE REDESIGN                         11AUG97A                        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ADDED SINCE PROJ 0282.            
                                               FS RELATIONSHIP ADDED TO ACT D10005.       
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               PLANNED MILESTONE DATE ADVANCED BY 9.      
 

 -----------------------------------------------------------------------------------------------------------------------------------
 CARMICHAEL, CALIFORNIA                         PRIMAVERA PROJECT PLANNER                       HOSPITAL EXP / RENOV.           

 REPORT DATE  9DEC98  RUN NO. 2622                                                              START DATE  3MAR97  FIN DATE 16FEB00 
              14:36                                                                                                                
 LOG REPORT                                                                                     DATA DATE  28SEP98  PAGE NO.    3
                                                                                                                 
                                                 
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
    ACTIVITY   ORIG REM                                 ACTIVITY DESCRIPTION                LEVELED  LEVELED   LATE     LATE   TOTAL
       ID      DUR  DUR CAL  %                                                                ES       EF      START   FINISH  FLOAT
  ----- -----  ---- ---- - --- ---------- ------------------------------------------------ -------- -------- -------- -------- -----
                                               FS RELATIONSHIP DELETED TO ACT D10005.     
                                               FS RELATIONSHIP ADDED TO ACT TEL102.       
 METAL STAIR REDESIGN - DELTA 1&2                
   P98-104        0    0 1 100            RELEASE FOR FAB - MTL STAIRS                               6AUG97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT P98-105.      
                                          0182 Base Project Review 1-12-1998 at 18:43:24  
                                               MILESTONES CODED AS ACTIVITIES.            
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTIVITY CHANGED TO MILESTONE, DUR WAS -1. 
   P98-105       65    0 1 100            COORD/FABRICATE - MTL STAIRS PER REDESIGN         6AUG97A 24NOV97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT P98-106.      
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               EST. COMPLETION LESS THAN PLANNED BY 3.    
                                               ACTIVITY HAD DESCRIPTION CHANGE FROM       
                                               "FABRICATE - MTL STAIRS PER REDESIGN"      
                                          0582 Project Review 11-12-1998 at 09:33:46      
                                               EST. COMPLETION MORE THAN PLANNED BY 5.    
                                          0682 Project Review 11-12-1998 at 09:46:39      
                                               EST. COMPLETION MORE THAN PLANNED BY 15.   
                                          0782 Project Review 11-12-1998 at 10:00:27      
                                               ACTUAL DURATION LESS THAN PLANNED BY 5.    
   P98-106        1    0 1 100            INITIAL DELIVERY - MTL STAIRS                    24NOV97A 24NOV97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT 1ST01A.       
                                               FS RELATIONSHIP ADDED TO ACT 1ST02A.       
                                               FS RELATIONSHIP ADDED TO ACT 1ST03A.       
                                               FS RELATIONSHIP ADDED TO ACT HEL200.       
                                          0182 Base Project Review 1-12-1998 at 18:43:24  
                                               MAJOR MATERIALS DELIVERY ACTIVITIES.       
                                               MILESTONES CODED AS ACTIVITIES.            
                                          0782 Project Review 11-12-1998 at 10:00:27      
                                               ACTUAL DURATION MORE THAN PLANNED BY 1.    
                                               ACTIVITY STARTED 1 EARLY.                  
   P98-109       10    0 1 100            ARCH APPRVL - MTL STAIRS                          7JUL97A  6AUG97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT P98-104.      
                                          0282 Project Review 11-12-1998 at 08:33:31      
                                               ACTIVITY STARTED 1 EARLY.                  
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               EST. COMPLETION MORE THAN PLANNED BY 15.   
                                          0482 Project Review 11-12-1998 at 09:02:08      
                                               ACTUAL DURATION LESS THAN PLANNED BY 2.    
   P98-130       10    0 1 100            PREP SD'S - MTL STAIRS                            2JUN97A  7JUL97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT P98-103.      
                                               FS RELATIONSHIP ADDED TO ACT P98-109.      
                                          0282 Project Review 11-12-1998 at 08:33:31      
                                               ACTUAL DURATION MORE THAN PLANNED BY 15.   
                                               LATE START OF 4 WITH TF = 8.               
 EFIS ATTACHMENT REDESIGN - DELTA 1&2            
   P99-104        0    0 1 100            RELEASE FOR FAB - EIFS ATTACH SYSTEM                      13AUG97A                        
                                          0182 Project Review 11-12-1998 at 08:20:45      
                                               ACTIVITY ADDED SINCE PROJ B182.            
                                               FS RELATIONSHIP ADDED TO ACT P99-105.      
                                          0182 Base Project Review 1-12-1998 at 18:43:24  
                                               MILESTONES CODED AS ACTIVITIES.            
                                               MULTIPLE NEAR-CRITICAL PATH ACTIVITIES.    
                                                   NUMBER OF CO-CRITICAL PATHS: 5.        
                                          0382 Project Review 11-12-1998 at 08:42:03      
                                               ACTIVITY ON MOST CRITICAL LIST.            
                                          0482 Project Review 11-12-1998 at 09:02:08