LONGEST PATH Software Example

 

 

 

Sorting in the traditional manner (using Total Float and Early Start Dates,) a typical critical path shedule would look like the following P3 screen.

This is a sample P3 schedule before using Longest Path Software.

 

Once you run LONGEST PATH Software, you can sort on Longest Path Value and on Longest Path Sequence just like the following P3 screen.

This is a sample P3 schedule after using Longest Path Software.

 

Notice how the activities are now shown in logical order with out-of-sequence progress clearly displayed as well as activities on different calendars and interruptible progress displayed.

 

LONGEST PATH Software is copyright Ron Winter Consulting LLC 2003.