Sample Update
Checker Report - Lists Have Been Trimmed to 10 Activities
SCHEDULE ANALYZER ============================ | Version 2.78 | ============================ Copyright Ron Winter Consulting LLC 1994/2003 This report was prepared by Ron Winter Consulting LLC. Target Project: C2I2 Analysis Date: 07-02-2003 at 09:07:40 Update Project: C2K0 November Update Project Completion Date checked. Analysis covers project status update from 10OCT02 to 17NOV02. ******************************************************** * CALENDAR ADDED : Calendar # E 7dpw - WB Canal * ******************************************************** **************************************************************************** * CALENDARS WHICH HAVE BEEN CHANGED * *------------------------------------+-------------------------------------* * DELETED FROM PROJECT C2I2 | ADDED TO PROJECT C2K0 * * CAL TYPE START TO END | CAL TYPE START TO END * *------------------------------------+-------------------------------------* * 1 HOLIDAY 25NOV00 TO 26NOV00| 1 HOLIDAY 25NOV00 * * | 1 HOLIDAY 23NOV01 * * 1 HOLIDAY 30NOV01 | * * | E WORK 1JAN * * | E WORK 4JUL * * | E WORK 25DEC * * | E WORK 11NOV00 * * | E WORK 11NOV01 * * | E WORK 21JAN02 * * | E WORK 12FEB02 * * | E WORK 18FEB02 * * | E WORK 31MAR02 * * | E WORK 27MAY02 * * | E WORK 2SEP02 * * | E WORK 9SEP02 * * | E WORK 14OCT02 * * | E WORK 11NOV02 * * | E WORK 28NOV02 * * | E WORK 29NOV02 * * | E WORK 20JAN03 * * | E WORK 12FEB03 * * | E WORK 17FEB03 * * | E WORK 31MAR03 * * | E WORK 26MAY03 * * | E WORK 1SEP03 * * | E WORK 9SEP03 * * | E WORK 13OCT03 * * | E WORK 11NOV03 * * | E WORK 27NOV03 * * | E WORK 28NOV03 * * | E WORK 19JAN04 * * | E WORK 12FEB04 * * | E WORK 16FEB04 * * | E WORK 31MAR04 * * | E WORK 31MAY04 * * | E WORK 6SEP04 * * | E WORK 9SEP04 * * | E WORK 11OCT04 * * | E WORK 11NOV04 * * | E WORK 25NOV04 * * | E WORK 26NOV04 * * | E WORK 17JAN05 * * | E WORK 12FEB05 * * | E WORK 21FEB05 * * | E WORK 31MAR05 * * | E WORK 30MAY05 * * | E WORK 5SEP05 * * | E WORK 9SEP05 * * | E WORK 10OCT05 * * | E WORK 11NOV05 * * | E WORK 24NOV05 * * | E WORK 25NOV05 * * | E WORK 16JAN06 * * | E WORK 12FEB06 * * | E WORK 20FEB06 * * | E WORK 31MAR06 * * | E WORK 29MAY06 * * | E WORK 4SEP06 * * | E WORK 9SEP06 * * | E WORK 11NOV06 * * | E WORK 23NOV06 * * | E WORK 24NOV06 * * | E WORK 12FEB07 * * | E WORK 31MAR07 * * | E WORK 9SEP07 * *------------------------------------+-------------------------------------* * 2 HOLIDAYS WERE DELETED | 64 HOLIDAYS WERE ADDED * **************************************************************************** Project Rules check okay. Scheduling Method checks. Types of Activity Scheduling Method checks. Total Float Calculation checks. ================================ ACTIVITIES ================================ 0 Target File activities are bogus. 0 Update File activities are bogus. Target Project C2I2 with 3963 activities. Data Date = 10OCT02 Update Project C2K0 with 4196 activities. Data Date = 17NOV02 0 As-Built activities have been deleted out of 1 total deleted. 0 In-Progress activities have been deleted out of 1 total deleted. ---------------------------------------------------------------------------- | PLANNED ACTIVITIES WHICH HAVE BEEN DELETED SINCE LAST UPDATE | | ACT PROBLEM FLOAT TITLE | :---------- -------- ----- ------------------------------------------------+ |PCCB02SC30 DELETED 47 Bed #2 Shutdown for Segment Storage Capacity | ---------------------------------------------------------------------------- 1 Planned activity has been deleted out of 1 total deleted. ---------------------------------------------------------------------------- | NEW AS-BUILT ACTIVITIES ADDED SINCE LAST UPDATE | | ACT PROBLEM FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |BPSUBMEN28 NEW ACT 60 NW Conc 1" Agg (Ftg) Mix Design: Resubmit | |ESSUBMEL01 NEW ACT 1051 SCADA: Prep & Submit | |FNFABRPL11 NEW ACT 59 HAMMER FOLLOWER/ACCES.: LABOR DISPUTE | |FNREVWPL39 NEW ACT 70 Bubble Curtain (Energy Attenuator): Rereview III| |FNSUBMFS16 NEW ACT 87 Pile Head Weld Procedure: Prep & Submit | |FNSUBMPL37 NEW ACT 58 Bubble Curtain (Energy Attenuator): Resubmit III| |FNSUBMPL45 NEW ACT 70 Bubble Curtain (Energy Attenuator): Resubmit IV | |FWSUBMMJ22 NEW ACT 275 Mod Joint Seal Working Dwgs: Resubmit III | |PCFABRSC23 NEW ACT 0 SEG BEDS: LONGSHOREMAN LABOR DISPUTE | |PCREVWPN32 NEW ACT 44 Segment Panels: Precast Forms: Review & Approve | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 24 As-Built activities have been added out of 234 total added. CAUTION: The float values printed above were obtained by noting the lowest float of all immediate, active successor activities. This does not mean that the float presented here was the activity's actual float, only that it is unlikely that the actual float was less than that shown. ---------------------------------------------------------------------------- | NEW IN-PROGRESS ACTIVITIES ADDED SINCE LAST UPDATE | | ACT PROBLEM FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |BPREVWEN29 NEW ACT 60 NW Conc 1" Agg (Ftg) Mix Design: Rereview | |ESREVWEL02 NEW ACT 1051 SCADA: Review & Approve | |ESSUBMEL03 NEW ACT 658 LVCC, UL Panels, Transformer: Re-submit | |FNFABRFS31 NEW ACT 14 Ftg 16E: Fabrication: Inclement Weather | |FNFABRFS33 NEW ACT 89 Ftg 15E: Fabrication: Inclement Weather | |FNFABRPL12 NEW ACT 59 HAMMER FOLLOWER/ACCES.: LOCATE/DELIVER | |FNREVWFS18 NEW ACT 87 Pile Head Weld Procedure: Review & Approve | |FNREVWPL47 NEW ACT 70 Bubble Curtain (Energy Attenuator): Rereview IV | |FNSUBMFC21 NEW ACT 55 Pile Cap Thermal Control Plan: Resubmit | |FWREVWMJ22 NEW ACT 275 Mod Joint Seal Working Dwgs: Rereview III | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 25 In-Progress activities have been added out of 234 total added. ---------------------------------------------------------------------------- | NEW PLANNED ACTIVITIES ADDED SINCE LAST UPDATE | | ACT PROBLEM FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |ESREVWEL04 NEW ACT 658 LVCC, UL Panels, Transformer: Re-review | |FNFABRFS36 NEW ACT 14 Footing 16E: Transit through Panama Canal | |FNFABRFS38 NEW ACT 89 Footing 15E: Transit through Panama Canal | |FNFABRFS41 NEW ACT 14 Footing 16E: Transport from Canal to Oakland | |FNFABRFS43 NEW ACT 89 Footing 15E: Transport from Canal to Oakland | |FNFABRFS44 NEW ACT 56 Ftg 14E & 13E: Fabrication: Inclement Weather | |FNFABRPF40 NEW ACT 622 RRP/CP Lumber: Procure/Fab/Deliver | |FNP03ECF45 NEW ACT 128 Pier 3E: Pile - Install Studs | |FNP03ECF55 NEW ACT 128 Pier 3E: Piles - Pour Lift #2 | |FNP03EFC12 NEW ACT 136 Pier 3E: Ftg - Pour LWC Lift #2 | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 185 Planned activities have been added out of 234 total added. 0 activities had their Activity Types revised. ---------------------------------------------------------------------------- | ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS | | ACT Ty OLD D NEW D TITLE | +---------- -- ----- ----- ------------------------------------------------+ |ESREVWEL32 T 21 30 Elec Substation Sealant: Review (Caltrans | |ESREVWEL42 T 21 30 Substation Metal Frame W'Dwg/Data: Review | |ESREVWEL52 T 21 30 Substation Finish Hdw Tech Info: Review | |ESREVWEL96 T 10 30 Substation Electric Information: Reiew & Approve| |ESSUBMEL10 T 20 70 Traffic OS Equip: Submit | |ESSUBMEL20 T 40 70 Elec Service Platform Working Dwg: Prep & Submit| |ESSUBMEL25 T 20 70 Substation Metal Panel W'Dwg/Data: Prep & Submit| |ESSUBMEL40 T 20 70 Substation Metal Frame W'Dwg/Data: Prep & Submit| |ESSUBMEL50 T 20 70 Substation Finish Hdw Tech Info: Prep & Submit | |ESSUBMEL60 T 20 70 Conduit Supports Cons'n Methods: Prep & Submit | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 318 activities had their Original Durations revised. NOTE: Original Durations will automatically change if the activity is a Hammock or WBS or if Expected Finish constraint is used. ---------------------------------------------------------------------------- | ACTIVITIES WITH NEW CALENDARS | | ACT OLD CAL NEW C TITLE | +---------- ------- ----- ------------------------------------------------+ |ESREVWEL21 1 A Substation Mat'l SOO: Review (Caltrans) | |ESREVWEL32 1 A Elec Substation Sealant: Review (Caltrans) | |ESREVWEL42 1 A Substation Metal Frame W'Dwg/Data: Review | |ESREVWEL52 1 A Substation Finish Hdw Tech Info: Review | |ESREVWEL96 1 A Substation Electric Information: Reiew & Approve| |FNFABRFS50 1 E Footing 9 thru 12 E: Sub Fab | |FNFABRFS60 1 E Footing 5 thru 8 E: Sub Fab | |FNFABRFS70 1 E Footing 3 & 4E, 15 & 16W: Sub Fab | |FNFABRFS80 1 E Footing 9 thru 14W: Sub Fab | |FNFABRFS90 1 E Footing 3 thru 8W: Sub Fab | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 38 activities had their calendars changed. Key to Calendars: Calendar 1 5 dpw Calendar 2 5 dpw Calendar 3 5 dpw Calendar 4 5 dpw Calendar 5 6 dpw Calendar 6 6 dpw Calendar 7 6 dpw Calendar 8 6 dpw Calendar 9 7 dpw Calendar A 7 dpw Calendar B 7 dpw Calendar C 7 dpw Calendar D 7 dpw Calendar E 7dpw - WB Canal ---------------------------------------------------------------------------- | ACTIVITIES ON THE LONGEST PATH | | ACT CALENDAR FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |PCFABRSC20 2 Segment Beds: Procure, Fab & Deliver (Partial) | |PCFABRSC23 A SEG BEDS: LONGSHOREMAN LABOR DISPUTE | |PCFABRSC24 2 0 SEG BEDS: DELIVER (PARTIAL) | |PCCB01SC99 2 0 Assemble Segment Bed #1 | |PCCB01SC01 1 1 Cast Trial Segment 12EU1 | |PCCB01SC03 2 1 Segment 12EU1: Stress Transverse & Vertical P.T.| |PCCB01SC05 2 1 Segment 12EU1: Grout P.T. | |PCCB01SC07 2 1 Approve Trial Segment | |PCC12ESC03 1 1 Cant 12EU: Cast Segments | |PCC12ESC02 1 1 Cant 12ED: Cast Segments | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 68 activities were on the Longest Path. NOTE: The most crtical float for this project is 0. CAUTION: Some of the activities on the above Longest Path have different calendars from the others. This will often cause the Total Float value to be dissimilar. This is normal. Float values should be the same for activities with the same calendar. If not, then look for constraints at the changes. Key to Calendars: Calendar 1 5 dpw Calendar 2 5 dpw Calendar 3 5 dpw Calendar 4 5 dpw Calendar 5 6 dpw Calendar 6 6 dpw Calendar 7 6 dpw Calendar 8 6 dpw Calendar 9 7 dpw Calendar A 7 dpw Calendar B 7 dpw Calendar C 7 dpw Calendar D 7 dpw Calendar E 7dpw - WB Canal ---------------------------------------------------------------------------- | ACTIVITIES WITH NEW ACTUAL DATES EARLIER THAN TARGET DATE (10OCT02) | | ACT PROBLEM DATE TITLE | +---------- -------- ------- ----------------------------------------------+ |ADNLOCRV70 START = 20SEP02 Mob #1.1 (5% / 50%) | |ADNLOCRV71 START = 20SEP02 Mob #1.2 (5% / 50%) | |ADNLOCRV72 START = 20SEP02 Mob #1.3 (5% / 50%) | |ADNLOCRV73 START = 20SEP02 Mob #1.4 (5% / 50%) | |ADNLOCRV74 START = 20SEP02 Mob #1.5 (5% / 50%) | |ESREVWEL91 START = 21AUG02 LVCC, UL Panels, Transformer: Review & Approve| |ESSUBMEL45 START = 26SEP02 Seismic Anchoring Dwgs: Prep & Submit | |ESSUBMEL60 START = 03SEP02 Conduit Supports Cons'n Methods: Prep & Submit| |ESSUBMEL76 START = 01AUG02 Utility & Lighting Panel: Submit | |ESSUBMEL77 START = 01AUG02 Dry Type Transformer: Submit | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 30 cases of new activity actual dates earlier than Target data date. 0 cases of new activity actual dates later than Update data date. ---------------------------------------------------------------------------- | ACTIVITIES WITH MODIFIED ACTUAL DATES | | ACT PROBLEM DELAY TITLE | +---------- -------- ----- ------------------------------------------------+ |PCREVWTC32 AS => ES 130 Precast Panel Forms: Review | |PCSUBMTC30 AS => ES 133 Precast Panel Forms: Prep & Submit | |PCSUBMTC40 AS => ES 111 Precast Panel Integrated Shop Dwg: Prep & Submit| |SPREVWHG42 AS => ES 36 Circular Bearing QC Plan: Review (Caltrans) | |SPSUBMHG40 AF => EF 36 Circular Bearing QC Plan: Prep & Submit | ---------------------------------------------------------------------------- 5 activities had their actual dates revised. 0 Suspend or Resume dates exist. ---------------------------------------------------------------------------- | ACTIVITIES WITH ACTUAL STARTS AND NO PROGRESS | | ACT START DT % CMP TITLE | +---------- -------- ----- ------------------------------------------------+ |BPNLOCOE10 04NOV02 Onsite Batch Plant Mobilization | |FNFABRCD40 05NOV02 Wales: Fab/Deliver Pier 11>7 & Assemble On-Site | |FNFABRTP30 07OCT02 Pile Template #3: Fab | |FNP14EPL05 28OCT02 Pier 14/13E: Fab & Deliver Piles | |MSSUBMME42 10JUL02 Mech Product Data: Prep & Submit | |SPSUBMHG80 10JUL02 Pipe Beam: Proposed Bending Method: Conduct | |SSSUBMTW10 11SEP02 Temp Towers (A&B) Design 3E & 3W: Prep & Submit | ---------------------------------------------------------------------------- 7 activities had an Actual Start but no progress. 0 activities showed progress without an Actual Start Date. ---------------------------------------------------------------------------- | ACTIVE ACTIVITIES WITH NO PROGRESS | | ACT FLOAT Ty % CMP TITLE | +---------- ----- -- ----- ------------------------------------------------+ |MSREVWPR23 76 T 90 Headed Bar R/S QC Plan: Rereview | |PCREVWQC27 61 T 90 Precast Segment/Panel QC Plan: Rereview | |PCREVWQC52 735 T 90 Precast Fender Mod QC Plan: Review (Caltrans) | |PCREVWSC13 66 T 90 Seg Casting Sequence Plan: Re-Review (Caltrans) | ---------------------------------------------------------------------------- 4 active activities showed no progress this period. ---------------------------------------------------------------------------- | NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED | | ACT FLOAT Ty LATE TITLE | +---------- ----- -- ----- ------------------------------------------------+ |BPSUBMEN35 T 2 Pile Concrete Mix Design: Final Prep/Submit | |ESREVWEL91 T 31 Low Voltage Control Center: Review | |ESSUBMEL60 T 16 Conduit Supports Cons'n Methods: Prep & Submit | |ESSUBMEL76 T 9 Utility & Lighting Panel: Submit | |ESSUBMEL77 T 9 Dry Type Transformer: Submit | |ESSUBMEL87 T 3 Corrosion Monitor Working Dwgs: Resubmit | |ESSUBMEL91 T 10 Low Voltage Control Center: Submit | |FNFABRCD30 T 2 Wales: Fab & Deliver 3 each | |FNFABRFS20 T 4 Found'n Wood Box Mockup: Fab & Install | |FNFABRPL15 T 8 Pile Hammers: Purchase, Fab, Deliver & Assemble | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 22 newly completed activities had actual durations greater than planned. ---------------------------------------------------------------------------- | NEWLY COMPLETED ACTIVITIES WHICH FINISHED EARLIER THAN EXPECTED | | ACT PROBLEM EARLY TITLE | +---------- -------- ----- ------------------------------------------------+ |ADNLOCRV13 XF > AF TRO Months 7/8 | |ADNLOCRV70 XF > AF Mob #1.1 (5% / 50%) | |ADNLOCRV71 XF > AF Mob #1.2 (5% / 50%) | |ADNLOCRV72 XF > AF Mob #1.3 (5% / 50%) | |ADNLOCRV73 XF > AF Mob #1.4 (5% / 50%) | |ADNLOCRV74 XF > AF Mob #1.5 (5% / 50%) | |BPREVWEN27 XF > AF 5 NW Conc 1" Agg (Ftg) Mix Design: Review/Approve | |BPREVWEN37 XF > AF 9 Pile Concrete Mix Design: Review & Approve | |FNFABRCD10 XF > AF 3 Shoring: Fab & Deliver | |FNFABRCD20 XF > AF 1 Wales: Fab & Deliver 2 each | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 39 newly completed activities had durations equal (or better) than planned 61 activities have completed this period. Average duration of these activities was 56.05 Days. Mean of difference of planned/actual durations was 2.44 Days early. Standard Deviation of the difference was 13.11 Days. ---------------------------------------------------------------------------- | INCOMPLETED ACTIVITIES WITH DURATIONS DIFFERENT FROM PLANNED | | ACT FLOAT Ty LATE TITLE | +---------- ------ -- ---- ------------------------------------------------+ |BPNLOCOE10 61 T 10 Onsite Batch Plant Mobilization | |ESREVWEL88 82 T 11 Corrosion Monitor Working Dwgs: Rereview | |ESSUBMEL45 654 T 32 Seismic Anchoring Dwgs: Prep & Submit | |FNFABRCD40 121 T 24 Wales: Fab & Deliver 4 each | |FNFABRPL20 58 T 18 Bubble Curtain: Fab & Deliver | |FNFABRTP30 77 T 28 Pile Template #3: Fab | |FNP12ECD00 26 H 38 Pier 12E: Cofferdam (Summary) | |FNP13ECD00 28 H 34 Pier 13E: Cofferdam (Summary) | |FNP14ECD00 14 H 43 Pier 14E: Cofferdam (Summary) | |FNP14EPL05 56 T 33 Pier 14/13E: Fab & Deliver Piles | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 44 incompleted activities had their durations revised. 73 activities are currently active. ---------------------------------------------------------------------------- | PLANNED ACTIVITIES WITH CHANGED DURATIONS | | ACT PROBLEM LONGER TITLE | +---------- -------- ----- ------------------------------------------------+ |ESSUBMEL10 PLAN CHG 50 Traffic OS Equip: Submit | |ESSUBMEL20 PLAN CHG 30 Elec Service Platform Working Dwg: Prep & Submit| |ESSUBMEL25 PLAN CHG 50 Substation Metal Panel W'Dwg/Data: Prep & Submit| |ESSUBMEL40 PLAN CHG 50 Substation Metal Frame W'Dwg/Data: Prep & Submit| |ESSUBMEL50 PLAN CHG 50 Substation Finish Hdw Tech Info: Prep & Submit | |ESSUBMEL73 PLAN CHG 25 Boxes & Enclosures: Prep & Submit | |ESSUBMEL75 PLAN CHG 25 Conduit: Prep & Submit | |ESSUBMEL80 PLAN CHG 50 Rdwy Lighting Working Dwg: Prep & Submit | |FNFABRFS35 PLAN CHG -24 Footing 16 E: Transport | |FNFABRFS37 PLAN CHG -24 Footing 15 E: Transport | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 273 planned activities had their duration changed. Note: This report looks at workdays and not dates or durations. You may note an activity in this list that has the same Origional Duration, Remaining Duration, or even the same start and finish dates. This usually means that holidays or non-workdays have been inserted or deleted during the period this activity is planned to be active. Note: 'Unexplainable' discrepancies have also occurred because one of the two schedules being reviewed had been modified without re- running the CPM calculation. Be sure that the current dates reflect current calculations. ---------------------------------------------------------------------------- | ACTIVITIES WITH ODD TOTAL FLOAT CHANGE (GREATER THAN # OF DAYS OBSERVED) | | ACT PROBLEM CHNG TITLE | +---------- -------- ---- ------------------------------------------------+ |ADNLOCMS05 ODD FLOT -28 Turnover Oakland Access (500 days) | |ADNLOCMS25 ODD FLOT 58 Piles: Install'n Complete (KFM) | |ADNLOCMS30 ODD FLOT 65 Footings: Slabs Complete (KFM) | |ADNLOCMS35 ODD FLOT 53 Piers: Construct'n Complete (KFM) | |ADNLOCMS76 ODD FLOT -282 Annual SWPPP Renewal #2 | |ADNLOCMS77 ODD FLOT -648 Annual SWPPP Renewal #3 | |ADNLOCMS78 ODD FLOT 1013 Annual SWPPP Renewal #4 | |ADNLOCRV14 ODD FLOT -28 TRO Months 9/10 | |ADNLOCRV15 ODD FLOT -28 TRO Months 11/12 | |ADNLOCRV16 ODD FLOT -28 TRO Months 13/14 | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 1030 activities had an odd change in float. ---------------------------------------------------------------------------- | ACTIVITIES WITH CHANGED DESCRIPTIONS | | ACT PROBLEM FILE TITLE | +---------- -------- ---- ------------------------------------------------+ |ESREVWEL91 DESC CHG C2I2 Low Voltage Control Center: Review | | C2K0 LVCC, UL Panels, Transformer: Review & Approve | | | |FNFABRCD30 DESC CHG C2I2 Wales: Fab & Deliver 3 each | | C2K0 Wales: Fab & Deliver 14/13/12 & Assemble On-Site| | | |FNFABRCD40 DESC CHG C2I2 Wales: Fab & Deliver 4 each | | C2K0 Wales: Fab/Deliver Pier 11>7 & Assemble On-Site | | | |FNFABRFS35 DESC CHG C2I2 Footing 16 E: Transport | | C2K0 Footing 16 E: Transport from Texas to Pan Canal | | | |FNFABRFS37 DESC CHG C2I2 Footing 15 E: Transport | | C2K0 Footing 15 E: Transport from Texas to Pan Canal | | | |FNP03ECF40 DESC CHG C2I2 Pier 3E: Set Pile Cages/ Install Studs | | C2K0 Pier 3E: Pile - Set Cages | | | |FNP03ECF50 DESC CHG C2I2 Pier 3E: Pour Pile | | C2K0 Pier 3E: Piles - Pour Lift #1 | | | |FNP03EFC10 DESC CHG C2I2 Pier 3E: Pour Exterior Footing Box Cells (LWC) | | C2K0 Pier 3E: Ftg - Pour LWC Lift #1 | | | |FNP03WCF40 DESC CHG C2I2 Pier 3W: Set Pile Cages/ Install Studs | | C2K0 Pier 3W: Pile - Set Cages | | | |FNP03WCF50 DESC CHG C2I2 Pier 3W: Pour Pile | | C2K0 Pier 3W: Piles - Pour Lift #1 | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 107 activities had their description changed. 0 milestones changed into activities. 0 activities changed into milestones. ---------------------------------------------------------------------------- | MILESTONES WHICH DISPLAY VARIANCES | | ACT ID VARIANCE DESCRIPTION | +---------- -------------- ------------------------------------------------+ |ADNLOCMS25 MS DELAYED 85 Piles: Install'n Complete (KFM) | |ADNLOCMS30 MS DELAYED 92 Footings: Slabs Complete (KFM) | |ADNLOCMS35 MS DELAYED 81 Piers: Construct'n Complete (KFM) | |ADNLOCMS40 MS DELAYED 33 Hinges EB: Install'n Complete (KFM) | |ADNLOCMS45 MS DELAYED 37 Pier Tables: Construct'n Complete (KFM) | |ADNLOCMS50 MS DELAYED 33 Superstructures: Construct'n Complete (KFM) | |ADNLOCMS55 MS DELAYED 30 Closures: Construct'n Complete (KFM) | |ADNLOCMS60 MS DELAYED 31 Hinges WB: Install'n Complete (KFM) | |ADNLOCMS80 MS DELAYED 29 Drive on Access to EB | |ADNLOCMS99 MS DELAYED 28 KFM Substantially Complete | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 18 milestones showed variances. ============================== RELATIONSHIPS =============================== Target Project: C2I2 with 5980 relationships. Update Project: C2K0 with 6301 relationships. 0 Target File relationships are bogus. 0 Update File relationships are bogus. ---------------------------------------------------------------------------- | RELATIONSHIPS WHICH HAVE BEEN DELETED SINCE LAST UPDATE | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |ADNLOCMS74 ---------- ---- --- Start of On-Site Concrete Production | | FNP16EFS55 0 FS Pier 16E: Place Concrete Footing Lift #1 | | | |ADREVWEN33 ---------- ---- --- SWPPP Plan: BCDC Review | | ADNLOCMS99 0 FS KFM Substantially Complete | | | |ADREVWEN34 ---------- ---- --- SWPPP Plan: RWQCB Review | | ADNLOCMS99 0 FS KFM Substantially Complete | | | |ADSUBMEN20 ---------- ---- --- Submit Electronic Mobile Diary Equip & Pers| | ADNLOCMS99 0 FS KFM Substantially Complete | | | |BPREVWEN22 ---------- ---- --- 55 MPA Creep/Shrink Test (Pier Table): Revi| | SBSUBMTB02 0 FS Pier Table Demo Pour: Perform & Submit | | | |BPREVWEN27 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Review/App| | FNP16EFS55 0 FS Pier 16E: Place Concrete Footing Lift #1 | | | |BPREVWEN57 ---------- ---- --- NW Conc (Pier Table) Mix Design: Review & A| | SBSUBMTB02 0 FS Pier Table Demo Pour: Perform & Submit | | | |ESREVWEL21 ---------- ---- --- Substation Mat'l SOO: Review (Caltrans) | | ADNLOCMS99 0 FS KFM Substantially Complete | | | |ESREVWEL72 ---------- ---- --- Structural Grounding: Review (Caltrans) | | SBP16EPR12 0 FS Pier 16E: Set Pier Form Lift #1 | | | |ESREVWEL75 ---------- ---- --- Boxes & Enclosures: Review (Caltrans) | | FWF04EBR10 0 FS Frame 4E: Barrier | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 172 relationships have been deleted, 2 not listed because act. deleted. ---------------------------------------------------------------------------- | RELATIONSHIPS TO ACTIVITIES WHICH HAVE BEEN DELETED SINCE LAST UPDATE | | PRED ACT SUCC ACT LAG REL TITLE | :---------- ---------- ---- --- -------------------------------------------+ |PCC16ESC04 ---------- ---- --- Cant 16ED: Stress Transverse & Vertical P.T| | PCCB02SC30 0 FS Bed #2 Shutdown for Segment Storage Capacit| | | |PCCB02SC30 ---------- ---- --- Bed #2 Shutdown for Segment Storage Capacit| | PCC16WSC03 0 FS Cant 16WU: Cast Segments | | | ---------------------------------------------------------------------------- 2 relationships from deleted activities have been deleted. ---------------------------------------------------------------------------- | RELATIONSHIPS WHICH HAVE BEEN ADDED SINCE LAST UPDATE | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |ADNLOCMS74 ---------- ---- --- Start of On-Site Concrete Production | | FNP15EFS55 0 FS Pier 15E: Place Concrete Footing Lift #1 | | | |ADREVWEN33 ---------- ---- --- SWPPP Plan: BCDC Review | | FNNLOCDR40 0 FS Access Dredging: P11E - P16 E/W | | | |ADREVWEN34 ---------- ---- --- SWPPP Plan: RWQCB Review | | FNNLOCDR40 0 FS Access Dredging: P11E - P16 E/W | | | |ADSUBMEN20 ---------- ---- --- Submit Electronic Mobile Diary Equip & Pers| | ADNLOCMS15 0 FS Pre-Construction Schedule Mtg | | | |BPREVWEN22 ---------- ---- --- 55 MPA Creep/Shrink Test (Pier Table): Revi| | SBREVWTB04 0 FS Pier Table Demo Pour & TCP: Review & Appro| | | |BPREVWEN57 ---------- ---- --- NW Conc (Pier Table) Mix Design: Review & A| | SBREVWTB04 0 FS Pier Table Demo Pour & TCP: Review & Appro| | | |ESREVWEL21 ---------- ---- --- Substation Mat'l SOO: Review (Caltrans) | | ESS08EEL10 0 FS Span 8E: Install Electrical Substation | | | |ESREVWEL62 ---------- ---- --- Conduit Supports Cons'n Methods: Review | | PCCB01SC01 0 FS Cast Trial Segment 12EU1 | | | |ESREVWEL72 ---------- ---- --- Structural Grounding: Review (Caltrans) | | FNP16EFC30 0 FS Pier 16E: Pour & Cure Col Cell Lift #1 | | | |ESREVWEL75 ---------- ---- --- Boxes & Enclosures: Review (Caltrans) | | ESS08EEL10 0 FS Span 8E: Install Electrical Substation | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 493 relationships have been added, 412 not listed because act. was added. ---------------------------------------------------------------------------- | RELATIONSHIPS TO ACTIVITIES WHICH HAVE BEEN ADDED SINCE LAST UPDATE | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |BPREVWEN27 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Review/App| | BPSUBMEN28 0 FS NW Conc 1" Agg (Ftg) Mix Design: Resubmit | | | |BPREVWEN29 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Rereview | | FNP16EFS55 0 FS Pier 16E: Place Concrete Footing Lift #1 | | | |BPSUBMEN28 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Resubmit | | BPREVWEN29 0 FS NW Conc 1" Agg (Ftg) Mix Design: Rereview | | | |ESREVWEL02 ---------- ---- --- SCADA: Review & Approve | | ESS08EEL10 0 FS Span 8E: Install Electrical Substation | | | |ESREVWEL04 ---------- ---- --- LVCC, UL Panels, Transformer: Re-review | | ESS08EEL10 0 FS Span 8E: Install Electrical Substation | | | |ESREVWEL91 ---------- ---- --- LVCC, UL Panels, Transformer: Review & Appr| | ESSUBMEL03 0 FS LVCC, UL Panels, Transformer: Re-submit | | | |ESSUBMEL01 ---------- ---- --- SCADA: Prep & Submit | | ESREVWEL02 0 FS SCADA: Review & Approve | | | |ESSUBMEL03 ---------- ---- --- LVCC, UL Panels, Transformer: Re-submit | | ESREVWEL04 0 FS LVCC, UL Panels, Transformer: Re-review | | | |ESSUBMEL60 ---------- ---- --- Conduit Supports Cons'n Methods: Prep & Sub| | ESSUBMEL01 0 SS SCADA: Prep & Submit | | | |FNFABRFS20 ---------- ---- --- Found'n Wood Box Mockup: Fab & Install | | FNSUBMFS16 0 FS Pile Head Weld Procedure: Prep & Submit | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 412 relationships from added activities have been added. ---------------------------------------------------------------------------- | ACTIVITIES WITH MODIFIED RELATIONSHIPS | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |ESSUBMEL95 ----- OLD REL = FS Substation Electrical Information: Submit | | ESSUBMEL91 SS Low Voltage Control Center: Submit | | | |FNFABRFS40 ----- OLD REL = FS Footing 13 & 14 E: Subcontractor Complete F| | FNFABRFS50 SS Footing 9 thru 12 E: Sub Fab | | | |FNFABRTP20 ----- OLD REL = FS Pile Template #2: Fab | | FNFABRTP30 SS Pile Template #3: Fab | | | |FNP03ECF40 OLD LAG/R= 7/SS Pier 3E: Pile - Set Cages | | FNP03ECF50 0/FS Pier 3E: Piles - Pour Lift #1 | | | |FNP03EFC10 OLD LAG/R= 1/SS Pier 3E: Ftg - Pour LWC Lift #1 | | FNP03ECF40 0/FS Pier 3E: Pile - Set Cages | | | |FNP03WCF40 OLD LAG/R= 7/SS Pier 3W: Pile - Set Cages | | FNP03WCF50 0/FS Pier 3W: Piles - Pour Lift #1 | | | |FNP03WFC10 OLD LAG/R= 1/SS Pier 3W: Ftg - Pour LWC Lift #1 | | FNP03WCF40 0/FS Pier 3W: Pile - Set Cages | | | |FNP04ECF40 OLD LAG/R= 7/SS Pier 4E: Pile - Set Cages | | FNP04ECF50 0/FS Pier 4E: Piles - Pour Lift #1 | | | |FNP04EFC10 OLD LAG/R= 1/SS Pier 4E: Ftg - Pour LWC Lift #1 | | FNP04ECF40 0/FS Pier 4E: Pile - Set Cages | | | |FNP04WCF40 OLD LAG/R= 7/SS Pier 4W: Pile - Set Cages | | FNP04WCF50 0/FS Pier 4W: Piles - Pour Lift #1 | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 60 relationships have been modified. 0 activities have been orphaned. ---------------------------------------------------------------------------- | RELATIONSHIPS WITH MODIFIED LAG DURATIONS | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |ADNLOCMS10 OLD LAG = 250 Notice to Proceed | | FNSUBMPF10 450 FS RRP/CP Lumber Working Dwg: Prep & Submit | | | |ADNLOCMS10 OLD LAG = 320 Notice to Proceed | | FWSUBMCN10 0 FS Cormorant Nesting Working Dwgs: Prep & Subm| | | |ADNLOCMS10 OLD LAG = 257 Notice to Proceed | | SBSUBMAC10 300 FS Pier Casing Falsework: Prep & Submit | | | |ADNLOCMS10 OLD LAG = 205 Notice to Proceed | | SSSUBMSG50 0 FS SS Fab Proc Ortho Box Shell Plate: Prep & S| | | |ADNLOCMS10 OLD LAG = 205 Notice to Proceed | | SSSUBMSG60 0 FS SS Fab Procedure Ortho Box: Prep & Submit | | | |ESSUBMEL95 OLD LAG = 25 Substation Electrical Information: Submit | | ESSUBMEL45 0 SS Seismic Anchoring Dwgs: Prep & Submit | | | |MBSFB1MB23 OLD LAG = 21 DB Oakland: Mobilize | | FNP16ECD25 0 FS Pier 16E: Place Locking Fill | | | |MBSFB1MB30 OLD LAG = 5 DB Vancouver: Mobilize | | FNP16ECD10 0 FS Pier 16E: Drive Sheets/Access Platforms | | | |MBSFB1MB35 OLD LAG = 20 Catamaran Barge: Mobilize | | FNP16EFS30 0 FS Pier 16E: Align, Set & Secure Footing Box | | | |MBSFB1MB40 OLD LAG = 20 DB Bremerton: Mobilize | | FNP16EFS20 0 FS Pier 16E: Dewater Cell to Top of Box | | | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 13 relationship lags changed. 0 relationship chains are interruptible. 0 Activities are missing Finish Relationships. ================================ CONSTRAINTS =============================== 0 Target File constraints are bogus. 0 Update File constraints are bogus. ---------------------------------------------------------------------------- | CONSTRAINTS WHICH HAVE BEEN DELETED SINCE LAST UPDATE | | ACT C-TYPE DATE TITLE | +---------- ------ ------- ------------------------------------------------+ |ADNLOCMS76 SNET 15JUL03 Annual SWPPP Renewal #2 | |ADNLOCMS77 SNET 15JUL04 Annual SWPPP Renewal #3 | |ADNLOCMS78 SNET 15JUL05 Annual SWPPP Renewal #4 | |ADNLOCMS99 FNLT 4AUG06 KFM Substantially Complete | |ADNLOCRV70 SNET 1OCT02 Mob #1.1 (5% / 50%) | |ADNLOCRV75 SNET 1JAN03 Mob #2.1 (10% / 75%) | |ADNLOCRV78 SNET 1MAY03 Mob #3.1 (20% / 95%) | |ADNLOCRV80 SNET 1FEB04 Mob #4 (50% / 100%) | |MSSUBMSN10 SNET 1JAN03 Sign Structure Working Dwg: Prep & Submit | ---------------------------------------------------------------------------- 9 constraints have been deleted. 0 constraints have been added. 0 constraints have been modified. 0 constraint dates have been modified. 0 Expected Finish dates are out of date. ================================ COST CHECKS =============================== Section skipped due to no cost entries ================================ LOG CHECKS ================================ 0 new log records were found in 0 activities. 0 old log records were deleted in 0 activities. 0 log records were modified in 0 activities. =========================== HIGHER LEVEL REPORTS =========================== ---------------------------------------------------------------------------- | MILESTONES AWAITING STATUS | | ACT ID TYPE FLOAT DESCRIPTION | +---------- -------- ----- ------------------------------------------------+ |ADNLOCMS35 FINISH 117 Piers: Construct'n Complete (KFM) | |ADNLOCMS40 FINISH 211 Hinges EB: Install'n Complete (KFM) | |ADNLOCMS45 FINISH 151 Pier Tables: Construct'n Complete (KFM) | |ADNLOCMS50 FINISH 102 Superstructures: Construct'n Complete (KFM) | |ADNLOCMS55 FINISH 64 Closures: Construct'n Complete (KFM) | |ADNLOCMS60 FINISH 60 Hinges WB: Install'n Complete (KFM) | |ADNLOCMS76 START 1399 Annual SWPPP Renewal #2 | |ADNLOCMS77 START 1399 Annual SWPPP Renewal #3 | |ADNLOCMS78 START 1399 Annual SWPPP Renewal #4 | |ADNLOCMS80 FINISH 17 Drive on Access to EB | | ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** | ---------------------------------------------------------------------------- 12 milestones are awaiting status. ---------------------------------------------------------------------------- | ACTIVITIES VIOLATING DUE DILIGENCE | | ACT PROBLEM LATE T-TF TITLE | +---------- -------- ---- ---- --------------------------------------------+ |BPNLOCOE10 LATE STR 48 35 Onsite Batch Plant Mobilization | |ESSUBMEL01 LATE STR 1 SCADA: Prep & Submit | |FNFABRTP30 LATE STR 2 19 Pile Template #3: Fab | |FNP13ECD05 LATE STR 2 72 Pier 13E: Install Wale System | |FNSUBMCD30 LATE STR 27 25 Cofferdam Dewatering Submittal | |SBSUBMPS18 LATE STR 43 PIER STAIRS: RESOLVE DISCREPENCIES | |SSREVWQC17 LATE STR 1 190 Steel QC Caltrans Audit: Conduct (Caltrans) | ---------------------------------------------------------------------------- 7 activities started late this period. The Mean of the late starts are 18 Days late. The Standard Deviation of the difference is 21 Days. ---------------------------------------------------------------------------- | ACTIVITIES WHICH STARTED EARLIER THAN PLANNED | | ACT PROBLEM EARLY T-TF TITLE | +---------- -------- ---- ---- --------------------------------------------+ |ADNLOCRV71 EARLY ST 1 872 Mob #1.2 (5% / 50%) | |ADNLOCRV72 EARLY ST 1 872 Mob #1.3 (5% / 50%) | |ADNLOCRV73 EARLY ST 1 872 Mob #1.4 (5% / 50%) | |ADNLOCRV74 EARLY ST 1 872 Mob #1.5 (5% / 50%) | |ESSUBMEL45 EARLY ST 14 623 Seismic Anchoring Dwgs: Prep & Submit | |PCPRECPC16 EARLY ST 6 31 Setup & Test Batch Plant | ---------------------------------------------------------------------------- 6 activities started earlier than planned this period. The Mean of the early starts are 94 Days late. The Standard Deviation of the difference is 43 Days. Critical Total Float for the Target project is 0. Critical Total Float for the Update project is 0. Critical Float Changed: 0 The Target File Had 39 critical activities. The Update File Had 64 critical activities. ---------------------------------------------------------------------------- | MOST CRITICAL LIST OF ACTIVITIIES (CHANGE 'd' IN WORK DAYS THIS PERIOD) | | TARGET UPDATE dES dEF dAS dAF DESCRIPTION | +---------- ---------- --- --- --- --- ------------------------------------+ |PCFABRSC20 PCFABRSC20 0 -29 0 Segment Beds: Procure, Fab & Deliver| | ** FS rel to Act PCFABRSC24 added **| | PCFABRSC24(activity added) SEG BEDS: DELIVER (PARTIAL) | | ** New critical activity added ** | | ** FS rel to Act PCCB01SC99 added **| |PCCB01SC99 PCCB01SC99 27 27 Assemble Segment Bed #1 | |PCCB02SC21 27 27 Assemble Segment Bed #2 | |PCCB03SC99 27 27 Assemble Segment Bed #3 | |PCC12ESC02 21 21 Cant 12ED: Cast Segments | |PCC11ESC02 21 21 Cant 11ED: Cast Segments | |PCF02EME10 PCF02EME10 32 32 Frame 2E: Mech Staging (Summary) | |PCC10ESC02 21 21 Cant 10ED: Cast Segments | |PCC09ESC02 21 21 Cant 9ED: Cast Segments | |PCF02WME10 PCF02WME10 32 32 Frame 2W: Mech Staging (Summary) | |PCC11WSC03 PCC11WSC03 32 32 Cant 11WU: Cast Segments | |PCC08ESC02 PCC08ESC02 32 32 Cant 8ED: Cast Segments | |PCC12WSC03 PCC12WSC03 32 32 Cant 12WU: Cast Segments | |PCF01EME10 PCF01EME10 34 32 Frame 1E: Mech Staging (Summary) | | ** Origional Duration modified ** | | ** Duration modified before started | |PCC07ESC02 PCC07ESC02 32 32 Cant 7ED: Cast Segments | |PCC06ESC02 PCC06ESC02 32 32 Cant 6ED: Cast Segments | |PCC05ESC02 PCC05ESC02 32 32 Cant 5ED: Cast Segments | |PCC04ESC02 PCC04ESC02 32 32 Cant 4ED: Cast Segments | |PCC03ESC02 PCC03ESC02 32 32 Cant 3ED: Cast Segments | |PCC03ESC03 PCC03ESC03 32 32 Cant 3EU: Cast Segments | |PCC10WSC03 PCC10WSC03 32 32 Cant 10WU: Cast Segments | |PCC09WSC03 PCC09WSC03 32 32 Cant 9WU: Cast Segments | |PCC08WSC03 PCC08WSC03 32 32 Cant 8WU: Cast Segments | |PCC07WSC03 PCC07WSC03 32 32 Cant 7WU: Cast Segments | |SPC07WSG00 SPC07WSG00 33 28 Cant. 7W: SLED (Summary) | | ** Origional Duration modified ** | | ** Duration modified before started | |ESF02WEL10 ESF02WEL10 28 28 Frame 2W: Cable Tray & Conduit | |SPC07WSG60 SPC07WSG60 28 28 Cant 7W: Erect Segments 2E/W thru 9E| | SPC05WSG10 28 28 Cant 5W: Erect SLED (Up/Down) | | SPC05WSG00 28 28 Cant. 5W: SLED (Summary) | | SPC05WSG20 28 28 Cant 5W: Erect Segments 1E/1W | | SPC05WSG30 28 28 Cant 5W: Cast Wet Joint & Cure | | SPC05WSG40 28 28 Cant 5W: Install & Stress Cant. Tend| | SPC05WSG60 28 28 Cant 5W: Erect Segments 2E/W thru 9E| | SSF01WTW20 28 28 San Francisco Tower BW: Erect Temp T| | SPC03WSG10 28 28 Cant 3W: Erect SLED (Up/Down) | | SPC03WSG20 28 28 Cant 3W: Erect Segments 1E/1W | | SPC03WSG00 28 28 Cant. 3W: SLED (Summary) | | SPC03WSG30 28 28 Cant 3W: Cast Wet Joint & Cure | | SSF01WTW10 28 28 San Francisco Tower AW: Erect Temp T| | SPC03WSG40 28 28 Cant 3W: Install & Stress Cant. Tend| | SPF01WCL00 28 29 Frame 1W: Closure (Summary) | | ** Origional Duration modified ** | | ** Duration modified before started | | SPC03WSG60 28 28 Cant 3W: Erect Segments 2E/W thru 5E| | SSS03WSG10 28 28 Erect Transition Span Steel W | | SPF01WPT00 28 29 Frame 1W: Post Tensioning (Summary) | | ** Origional Duration modified ** | | ** Duration modified before started | | SPF01WHG10 28 28 Hinge AW: Lift & Secure pipe | | SPS03WCL10 28 28 Span 3W: Complete Closure to Steel | | SPC03WSG70 28 28 Cant 3W: Erect Segments 6E thru 9E | | SSS03WSG20 28 28 Span 3W: Lower Transition Span Tip | | SPS04WCL10 28 28 Span 4W: Complete Exterior Closure | | SPF01WCL10 28 28 Frame 1W: Align & Jack | | SPF01WCL20 28 28 Frame 1W: Install Resteel & Pour Clo| | SPF01WHG63 32 32 Hinge AW Pipe Beam: Deliver | |ESF02WEL42 ESF02WEL42 28 28 Frame 2W: Pre-Pour Rough Barrier Ele| | SPS05WPT10 29 29 Span 5W: Stress & Grout Span Tendons| | SPS03WPT10 29 29 Span 3W: Stress & Grout Span Tendons| | SPS07WPT12 29 29 Span 7WW: Stress & Grout Span Tendon| | SPS07WHG20 29 29 Hinge BW: Align Pipe Beams & Grout B| | SPF01WPT20 29 29 Frame 1W: Stress Continuity Tendons | |ESF02WEL45 ESF02WEL45 28 28 Frame 2W: Barrier Electrical | |FWF02WBR10 FWF02WBR10 28 28 Frame 2W: Barrier | |ESF01WEL45 ESF01WEL45 28 28 Frame 1W: Barrier Electrical | |FWF01WBR10 FWF01WBR10 28 28 Frame 1W: Barrier | |ESF01WEL30 ESF01WEL30 28 28 Frame 1W: Wire & Devices | |ESF01WEL70 ESF01WEL70 28 28 Frame 1W: Roadway Level Electrical T| |ESF01WEL60 ESF01WEL60 28 28 Frame 1W: Roadway Lighting | |ESNLOCEL20 ESNLOCEL20 28 28 Electrical Testing WB | |FWNLOCPU10 FWNLOCPU10 28 28 Punchlist Roadway Surface | |ADNLOCMS99 ADNLOCMS99 28 KFM Substantially Complete | |PCP07WAR25 PCP07WAR25 44 44 Pier 7W: Segment Age Restriction 6 m| | SPF01WCL25 43 43 Frame 1W: Cure Interior Closure | ---------------------------------------------------------------------------- ============================== END OF REPORT =============================== Analysis complete at 09:14:36.