Schedule Analyzer Professional

Copyright Ron Winter 2002

Sample Update Checker Report - Lists Have Been Trimmed to 10 Activities


                             SCHEDULE ANALYZER
                       ============================
                       |        Version 2.78      |
                       ============================
                 Copyright Ron Winter Consulting LLC 1994/2003

 This report was prepared by Ron Winter Consulting LLC.

 Target Project: C2I2                  Analysis Date: 07-02-2003 at 09:07:40
 Update Project: C2K0

 November Update                     

Project Completion Date checked.
 Analysis covers project status update from 10OCT02 to 17NOV02.

********************************************************
* CALENDAR ADDED :  Calendar # E 7dpw - WB Canal       *
********************************************************


****************************************************************************
*                    CALENDARS WHICH HAVE BEEN CHANGED                     *
*------------------------------------+-------------------------------------*
*     DELETED FROM PROJECT C2I2      |       ADDED TO PROJECT C2K0         *
*  CAL   TYPE      START   TO    END |  CAL   TYPE      START   TO     END *
*------------------------------------+-------------------------------------*
*   1   HOLIDAY   25NOV00  TO 26NOV00|   1   HOLIDAY   25NOV00             *
*                                    |   1   HOLIDAY   23NOV01             *
*   1   HOLIDAY   30NOV01            |                                     *
*                                    |   E      WORK    1JAN               *
*                                    |   E      WORK    4JUL               *
*                                    |   E      WORK   25DEC               *
*                                    |   E      WORK   11NOV00             *
*                                    |   E      WORK   11NOV01             *
*                                    |   E      WORK   21JAN02             *
*                                    |   E      WORK   12FEB02             *
*                                    |   E      WORK   18FEB02             *
*                                    |   E      WORK   31MAR02             *
*                                    |   E      WORK   27MAY02             *
*                                    |   E      WORK    2SEP02             *
*                                    |   E      WORK    9SEP02             *
*                                    |   E      WORK   14OCT02             *
*                                    |   E      WORK   11NOV02             *
*                                    |   E      WORK   28NOV02             *
*                                    |   E      WORK   29NOV02             *
*                                    |   E      WORK   20JAN03             *
*                                    |   E      WORK   12FEB03             *
*                                    |   E      WORK   17FEB03             *
*                                    |   E      WORK   31MAR03             *
*                                    |   E      WORK   26MAY03             *
*                                    |   E      WORK    1SEP03             *
*                                    |   E      WORK    9SEP03             *
*                                    |   E      WORK   13OCT03             *
*                                    |   E      WORK   11NOV03             *
*                                    |   E      WORK   27NOV03             *
*                                    |   E      WORK   28NOV03             *
*                                    |   E      WORK   19JAN04             *
*                                    |   E      WORK   12FEB04             *
*                                    |   E      WORK   16FEB04             *
*                                    |   E      WORK   31MAR04             *
*                                    |   E      WORK   31MAY04             *
*                                    |   E      WORK    6SEP04             *
*                                    |   E      WORK    9SEP04             *
*                                    |   E      WORK   11OCT04             *
*                                    |   E      WORK   11NOV04             *
*                                    |   E      WORK   25NOV04             *
*                                    |   E      WORK   26NOV04             *
*                                    |   E      WORK   17JAN05             *
*                                    |   E      WORK   12FEB05             *
*                                    |   E      WORK   21FEB05             *
*                                    |   E      WORK   31MAR05             *
*                                    |   E      WORK   30MAY05             *
*                                    |   E      WORK    5SEP05             *
*                                    |   E      WORK    9SEP05             *
*                                    |   E      WORK   10OCT05             *
*                                    |   E      WORK   11NOV05             *
*                                    |   E      WORK   24NOV05             *
*                                    |   E      WORK   25NOV05             *
*                                    |   E      WORK   16JAN06             *
*                                    |   E      WORK   12FEB06             *
*                                    |   E      WORK   20FEB06             *
*                                    |   E      WORK   31MAR06             *
*                                    |   E      WORK   29MAY06             *
*                                    |   E      WORK    4SEP06             *
*                                    |   E      WORK    9SEP06             *
*                                    |   E      WORK   11NOV06             *
*                                    |   E      WORK   23NOV06             *
*                                    |   E      WORK   24NOV06             *
*                                    |   E      WORK   12FEB07             *
*                                    |   E      WORK   31MAR07             *
*                                    |   E      WORK    9SEP07             *
*------------------------------------+-------------------------------------*
*        2 HOLIDAYS WERE DELETED     |       64 HOLIDAYS WERE ADDED        *
****************************************************************************

 Project Rules check okay.
 Scheduling Method checks.
 Types of Activity Scheduling Method checks.
 Total Float Calculation checks.

================================ ACTIVITIES ================================

 0 Target File activities are bogus.
 0 Update File activities are bogus.

 Target Project C2I2 with 3963 activities.  Data Date = 10OCT02
 Update Project C2K0 with 4196 activities.  Data Date = 17NOV02

 0 As-Built activities have been deleted out of 1 total deleted.
 0 In-Progress activities have been deleted out of 1 total deleted.

----------------------------------------------------------------------------
| PLANNED ACTIVITIES WHICH HAVE BEEN DELETED SINCE LAST UPDATE             |
| ACT       PROBLEM  FLOAT  TITLE                                          |
:---------- -------- ----- ------------------------------------------------+
|PCCB02SC30 DELETED     47 Bed #2 Shutdown for Segment Storage Capacity    |
----------------------------------------------------------------------------
 1 Planned activity has been deleted out of 1 total deleted.

----------------------------------------------------------------------------
| NEW AS-BUILT ACTIVITIES ADDED SINCE LAST UPDATE                          |
| ACT       PROBLEM  FLOAT  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|BPSUBMEN28 NEW ACT     60 NW Conc 1" Agg (Ftg) Mix Design: Resubmit       |
|ESSUBMEL01 NEW ACT   1051 SCADA: Prep & Submit                            |
|FNFABRPL11 NEW ACT     59 HAMMER FOLLOWER/ACCES.: LABOR DISPUTE           |
|FNREVWPL39 NEW ACT     70 Bubble Curtain (Energy Attenuator): Rereview III|
|FNSUBMFS16 NEW ACT     87 Pile Head Weld Procedure: Prep & Submit         |
|FNSUBMPL37 NEW ACT     58 Bubble Curtain (Energy Attenuator): Resubmit III|
|FNSUBMPL45 NEW ACT     70 Bubble Curtain (Energy Attenuator): Resubmit IV |
|FWSUBMMJ22 NEW ACT    275 Mod Joint Seal Working Dwgs: Resubmit III       |
|PCFABRSC23 NEW ACT      0 SEG BEDS: LONGSHOREMAN LABOR DISPUTE            |
|PCREVWPN32 NEW ACT     44 Segment Panels: Precast Forms: Review & Approve |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 24 As-Built activities have been added out of 234 total added.
    CAUTION:  The float values printed above were obtained by noting the
        lowest float of all immediate, active successor activities.  This
        does not mean that the float presented here was the activity's
        actual float, only that it is unlikely that the actual float was
        less than that shown.

----------------------------------------------------------------------------
| NEW IN-PROGRESS ACTIVITIES ADDED SINCE LAST UPDATE                       |
| ACT       PROBLEM  FLOAT  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|BPREVWEN29 NEW ACT     60 NW Conc 1" Agg (Ftg) Mix Design: Rereview       |
|ESREVWEL02 NEW ACT   1051 SCADA: Review & Approve                         |
|ESSUBMEL03 NEW ACT    658 LVCC, UL Panels, Transformer: Re-submit         |
|FNFABRFS31 NEW ACT     14 Ftg 16E: Fabrication: Inclement Weather         |
|FNFABRFS33 NEW ACT     89 Ftg 15E: Fabrication: Inclement Weather         |
|FNFABRPL12 NEW ACT     59 HAMMER FOLLOWER/ACCES.: LOCATE/DELIVER          |
|FNREVWFS18 NEW ACT     87 Pile Head Weld Procedure: Review & Approve      |
|FNREVWPL47 NEW ACT     70 Bubble Curtain (Energy Attenuator): Rereview IV |
|FNSUBMFC21 NEW ACT     55 Pile Cap Thermal Control Plan: Resubmit         |
|FWREVWMJ22 NEW ACT    275 Mod Joint Seal Working Dwgs: Rereview III       |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 25 In-Progress activities have been added out of 234 total added.

----------------------------------------------------------------------------
| NEW PLANNED ACTIVITIES ADDED SINCE LAST UPDATE                           |
| ACT       PROBLEM  FLOAT  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|ESREVWEL04 NEW ACT    658 LVCC, UL Panels, Transformer: Re-review         |
|FNFABRFS36 NEW ACT     14 Footing 16E: Transit through Panama Canal       |
|FNFABRFS38 NEW ACT     89 Footing 15E: Transit through Panama Canal       |
|FNFABRFS41 NEW ACT     14 Footing 16E: Transport from Canal to Oakland    |
|FNFABRFS43 NEW ACT     89 Footing 15E: Transport from Canal to Oakland    |
|FNFABRFS44 NEW ACT     56 Ftg 14E & 13E: Fabrication: Inclement Weather   |
|FNFABRPF40 NEW ACT    622 RRP/CP Lumber: Procure/Fab/Deliver              |
|FNP03ECF45 NEW ACT    128 Pier 3E: Pile - Install Studs                   |
|FNP03ECF55 NEW ACT    128 Pier 3E: Piles - Pour Lift #2                   |
|FNP03EFC12 NEW ACT    136 Pier 3E: Ftg - Pour LWC Lift #2                 |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 185 Planned activities have been added out of 234 total added.
 0 activities had their Activity Types revised.

----------------------------------------------------------------------------
| ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS                              |
| ACT       Ty OLD D NEW D  TITLE                                          |
+---------- -- ----- ----- ------------------------------------------------+
|ESREVWEL32  T    21    30 Elec Substation Sealant: Review (Caltrans       |
|ESREVWEL42  T    21    30 Substation Metal Frame W'Dwg/Data: Review       |
|ESREVWEL52  T    21    30 Substation Finish Hdw Tech Info: Review         |
|ESREVWEL96  T    10    30 Substation Electric Information: Reiew & Approve|
|ESSUBMEL10  T    20    70 Traffic OS Equip: Submit                        |
|ESSUBMEL20  T    40    70 Elec Service Platform Working Dwg: Prep & Submit|
|ESSUBMEL25  T    20    70 Substation Metal Panel W'Dwg/Data: Prep & Submit|
|ESSUBMEL40  T    20    70 Substation Metal Frame W'Dwg/Data: Prep & Submit|
|ESSUBMEL50  T    20    70 Substation Finish Hdw Tech Info: Prep & Submit  |
|ESSUBMEL60  T    20    70 Conduit Supports Cons'n Methods: Prep & Submit  |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 318 activities had their Original Durations revised.
    NOTE: Original Durations will automatically change if the activity is a
        Hammock or WBS or if Expected Finish constraint is used.

----------------------------------------------------------------------------
| ACTIVITIES WITH NEW CALENDARS                                            |
| ACT       OLD CAL  NEW C  TITLE                                          |
+---------- -------  ----- ------------------------------------------------+
|ESREVWEL21    1       A   Substation Mat'l SOO: Review (Caltrans)         |
|ESREVWEL32    1       A   Elec Substation Sealant: Review (Caltrans)      |
|ESREVWEL42    1       A   Substation Metal Frame W'Dwg/Data: Review       |
|ESREVWEL52    1       A   Substation Finish Hdw Tech Info: Review         |
|ESREVWEL96    1       A   Substation Electric Information: Reiew & Approve|
|FNFABRFS50    1       E   Footing 9 thru 12 E: Sub Fab                    |
|FNFABRFS60    1       E   Footing 5 thru 8 E: Sub Fab                     |
|FNFABRFS70    1       E   Footing 3 & 4E, 15 & 16W: Sub Fab               |
|FNFABRFS80    1       E   Footing 9 thru 14W: Sub Fab                     |
|FNFABRFS90    1       E   Footing 3 thru 8W: Sub Fab                      |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 38 activities had their calendars changed.
    Key to Calendars:
        Calendar 1 5 dpw 
        Calendar 2 5 dpw 
        Calendar 3 5 dpw 
        Calendar 4 5 dpw 
        Calendar 5 6 dpw 
        Calendar 6 6 dpw 
        Calendar 7 6 dpw 
        Calendar 8 6 dpw 
        Calendar 9 7 dpw 
        Calendar A 7 dpw 
        Calendar B 7 dpw 
        Calendar C 7 dpw 
        Calendar D 7 dpw 
        Calendar E 7dpw - WB Canal 

----------------------------------------------------------------------------
| ACTIVITIES ON THE LONGEST PATH                                           |
| ACT       CALENDAR FLOAT  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|PCFABRSC20    2           Segment Beds: Procure, Fab & Deliver (Partial)  |
|PCFABRSC23    A           SEG BEDS: LONGSHOREMAN LABOR DISPUTE            |
|PCFABRSC24    2         0 SEG BEDS: DELIVER (PARTIAL)                     |
|PCCB01SC99    2         0 Assemble Segment Bed #1                         |
|PCCB01SC01    1         1 Cast Trial Segment 12EU1                        |
|PCCB01SC03    2         1 Segment 12EU1: Stress Transverse & Vertical P.T.|
|PCCB01SC05    2         1 Segment 12EU1: Grout P.T.                       |
|PCCB01SC07    2         1 Approve Trial Segment                           |
|PCC12ESC03    1         1 Cant 12EU: Cast Segments                        |
|PCC12ESC02    1         1 Cant 12ED: Cast Segments                        |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 68 activities were on the Longest Path.
    NOTE: The most crtical float for this project is 0.
    CAUTION: Some of the activities on the above Longest Path have different
        calendars from the others.  This will often cause the Total Float
        value to be dissimilar.  This is normal.  Float values should be the
        same for activities with the same calendar.  If not, then look for
        constraints at the changes.
    Key to Calendars:
        Calendar 1 5 dpw 
        Calendar 2 5 dpw 
        Calendar 3 5 dpw 
        Calendar 4 5 dpw 
        Calendar 5 6 dpw 
        Calendar 6 6 dpw 
        Calendar 7 6 dpw 
        Calendar 8 6 dpw 
        Calendar 9 7 dpw 
        Calendar A 7 dpw 
        Calendar B 7 dpw 
        Calendar C 7 dpw 
        Calendar D 7 dpw 
        Calendar E 7dpw - WB Canal 

----------------------------------------------------------------------------
| ACTIVITIES WITH NEW ACTUAL DATES EARLIER THAN TARGET DATE (10OCT02)      |
| ACT       PROBLEM   DATE   TITLE                                         |
+---------- -------- ------- ----------------------------------------------+
|ADNLOCRV70  START = 20SEP02 Mob #1.1 (5% / 50%)                           |
|ADNLOCRV71  START = 20SEP02 Mob #1.2 (5% / 50%)                           |
|ADNLOCRV72  START = 20SEP02 Mob #1.3 (5% / 50%)                           |
|ADNLOCRV73  START = 20SEP02 Mob #1.4 (5% / 50%)                           |
|ADNLOCRV74  START = 20SEP02 Mob #1.5 (5% / 50%)                           |
|ESREVWEL91  START = 21AUG02 LVCC, UL Panels, Transformer: Review & Approve|
|ESSUBMEL45  START = 26SEP02 Seismic Anchoring Dwgs: Prep & Submit         |
|ESSUBMEL60  START = 03SEP02 Conduit Supports Cons'n Methods: Prep & Submit|
|ESSUBMEL76  START = 01AUG02 Utility & Lighting Panel: Submit              |
|ESSUBMEL77  START = 01AUG02 Dry Type Transformer: Submit                  |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 30 cases of new activity actual dates earlier than Target data date.
 0 cases of new activity actual dates later than Update data date.

----------------------------------------------------------------------------
| ACTIVITIES WITH MODIFIED ACTUAL DATES                                    |
| ACT       PROBLEM  DELAY  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|PCREVWTC32 AS => ES   130 Precast Panel Forms: Review                     |
|PCSUBMTC30 AS => ES   133 Precast Panel Forms: Prep & Submit              |
|PCSUBMTC40 AS => ES   111 Precast Panel Integrated Shop Dwg: Prep & Submit|
|SPREVWHG42 AS => ES    36 Circular Bearing QC Plan: Review (Caltrans)     |
|SPSUBMHG40 AF => EF    36 Circular Bearing QC Plan: Prep & Submit         |
----------------------------------------------------------------------------
 5 activities had their actual dates revised.
 0 Suspend or Resume dates exist.

----------------------------------------------------------------------------
| ACTIVITIES WITH ACTUAL STARTS AND NO PROGRESS                            |
| ACT       START DT % CMP  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|BPNLOCOE10  04NOV02       Onsite Batch Plant Mobilization                 |
|FNFABRCD40  05NOV02       Wales: Fab/Deliver Pier 11>7 & Assemble On-Site |
|FNFABRTP30  07OCT02       Pile Template #3: Fab                           |
|FNP14EPL05  28OCT02       Pier 14/13E: Fab & Deliver Piles                |
|MSSUBMME42  10JUL02       Mech Product Data: Prep & Submit                |
|SPSUBMHG80  10JUL02       Pipe Beam: Proposed Bending Method: Conduct     |
|SSSUBMTW10  11SEP02       Temp Towers (A&B) Design 3E & 3W: Prep & Submit |
----------------------------------------------------------------------------
 7 activities had an Actual Start but no progress.
 0 activities showed progress without an Actual Start Date.

----------------------------------------------------------------------------
| ACTIVE ACTIVITIES WITH NO PROGRESS                                       |
| ACT       FLOAT Ty % CMP  TITLE                                          |
+---------- ----- -- ----- ------------------------------------------------+
|MSREVWPR23    76  T    90 Headed Bar R/S QC Plan: Rereview                |
|PCREVWQC27    61  T    90 Precast Segment/Panel QC Plan: Rereview         |
|PCREVWQC52   735  T    90 Precast Fender Mod QC Plan: Review (Caltrans)   |
|PCREVWSC13    66  T    90 Seg Casting Sequence Plan: Re-Review (Caltrans) |
----------------------------------------------------------------------------
 4 active activities showed no progress this period.

----------------------------------------------------------------------------
| NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED            |
| ACT       FLOAT Ty  LATE  TITLE                                          |
+---------- ----- -- ----- ------------------------------------------------+
|BPSUBMEN35        T     2 Pile Concrete Mix Design: Final Prep/Submit     |
|ESREVWEL91        T    31 Low Voltage Control Center: Review              |
|ESSUBMEL60        T    16 Conduit Supports Cons'n Methods: Prep & Submit  |
|ESSUBMEL76        T     9 Utility & Lighting Panel: Submit                |
|ESSUBMEL77        T     9 Dry Type Transformer: Submit                    |
|ESSUBMEL87        T     3 Corrosion Monitor Working Dwgs: Resubmit        |
|ESSUBMEL91        T    10 Low Voltage Control Center: Submit              |
|FNFABRCD30        T     2 Wales: Fab & Deliver 3 each                     |
|FNFABRFS20        T     4 Found'n Wood Box Mockup: Fab & Install          |
|FNFABRPL15        T     8 Pile Hammers: Purchase, Fab, Deliver & Assemble |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 22 newly completed activities had actual durations greater than planned.

----------------------------------------------------------------------------
| NEWLY COMPLETED ACTIVITIES WHICH FINISHED EARLIER THAN EXPECTED          |
| ACT       PROBLEM  EARLY  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|ADNLOCRV13 XF  > AF       TRO Months 7/8                                  |
|ADNLOCRV70 XF  > AF       Mob #1.1 (5% / 50%)                             |
|ADNLOCRV71 XF  > AF       Mob #1.2 (5% / 50%)                             |
|ADNLOCRV72 XF  > AF       Mob #1.3 (5% / 50%)                             |
|ADNLOCRV73 XF  > AF       Mob #1.4 (5% / 50%)                             |
|ADNLOCRV74 XF  > AF       Mob #1.5 (5% / 50%)                             |
|BPREVWEN27 XF  > AF     5 NW Conc 1" Agg (Ftg) Mix Design: Review/Approve |
|BPREVWEN37 XF  > AF     9 Pile Concrete Mix Design: Review & Approve      |
|FNFABRCD10 XF  > AF     3 Shoring: Fab & Deliver                          |
|FNFABRCD20 XF  > AF     1 Wales: Fab & Deliver 2 each                     |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 39 newly completed activities had durations equal (or better) than planned
 61 activities have completed this period.
     Average duration of these activities was 56.05 Days.
     Mean of difference of planned/actual durations was 2.44 Days early.
     Standard Deviation of the difference was 13.11 Days.

----------------------------------------------------------------------------
| INCOMPLETED ACTIVITIES WITH DURATIONS DIFFERENT FROM PLANNED             |
| ACT        FLOAT Ty LATE  TITLE                                          |
+---------- ------ -- ---- ------------------------------------------------+
|BPNLOCOE10     61  T   10 Onsite Batch Plant Mobilization                 |
|ESREVWEL88     82  T   11 Corrosion Monitor Working Dwgs: Rereview        |
|ESSUBMEL45    654  T   32 Seismic Anchoring Dwgs: Prep & Submit           |
|FNFABRCD40    121  T   24 Wales: Fab & Deliver 4 each                     |
|FNFABRPL20     58  T   18 Bubble Curtain: Fab & Deliver                   |
|FNFABRTP30     77  T   28 Pile Template #3: Fab                           |
|FNP12ECD00     26  H   38 Pier 12E: Cofferdam (Summary)                   |
|FNP13ECD00     28  H   34 Pier 13E: Cofferdam (Summary)                   |
|FNP14ECD00     14  H   43 Pier 14E: Cofferdam (Summary)                   |
|FNP14EPL05     56  T   33 Pier 14/13E: Fab & Deliver Piles                |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 44 incompleted activities had their durations revised.
 73 activities are currently active.

----------------------------------------------------------------------------
| PLANNED ACTIVITIES WITH CHANGED DURATIONS                                |
| ACT       PROBLEM LONGER  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|ESSUBMEL10 PLAN CHG    50 Traffic OS Equip: Submit                        |
|ESSUBMEL20 PLAN CHG    30 Elec Service Platform Working Dwg: Prep & Submit|
|ESSUBMEL25 PLAN CHG    50 Substation Metal Panel W'Dwg/Data: Prep & Submit|
|ESSUBMEL40 PLAN CHG    50 Substation Metal Frame W'Dwg/Data: Prep & Submit|
|ESSUBMEL50 PLAN CHG    50 Substation Finish Hdw Tech Info: Prep & Submit  |
|ESSUBMEL73 PLAN CHG    25 Boxes & Enclosures: Prep & Submit               |
|ESSUBMEL75 PLAN CHG    25 Conduit: Prep & Submit                          |
|ESSUBMEL80 PLAN CHG    50 Rdwy Lighting Working Dwg: Prep & Submit        |
|FNFABRFS35 PLAN CHG   -24 Footing 16 E: Transport                         |
|FNFABRFS37 PLAN CHG   -24 Footing 15 E: Transport                         |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 273 planned activities had their duration changed.
    Note: This report looks at workdays and not dates or durations.  You may
        note an activity in this list that has the same Origional Duration,
        Remaining Duration, or even the same start and finish dates.  This
        usually means that holidays or non-workdays have been inserted or
        deleted during the period this activity is planned to be active.
    Note: 'Unexplainable' discrepancies have also occurred  because one of
        the two schedules being reviewed had been modified without re-
        running the CPM calculation.  Be sure that the current dates
        reflect current calculations.

----------------------------------------------------------------------------
| ACTIVITIES WITH ODD TOTAL FLOAT CHANGE (GREATER THAN # OF DAYS OBSERVED) |
| ACT       PROBLEM  CHNG   TITLE                                          |
+---------- -------- ----  ------------------------------------------------+
|ADNLOCMS05 ODD FLOT  -28  Turnover Oakland Access (500 days)              |
|ADNLOCMS25 ODD FLOT   58  Piles: Install'n Complete (KFM)                 |
|ADNLOCMS30 ODD FLOT   65  Footings: Slabs Complete (KFM)                  |
|ADNLOCMS35 ODD FLOT   53  Piers: Construct'n Complete (KFM)               |
|ADNLOCMS76 ODD FLOT -282  Annual SWPPP Renewal #2                         |
|ADNLOCMS77 ODD FLOT -648  Annual SWPPP Renewal #3                         |
|ADNLOCMS78 ODD FLOT 1013  Annual SWPPP Renewal #4                         |
|ADNLOCRV14 ODD FLOT  -28  TRO Months 9/10                                 |
|ADNLOCRV15 ODD FLOT  -28  TRO Months 11/12                                |
|ADNLOCRV16 ODD FLOT  -28  TRO Months 13/14                                |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 1030 activities had an odd change in float.

----------------------------------------------------------------------------
| ACTIVITIES WITH CHANGED DESCRIPTIONS                                     |
| ACT       PROBLEM  FILE   TITLE                                          |
+---------- -------- ----  ------------------------------------------------+
|ESREVWEL91 DESC CHG C2I2  Low Voltage Control Center: Review              |
|                    C2K0  LVCC, UL Panels, Transformer: Review & Approve  |
|                                                                          |
|FNFABRCD30 DESC CHG C2I2  Wales: Fab & Deliver 3 each                     |
|                    C2K0  Wales: Fab & Deliver 14/13/12 & Assemble On-Site|
|                                                                          |
|FNFABRCD40 DESC CHG C2I2  Wales: Fab & Deliver 4 each                     |
|                    C2K0  Wales: Fab/Deliver Pier 11>7 & Assemble On-Site |
|                                                                          |
|FNFABRFS35 DESC CHG C2I2  Footing 16 E: Transport                         |
|                    C2K0  Footing 16 E: Transport from Texas to Pan Canal |
|                                                                          |
|FNFABRFS37 DESC CHG C2I2  Footing 15 E: Transport                         |
|                    C2K0  Footing 15 E: Transport from Texas to Pan Canal |
|                                                                          |
|FNP03ECF40 DESC CHG C2I2  Pier 3E: Set Pile Cages/ Install Studs          |
|                    C2K0  Pier 3E: Pile - Set Cages                       |
|                                                                          |
|FNP03ECF50 DESC CHG C2I2  Pier 3E: Pour Pile                              |
|                    C2K0  Pier 3E: Piles - Pour Lift #1                   |
|                                                                          |
|FNP03EFC10 DESC CHG C2I2  Pier 3E: Pour Exterior Footing Box Cells (LWC)  |
|                    C2K0  Pier 3E: Ftg - Pour LWC Lift #1                 |
|                                                                          |
|FNP03WCF40 DESC CHG C2I2  Pier 3W: Set Pile Cages/ Install Studs          |
|                    C2K0  Pier 3W: Pile - Set Cages                       |
|                                                                          |
|FNP03WCF50 DESC CHG C2I2  Pier 3W: Pour Pile                              |
|                    C2K0  Pier 3W: Piles - Pour Lift #1                   |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 107 activities had their description changed.
 0 milestones changed into activities.
 0 activities changed into milestones.

----------------------------------------------------------------------------
| MILESTONES WHICH DISPLAY VARIANCES                                       |
|  ACT ID      VARIANCE    DESCRIPTION                                     |
+---------- -------------- ------------------------------------------------+
|ADNLOCMS25 MS DELAYED  85 Piles: Install'n Complete (KFM)                 |
|ADNLOCMS30 MS DELAYED  92 Footings: Slabs Complete (KFM)                  |
|ADNLOCMS35 MS DELAYED  81 Piers: Construct'n Complete (KFM)               |
|ADNLOCMS40 MS DELAYED  33 Hinges EB: Install'n Complete (KFM)             |
|ADNLOCMS45 MS DELAYED  37 Pier Tables: Construct'n Complete (KFM)         |
|ADNLOCMS50 MS DELAYED  33 Superstructures: Construct'n Complete (KFM)     |
|ADNLOCMS55 MS DELAYED  30 Closures: Construct'n Complete (KFM)            |
|ADNLOCMS60 MS DELAYED  31 Hinges WB: Install'n Complete (KFM)             |
|ADNLOCMS80 MS DELAYED  29 Drive on Access to EB                           |
|ADNLOCMS99 MS DELAYED  28 KFM Substantially Complete                      |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 18 milestones showed variances.

============================== RELATIONSHIPS ===============================

 Target Project: C2I2 with 5980 relationships.
 Update Project: C2K0 with 6301 relationships.

 0 Target File relationships are bogus.
 0 Update File relationships are bogus.

----------------------------------------------------------------------------
| RELATIONSHIPS WHICH HAVE BEEN DELETED SINCE LAST UPDATE                  |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|ADNLOCMS74 ---------- ---- --- Start of On-Site Concrete Production       |
|           FNP16EFS55    0 FS  Pier 16E: Place Concrete Footing Lift #1   |
|                                                                          |
|ADREVWEN33 ---------- ---- --- SWPPP Plan: BCDC Review                    |
|           ADNLOCMS99    0 FS  KFM Substantially Complete                 |
|                                                                          |
|ADREVWEN34 ---------- ---- --- SWPPP Plan: RWQCB Review                   |
|           ADNLOCMS99    0 FS  KFM Substantially Complete                 |
|                                                                          |
|ADSUBMEN20 ---------- ---- --- Submit Electronic Mobile Diary Equip & Pers|
|           ADNLOCMS99    0 FS  KFM Substantially Complete                 |
|                                                                          |
|BPREVWEN22 ---------- ---- --- 55 MPA Creep/Shrink Test (Pier Table): Revi|
|           SBSUBMTB02    0 FS  Pier Table Demo Pour: Perform & Submit     |
|                                                                          |
|BPREVWEN27 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Review/App|
|           FNP16EFS55    0 FS  Pier 16E: Place Concrete Footing Lift #1   |
|                                                                          |
|BPREVWEN57 ---------- ---- --- NW Conc (Pier Table) Mix Design: Review & A|
|           SBSUBMTB02    0 FS  Pier Table Demo Pour: Perform & Submit     |
|                                                                          |
|ESREVWEL21 ---------- ---- --- Substation Mat'l SOO: Review (Caltrans)    |
|           ADNLOCMS99    0 FS  KFM Substantially Complete                 |
|                                                                          |
|ESREVWEL72 ---------- ---- --- Structural Grounding: Review (Caltrans)    |
|           SBP16EPR12    0 FS  Pier 16E: Set Pier Form Lift #1            |
|                                                                          |
|ESREVWEL75 ---------- ---- --- Boxes & Enclosures: Review (Caltrans)      |
|           FWF04EBR10    0 FS  Frame 4E: Barrier                          |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 172 relationships have been deleted, 2 not listed because act. deleted.

----------------------------------------------------------------------------
| RELATIONSHIPS TO ACTIVITIES WHICH HAVE BEEN DELETED SINCE LAST UPDATE    |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
:---------- ---------- ---- --- -------------------------------------------+
|PCC16ESC04 ---------- ---- --- Cant 16ED: Stress Transverse & Vertical P.T|
|           PCCB02SC30    0 FS  Bed #2 Shutdown for Segment Storage Capacit|
|                                                                          |
|PCCB02SC30 ---------- ---- --- Bed #2 Shutdown for Segment Storage Capacit|
|           PCC16WSC03    0 FS  Cant 16WU: Cast Segments                   |
|                                                                          |
----------------------------------------------------------------------------
 2 relationships from deleted activities have been deleted.

----------------------------------------------------------------------------
| RELATIONSHIPS WHICH HAVE BEEN ADDED SINCE LAST UPDATE                    |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|ADNLOCMS74 ---------- ---- --- Start of On-Site Concrete Production       |
|           FNP15EFS55    0 FS  Pier 15E: Place Concrete Footing Lift #1   |
|                                                                          |
|ADREVWEN33 ---------- ---- --- SWPPP Plan: BCDC Review                    |
|           FNNLOCDR40    0 FS  Access Dredging: P11E - P16 E/W            |
|                                                                          |
|ADREVWEN34 ---------- ---- --- SWPPP Plan: RWQCB Review                   |
|           FNNLOCDR40    0 FS  Access Dredging: P11E - P16 E/W            |
|                                                                          |
|ADSUBMEN20 ---------- ---- --- Submit Electronic Mobile Diary Equip & Pers|
|           ADNLOCMS15    0 FS  Pre-Construction Schedule Mtg              |
|                                                                          |
|BPREVWEN22 ---------- ---- --- 55 MPA Creep/Shrink Test (Pier Table): Revi|
|           SBREVWTB04    0 FS  Pier Table Demo Pour & TCP: Review &  Appro|
|                                                                          |
|BPREVWEN57 ---------- ---- --- NW Conc (Pier Table) Mix Design: Review & A|
|           SBREVWTB04    0 FS  Pier Table Demo Pour & TCP: Review &  Appro|
|                                                                          |
|ESREVWEL21 ---------- ---- --- Substation Mat'l SOO: Review (Caltrans)    |
|           ESS08EEL10    0 FS  Span 8E: Install Electrical Substation     |
|                                                                          |
|ESREVWEL62 ---------- ---- --- Conduit Supports Cons'n Methods: Review    |
|           PCCB01SC01    0 FS  Cast Trial Segment 12EU1                   |
|                                                                          |
|ESREVWEL72 ---------- ---- --- Structural Grounding: Review (Caltrans)    |
|           FNP16EFC30    0 FS  Pier 16E: Pour & Cure Col Cell Lift #1     |
|                                                                          |
|ESREVWEL75 ---------- ---- --- Boxes & Enclosures: Review (Caltrans)      |
|           ESS08EEL10    0 FS  Span 8E: Install Electrical Substation     |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 493 relationships have been added, 412 not listed because act. was added.

----------------------------------------------------------------------------
| RELATIONSHIPS TO ACTIVITIES WHICH HAVE BEEN ADDED SINCE LAST UPDATE      |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|BPREVWEN27 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Review/App|
|           BPSUBMEN28    0 FS  NW Conc 1" Agg (Ftg) Mix Design: Resubmit  |
|                                                                          |
|BPREVWEN29 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Rereview  |
|           FNP16EFS55    0 FS  Pier 16E: Place Concrete Footing Lift #1   |
|                                                                          |
|BPSUBMEN28 ---------- ---- --- NW Conc 1" Agg (Ftg) Mix Design: Resubmit  |
|           BPREVWEN29    0 FS  NW Conc 1" Agg (Ftg) Mix Design: Rereview  |
|                                                                          |
|ESREVWEL02 ---------- ---- --- SCADA: Review & Approve                    |
|           ESS08EEL10    0 FS  Span 8E: Install Electrical Substation     |
|                                                                          |
|ESREVWEL04 ---------- ---- --- LVCC, UL Panels, Transformer: Re-review    |
|           ESS08EEL10    0 FS  Span 8E: Install Electrical Substation     |
|                                                                          |
|ESREVWEL91 ---------- ---- --- LVCC, UL Panels, Transformer: Review & Appr|
|           ESSUBMEL03    0 FS  LVCC, UL Panels, Transformer: Re-submit    |
|                                                                          |
|ESSUBMEL01 ---------- ---- --- SCADA: Prep & Submit                       |
|           ESREVWEL02    0 FS  SCADA: Review & Approve                    |
|                                                                          |
|ESSUBMEL03 ---------- ---- --- LVCC, UL Panels, Transformer: Re-submit    |
|           ESREVWEL04    0 FS  LVCC, UL Panels, Transformer: Re-review    |
|                                                                          |
|ESSUBMEL60 ---------- ---- --- Conduit Supports Cons'n Methods: Prep & Sub|
|           ESSUBMEL01    0 SS  SCADA: Prep & Submit                       |
|                                                                          |
|FNFABRFS20 ---------- ---- --- Found'n Wood Box Mockup: Fab & Install     |
|           FNSUBMFS16    0 FS  Pile Head Weld Procedure: Prep & Submit    |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 412 relationships from added activities have been added.

----------------------------------------------------------------------------
| ACTIVITIES WITH MODIFIED RELATIONSHIPS                                   |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|ESSUBMEL95 ----- OLD REL = FS  Substation Electrical Information: Submit  |
|           ESSUBMEL91      SS  Low Voltage Control Center: Submit         |
|                                                                          |
|FNFABRFS40 ----- OLD REL = FS  Footing 13 & 14 E: Subcontractor Complete F|
|           FNFABRFS50      SS  Footing 9 thru 12 E: Sub Fab               |
|                                                                          |
|FNFABRTP20 ----- OLD REL = FS  Pile Template #2: Fab                      |
|           FNFABRTP30      SS  Pile Template #3: Fab                      |
|                                                                          |
|FNP03ECF40 OLD LAG/R=    7/SS  Pier 3E: Pile - Set Cages                  |
|           FNP03ECF50    0/FS  Pier 3E: Piles - Pour Lift #1              |
|                                                                          |
|FNP03EFC10 OLD LAG/R=    1/SS  Pier 3E: Ftg - Pour LWC Lift #1            |
|           FNP03ECF40    0/FS  Pier 3E: Pile - Set Cages                  |
|                                                                          |
|FNP03WCF40 OLD LAG/R=    7/SS  Pier 3W: Pile - Set Cages                  |
|           FNP03WCF50    0/FS  Pier 3W: Piles - Pour Lift #1              |
|                                                                          |
|FNP03WFC10 OLD LAG/R=    1/SS  Pier 3W: Ftg - Pour LWC Lift #1            |
|           FNP03WCF40    0/FS  Pier 3W: Pile - Set Cages                  |
|                                                                          |
|FNP04ECF40 OLD LAG/R=    7/SS  Pier 4E: Pile - Set Cages                  |
|           FNP04ECF50    0/FS  Pier 4E: Piles - Pour Lift #1              |
|                                                                          |
|FNP04EFC10 OLD LAG/R=    1/SS  Pier 4E: Ftg - Pour LWC Lift #1            |
|           FNP04ECF40    0/FS  Pier 4E: Pile - Set Cages                  |
|                                                                          |
|FNP04WCF40 OLD LAG/R=    7/SS  Pier 4W: Pile - Set Cages                  |
|           FNP04WCF50    0/FS  Pier 4W: Piles - Pour Lift #1              |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 60 relationships have been modified.
 0 activities have been orphaned.

----------------------------------------------------------------------------
| RELATIONSHIPS WITH MODIFIED LAG DURATIONS                                |
| PRED ACT  SUCC ACT   LAG  REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|ADNLOCMS10  OLD LAG =  250     Notice to Proceed                          |
|           FNSUBMPF10  450 FS  RRP/CP Lumber Working Dwg: Prep & Submit   |
|                                                                          |
|ADNLOCMS10  OLD LAG =  320     Notice to Proceed                          |
|           FWSUBMCN10    0 FS  Cormorant Nesting Working Dwgs: Prep & Subm|
|                                                                          |
|ADNLOCMS10  OLD LAG =  257     Notice to Proceed                          |
|           SBSUBMAC10  300 FS  Pier Casing Falsework: Prep & Submit       |
|                                                                          |
|ADNLOCMS10  OLD LAG =  205     Notice to Proceed                          |
|           SSSUBMSG50    0 FS  SS Fab Proc Ortho Box Shell Plate: Prep & S|
|                                                                          |
|ADNLOCMS10  OLD LAG =  205     Notice to Proceed                          |
|           SSSUBMSG60    0 FS  SS Fab Procedure Ortho Box: Prep & Submit  |
|                                                                          |
|ESSUBMEL95  OLD LAG =   25     Substation Electrical Information: Submit  |
|           ESSUBMEL45    0 SS  Seismic Anchoring Dwgs: Prep & Submit      |
|                                                                          |
|MBSFB1MB23  OLD LAG =   21     DB Oakland: Mobilize                       |
|           FNP16ECD25    0 FS  Pier 16E: Place Locking Fill               |
|                                                                          |
|MBSFB1MB30  OLD LAG =    5     DB Vancouver: Mobilize                     |
|           FNP16ECD10    0 FS  Pier 16E: Drive Sheets/Access Platforms    |
|                                                                          |
|MBSFB1MB35  OLD LAG =   20     Catamaran Barge: Mobilize                  |
|           FNP16EFS30    0 FS  Pier 16E: Align, Set & Secure Footing Box  |
|                                                                          |
|MBSFB1MB40  OLD LAG =   20     DB Bremerton: Mobilize                     |
|           FNP16EFS20    0 FS  Pier 16E: Dewater Cell to Top of Box       |
|                                                                          |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 13 relationship lags changed.
 0 relationship chains are interruptible.
 0 Activities are missing Finish Relationships.

================================ CONSTRAINTS ===============================

 0 Target File constraints are bogus.
 0 Update File constraints are bogus.

----------------------------------------------------------------------------
| CONSTRAINTS WHICH HAVE BEEN DELETED SINCE LAST UPDATE                    |
| ACT       C-TYPE  DATE    TITLE                                          |
+---------- ------ ------- ------------------------------------------------+
|ADNLOCMS76  SNET  15JUL03 Annual SWPPP Renewal #2                         |
|ADNLOCMS77  SNET  15JUL04 Annual SWPPP Renewal #3                         |
|ADNLOCMS78  SNET  15JUL05 Annual SWPPP Renewal #4                         |
|ADNLOCMS99  FNLT   4AUG06 KFM Substantially Complete                      |
|ADNLOCRV70  SNET   1OCT02 Mob #1.1 (5% / 50%)                             |
|ADNLOCRV75  SNET   1JAN03 Mob #2.1 (10% / 75%)                            |
|ADNLOCRV78  SNET   1MAY03 Mob #3.1 (20% / 95%)                            |
|ADNLOCRV80  SNET   1FEB04 Mob #4 (50% / 100%)                             |
|MSSUBMSN10  SNET   1JAN03 Sign Structure Working Dwg: Prep & Submit       |
----------------------------------------------------------------------------
 9 constraints have been deleted.
 0 constraints have been added.
 0 constraints have been modified.
 0 constraint dates have been modified.
 0 Expected Finish dates are out of date.

================================ COST CHECKS ===============================

 Section skipped due to no cost entries

================================ LOG CHECKS ================================

 0 new log records were found in 0 activities.
 0 old log records were deleted in 0 activities.
 0 log records were modified in 0 activities.

=========================== HIGHER LEVEL REPORTS ===========================


----------------------------------------------------------------------------
| MILESTONES AWAITING STATUS                                               |
|  ACT ID     TYPE   FLOAT DESCRIPTION                                     |
+---------- -------- ----- ------------------------------------------------+
|ADNLOCMS35  FINISH    117 Piers: Construct'n Complete (KFM)               |
|ADNLOCMS40  FINISH    211 Hinges EB: Install'n Complete (KFM)             |
|ADNLOCMS45  FINISH    151 Pier Tables: Construct'n Complete (KFM)         |
|ADNLOCMS50  FINISH    102 Superstructures: Construct'n Complete (KFM)     |
|ADNLOCMS55  FINISH     64 Closures: Construct'n Complete (KFM)            |
|ADNLOCMS60  FINISH     60 Hinges WB: Install'n Complete (KFM)             |
|ADNLOCMS76   START   1399 Annual SWPPP Renewal #2                         |
|ADNLOCMS77   START   1399 Annual SWPPP Renewal #3                         |
|ADNLOCMS78   START   1399 Annual SWPPP Renewal #4                         |
|ADNLOCMS80  FINISH     17 Drive on Access to EB                           |
|  ********** REMAINING ACTIVITIES SUPPRESSED FOR DEMO PURPOSES ********** |
----------------------------------------------------------------------------
 12 milestones are awaiting status.

----------------------------------------------------------------------------
| ACTIVITIES VIOLATING DUE DILIGENCE                                       |
| ACT       PROBLEM  LATE T-TF TITLE                                       |
+---------- -------- ---- ---- --------------------------------------------+
|BPNLOCOE10 LATE STR   48   35 Onsite Batch Plant Mobilization             |
|ESSUBMEL01 LATE STR    1      SCADA: Prep & Submit                        |
|FNFABRTP30 LATE STR    2   19 Pile Template #3: Fab                       |
|FNP13ECD05 LATE STR    2   72 Pier 13E: Install Wale System               |
|FNSUBMCD30 LATE STR   27   25 Cofferdam Dewatering Submittal              |
|SBSUBMPS18 LATE STR   43      PIER STAIRS: RESOLVE DISCREPENCIES          |
|SSREVWQC17 LATE STR    1  190 Steel QC Caltrans Audit: Conduct (Caltrans) |
----------------------------------------------------------------------------
 7 activities started late this period.
    The Mean of the late starts are 18 Days late.
    The Standard Deviation of the difference is 21 Days.

----------------------------------------------------------------------------
| ACTIVITIES WHICH STARTED EARLIER THAN PLANNED                            |
| ACT       PROBLEM EARLY T-TF TITLE                                       |
+---------- -------- ---- ---- --------------------------------------------+
|ADNLOCRV71 EARLY ST    1  872 Mob #1.2 (5% / 50%)                         |
|ADNLOCRV72 EARLY ST    1  872 Mob #1.3 (5% / 50%)                         |
|ADNLOCRV73 EARLY ST    1  872 Mob #1.4 (5% / 50%)                         |
|ADNLOCRV74 EARLY ST    1  872 Mob #1.5 (5% / 50%)                         |
|ESSUBMEL45 EARLY ST   14  623 Seismic Anchoring Dwgs: Prep & Submit       |
|PCPRECPC16 EARLY ST    6   31 Setup & Test Batch Plant                    |
----------------------------------------------------------------------------
 6 activities started earlier than planned this period.
    The Mean of the early starts are 94 Days late.
    The Standard Deviation of the difference is 43 Days.

 Critical Total Float for the Target project is 0.
 Critical Total Float for the Update project is 0.
 Critical Float Changed:  0 

 The Target File Had 39 critical activities.
 The Update File Had 64 critical activities.

----------------------------------------------------------------------------
| MOST CRITICAL LIST OF ACTIVITIIES (CHANGE 'd' IN WORK DAYS THIS PERIOD)  |
| TARGET     UPDATE    dES dEF dAS dAF DESCRIPTION                         |
+---------- ---------- --- --- --- --- ------------------------------------+
|PCFABRSC20 PCFABRSC20   0 -29   0     Segment Beds: Procure, Fab & Deliver|
|                                      ** FS rel to Act PCFABRSC24 added **|
|           PCFABRSC24(activity added) SEG BEDS: DELIVER (PARTIAL)         |
|                                      ** New critical activity added **   |
|                                      ** FS rel to Act PCCB01SC99 added **|
|PCCB01SC99 PCCB01SC99  27  27         Assemble Segment Bed #1             |
|PCCB02SC21             27  27         Assemble Segment Bed #2             |
|PCCB03SC99             27  27         Assemble Segment Bed #3             |
|PCC12ESC02             21  21         Cant 12ED: Cast Segments            |
|PCC11ESC02             21  21         Cant 11ED: Cast Segments            |
|PCF02EME10 PCF02EME10  32  32         Frame 2E: Mech Staging (Summary)    |
|PCC10ESC02             21  21         Cant 10ED: Cast Segments            |
|PCC09ESC02             21  21         Cant 9ED: Cast Segments             |
|PCF02WME10 PCF02WME10  32  32         Frame 2W: Mech Staging (Summary)    |
|PCC11WSC03 PCC11WSC03  32  32         Cant 11WU: Cast Segments            |
|PCC08ESC02 PCC08ESC02  32  32         Cant 8ED: Cast Segments             |
|PCC12WSC03 PCC12WSC03  32  32         Cant 12WU: Cast Segments            |
|PCF01EME10 PCF01EME10  34  32         Frame 1E: Mech Staging (Summary)    |
|                                      ** Origional Duration modified **   |
|                                      ** Duration modified before started |
|PCC07ESC02 PCC07ESC02  32  32         Cant 7ED: Cast Segments             |
|PCC06ESC02 PCC06ESC02  32  32         Cant 6ED: Cast Segments             |
|PCC05ESC02 PCC05ESC02  32  32         Cant 5ED: Cast Segments             |
|PCC04ESC02 PCC04ESC02  32  32         Cant 4ED: Cast Segments             |
|PCC03ESC02 PCC03ESC02  32  32         Cant 3ED: Cast Segments             |
|PCC03ESC03 PCC03ESC03  32  32         Cant 3EU: Cast Segments             |
|PCC10WSC03 PCC10WSC03  32  32         Cant 10WU: Cast Segments            |
|PCC09WSC03 PCC09WSC03  32  32         Cant 9WU: Cast Segments             |
|PCC08WSC03 PCC08WSC03  32  32         Cant 8WU: Cast Segments             |
|PCC07WSC03 PCC07WSC03  32  32         Cant 7WU: Cast Segments             |
|SPC07WSG00 SPC07WSG00  33  28         Cant. 7W: SLED (Summary)            |
|                                      ** Origional Duration modified **   |
|                                      ** Duration modified before started |
|ESF02WEL10 ESF02WEL10  28  28         Frame 2W: Cable Tray & Conduit      |
|SPC07WSG60 SPC07WSG60  28  28         Cant 7W: Erect Segments 2E/W thru 9E|
|           SPC05WSG10  28  28         Cant 5W: Erect SLED (Up/Down)       |
|           SPC05WSG00  28  28         Cant. 5W: SLED (Summary)            |
|           SPC05WSG20  28  28         Cant 5W: Erect Segments 1E/1W       |
|           SPC05WSG30  28  28         Cant 5W: Cast Wet Joint & Cure      |
|           SPC05WSG40  28  28         Cant 5W: Install & Stress Cant. Tend|
|           SPC05WSG60  28  28         Cant 5W: Erect Segments 2E/W thru 9E|
|           SSF01WTW20  28  28         San Francisco Tower BW: Erect Temp T|
|           SPC03WSG10  28  28         Cant 3W: Erect SLED (Up/Down)       |
|           SPC03WSG20  28  28         Cant 3W: Erect Segments 1E/1W       |
|           SPC03WSG00  28  28         Cant. 3W: SLED (Summary)            |
|           SPC03WSG30  28  28         Cant 3W: Cast Wet Joint & Cure      |
|           SSF01WTW10  28  28         San Francisco Tower AW: Erect Temp T|
|           SPC03WSG40  28  28         Cant 3W: Install & Stress Cant. Tend|
|           SPF01WCL00  28  29         Frame 1W: Closure (Summary)         |
|                                      ** Origional Duration modified **   |
|                                      ** Duration modified before started |
|           SPC03WSG60  28  28         Cant 3W: Erect Segments 2E/W thru 5E|
|           SSS03WSG10  28  28         Erect Transition Span Steel W       |
|           SPF01WPT00  28  29         Frame 1W: Post Tensioning (Summary) |
|                                      ** Origional Duration modified **   |
|                                      ** Duration modified before started |
|           SPF01WHG10  28  28         Hinge AW: Lift & Secure pipe        |
|           SPS03WCL10  28  28         Span 3W: Complete Closure to Steel  |
|           SPC03WSG70  28  28         Cant 3W: Erect Segments 6E thru 9E  |
|           SSS03WSG20  28  28         Span 3W: Lower Transition Span Tip  |
|           SPS04WCL10  28  28         Span 4W: Complete Exterior Closure  |
|           SPF01WCL10  28  28         Frame 1W: Align & Jack              |
|           SPF01WCL20  28  28         Frame 1W: Install Resteel & Pour Clo|
|           SPF01WHG63  32  32         Hinge AW Pipe Beam: Deliver         |
|ESF02WEL42 ESF02WEL42  28  28         Frame 2W: Pre-Pour Rough Barrier Ele|
|           SPS05WPT10  29  29         Span 5W: Stress & Grout Span Tendons|
|           SPS03WPT10  29  29         Span 3W: Stress & Grout Span Tendons|
|           SPS07WPT12  29  29         Span 7WW: Stress & Grout Span Tendon|
|           SPS07WHG20  29  29         Hinge BW: Align Pipe Beams & Grout B|
|           SPF01WPT20  29  29         Frame 1W: Stress Continuity Tendons |
|ESF02WEL45 ESF02WEL45  28  28         Frame 2W: Barrier Electrical        |
|FWF02WBR10 FWF02WBR10  28  28         Frame 2W: Barrier                   |
|ESF01WEL45 ESF01WEL45  28  28         Frame 1W: Barrier Electrical        |
|FWF01WBR10 FWF01WBR10  28  28         Frame 1W: Barrier                   |
|ESF01WEL30 ESF01WEL30  28  28         Frame 1W:  Wire & Devices           |
|ESF01WEL70 ESF01WEL70  28  28         Frame 1W: Roadway Level Electrical T|
|ESF01WEL60 ESF01WEL60  28  28         Frame 1W: Roadway Lighting          |
|ESNLOCEL20 ESNLOCEL20  28  28         Electrical Testing WB               |
|FWNLOCPU10 FWNLOCPU10  28  28         Punchlist Roadway Surface           |
|ADNLOCMS99 ADNLOCMS99      28         KFM Substantially Complete          |
|PCP07WAR25 PCP07WAR25  44  44         Pier 7W: Segment Age Restriction 6 m|
|           SPF01WCL25  43  43         Frame 1W: Cure Interior Closure     |
----------------------------------------------------------------------------
============================== END OF REPORT ===============================
 Analysis complete at 09:14:36.

Return to SA Pro Overview.