Schedule Analyzer Professional

Copyright Ron Winter 2003

Sample Baseline Checker Report - Lists Limited to First 10 Entries


                         SA PRO BASELINE CHECKER
                       ============================
                       |        Version 2.78      |
                       ============================
                     Copyright by Ron Winter 1998/2003

    This report was prepared by Ron Winter Consulting LLC.

    BASELINE: BL00                 Analysis Date: 07-01-2003 at 16:15:28

    Schedule used for Coding Standards = C:\P3WIN\PROJECTS\242Med\514A
    Company Name  = Unnamed Joint Venture                  
    Project Title = Unnamed Project           
    Report Title  = (nothing on record.)
        CAUTION: You should enter a Report Title under Tools, Tabular,
            Reports, Options: Center Heading. It will be printed in the
            middle center of the header in tabular reports.

    Project Version  = Baseline        

    Project Start = 16JUL01    Project Early Finish = 13OCT05

=========================== SCHEDULE STATISTICS ============================

----------------------- STATISTICAL STANDARDS CHECK ------------------------
This project does not use Imposed Finish Dates in violation of standards.
Calendar Start Date does not match Standard.
Calendar 2 Description has been changed.
Calendar 3 has been added.
Calendar 4 has been added.
Calendar 5 has been added.
Calendar 6 has been added.
Calendar 7 has been added.
Calendar 8 has been added.
Calendar 9 has been added.
Calendar A has been added.
Calendar B has been added.
Calendar C has been added.
Some Calendar Holidays have been deleted.
The total number of calendar holidays changed form 28  to 432 .
Rule 4a: When Quantities change, recompute Budget Costs has been changed.
The Total Float Calculation rule has been changed.
----------------------------------------------------------------------------

CALENDAR CHECK

    CAUTION: This project uses an Imposed Finish Date of 10/13/2005 .  This
             setting will not allow for the addition of activities after
             Substantial Completion (such as Punchlist) without messing-up
             float calculations for the whole project.  Recommend that you
             constrain the Late Finish of the activity that describes
             Substantial Completion instead of using this feature.  You can
             remove this Imposed Finished Date under Project Overview under
             the heading of 'Project must finish by'.

    Project computes durations in Days.
        NOTE: This project calculates durations in Days.  This is the 
            standard setting, offering a balance between accuracy and
            maintainability. The only way to change this unit of measurement
            is to copy the schedule and define the new unit during the process.

        NOTE: The start day for the week (Monday) is used for reporting
            on a weekly timescale and to determine when weekends occur for
            Calendar 1. This setting can be changed once defined by
            selection Data, Calendars, Global Calendar, Standard.

    The following calendars are defined:
    ----------------------------------------
        Global Calendar,
        Calendar 1                  CAUTION: Calendar Title is missing.
        Calendar 2 7-Days/Week     
        Calendar 3 5-Days/Wk, H    
        Calendar 4 5D/Wk H/W       
        Calendar 5 5 Days -H/Winter
        Calendar 6 PAINT 5D/CTA/W  
        Calendar 7 WEnd - H/CTA/WIN
        Calendar 8 WEnd/H          
        Calendar 9 6 DAYS          
        Calendar A Wend - Day Shift
        Calendar B 5DAY/W-4DAY (H) 
        Calendar C 5DAY/W-4DAY (SB)
    ----------------------------------------
        A total of 12 calendars are defined.
        CAUTION:  You are missing some calendar titles.  The use of
            descripive titles helps you to identify the correct one when
            assigning activity calendars, preventing mistakes.
----------------------------------------------------------------------------
| PROJECT WEEKEND LISTING                                                  |
| DAY      CALENDAR WHICH HAS THAT WEEKEND  NOTES                          |
!--------- -------------------------------- -------------------------------+
|           123456789ABC                    List of all active calendars.  |
| MONDAY          78 A                      Note: Unusual day for weekend. |
| TUESDAY         78 A                      Note: Unusual day for weekend. |
| WEDNESDAY       78 A                      Note: Unusual day for weekend. |
| THURSDAY        78 A                      Note: Unusual day for weekend. |
| FRIDAY          78 A                      Note: Unusual day for weekend. |
| SATURDAY  1 3456    BC                                                   |
| SUNDAY    1 3456  9 BC                                                   |
---------- -------------------------------- --------------------------------

HOLIDAY CHECK:

    CAUTION: According to settings, holidays will automatically be moved to
        the nearest workday if they fall on non-workdays (weekends.)

----------------------------------------------------------------------------
| PROJECT HOLIDAY LISTING                                                  |
| DATE     CALENDAR WHICH HAS THAT HOLIDAY              NOTES              |
!--------- -------------------------------- -------------------------------+
|          *123456789ABC                    List of all active calendars.  |
| 30AUG01       56                                                         |
| 31AUG01       56                                                         |
| 01SEP01         78                                                       |
| 02SEP01         78                                                       |
| 03SEP01     3456    BC                                                   |
| 15NOV01        6                                                         |
| 16NOV01        6                                                         |
| 19NOV01        6                                                         |
| 20NOV01        6                                                         |
| 21NOV01        6                                                         |
| 22NOV01     3456    BC                                                   |
| 23NOV01     3456    BC                                                   |
| 24NOV01          8                                                       |
| 25NOV01          8                                                       |
| 26NOV01        6                                                         |
| 27NOV01        6                                                         |
| 28NOV01        6                                                         |
| 29NOV01        6                                                         |
| 30NOV01        6                                                         |
| 03DEC01        6                                                         |
| 04DEC01        6                                                         |
| 05DEC01        6                                                         |
| 06DEC01        6                                                         |
| 07DEC01        6                                                         |
| 10DEC01        6                                                         |
| 11DEC01        6                                                         |
| 12DEC01        6                                                         |
| 13DEC01        6                                                         |
| 14DEC01        6                                                         |
| 17DEC01      456                                                         |
| 18DEC01      456                                                         |
| 19DEC01      456                                                         |
| 20DEC01      456                                                         |
| 21DEC01      456                                                         |
| 22DEC01         78                                                       |
| 23DEC01         78                                                       |
| 24DEC01     3456    BC                                                   |
| 25DEC01     3456    BC                                                   |
| 26DEC01      456    BC                                                   |
| 27DEC01      456    BC                                                   |
| 28DEC01      456    BC                                                   |
| 29DEC01         7                                                        |
| 30DEC01         7                                                        |
| 31DEC01      456    BC                                                   |
| 01JAN02     3456    BC                                                   |
| 02JAN02      456    BC                                                   |
| 03JAN02      456    BC                                                   |
| 04JAN02      456    BC                                                   |
| 05JAN02         7                                                        |
| 06JAN02         7                         Date delayed due to weekend.   |
| 07JAN02      456                                                         |
| 08JAN02      456                                                         |
| 09JAN02      456                                                         |
| 10JAN02      456                                                         |
| 11JAN02      456    BC                                                   |
| 13JAN02         7                         Date delayed due to weekend.   |
| 14JAN02      456                                                         |
| 15JAN02      456                                                         |
| 16JAN02      456                                                         |
| 17JAN02      456                                                         |
| 18JAN02      456    BC                                                   |
| 20JAN02         7                         Date delayed due to weekend.   |
| 21JAN02      456                                                         |
| 22JAN02      456                                                         |
| 23JAN02      456                                                         |
| 24JAN02      456                                                         |
| 25JAN02      456    BC                                                   |
| 27JAN02         7                         Date delayed due to weekend.   |
| 28JAN02      456                                                         |
| 29JAN02      456                                                         |
| 30JAN02      456                                                         |
| 31JAN02      456                                                         |
| 01FEB02      456    BC                                                   |
| 04FEB02      456                                                         |
| 05FEB02      456                                                         |
| 06FEB02      456                                                         |
| 07FEB02      456                                                         |
| 08FEB02      456    BC                                                   |
| 09FEB02         7                                                        |
| 10FEB02         7                                                        |
| 11FEB02      456                                                         |
| 12FEB02      456                                                         |
| 13FEB02      456                                                         |
| 14FEB02      456                                                         |
| 15FEB02      4 6    BC                                                   |
| 18FEB02        6                                                         |
| 19FEB02        6                                                         |
| 20FEB02        6                                                         |
| 21FEB02        6                                                         |
| 22FEB02        6    BC                                                   |
| 25FEB02        6                                                         |
| 26FEB02        6                                                         |
| 27FEB02        6                                                         |
| 28FEB02        6                                                         |
| 01MAR02        6    BC                                                   |
| 04MAR02        6                                                         |
| 05MAR02        6                                                         |
| 06MAR02        6                                                         |
| 07MAR02        6                                                         |
| 08MAR02        6    BC                                                   |
| 11MAR02        6                                                         |
| 12MAR02        6                                                         |
| 13MAR02        6                                                         |
| 14MAR02        6                                                         |
| 15MAR02        6    BC                                                   |
| 22MAR02             BC                                                   |
| 29MAR02             BC                                                   |
| 13APR02         78                                                       |
| 14APR02         78                                                       |
| 25MAY02         78                                                       |
| 26MAY02         78                                                       |
| 27MAY02     3456    BC                                                   |
| 31MAY02        6                                                         |
| 28JUN02        6                                                         |
| 01JUL02        6                                                         |
| 02JUL02        6                                                         |
| 03JUL02        6                                                         |
| 04JUL02     3 56    BC                                                   |
| 05JUL02        6    B                                                    |
| 29AUG02        6                                                         |
| 30AUG02        6                                                         |
| 31AUG02         78                                                       |
| 01SEP02         78                                                       |
| 02SEP02     3456    BC                                                   |
| 15NOV02        6                                                         |
| 18NOV02        6                                                         |
| 19NOV02        6                                                         |
| 20NOV02        6                                                         |
| 21NOV02        6                                                         |
| 22NOV02        6                                                         |
| 25NOV02        6                                                         |
| 26NOV02        6                                                         |
| 27NOV02        6                                                         |
| 28NOV02     3456    BC                                                   |
| 29NOV02     3456    BC                                                   |
| 30NOV02          8                                                       |
| 01DEC02          8                                                       |
| 02DEC02        6                                                         |
| 03DEC02        6                                                         |
| 04DEC02        6                                                         |
| 05DEC02        6                                                         |
| 06DEC02        6                                                         |
| 09DEC02        6                                                         |
| 10DEC02        6                                                         |
| 11DEC02        6                                                         |
| 12DEC02        6                                                         |
| 13DEC02        6                                                         |
| 16DEC02      456                                                         |
| 17DEC02      456                                                         |
| 18DEC02      456                                                         |
| 19DEC02      456                                                         |
| 20DEC02      456                                                         |
| 21DEC02         7                                                        |
| 22DEC02         7                                                        |
| 23DEC02      456    BC                                                   |
| 24DEC02     3456    BC                                                   |
| 25DEC02     3456    BC                                                   |
| 26DEC02      456    BC                                                   |
| 27DEC02      456    BC                                                   |
| 28DEC02         7                                                        |
| 29DEC02         7                                                        |
| 30DEC02      456    BC                                                   |
| 31DEC02      456    BC                                                   |
| 01JAN03     3456    BC                                                   |
| 02JAN03      456    BC                                                   |
| 03JAN03      456    BC                                                   |
| 04JAN03         7                         Date advanced due to weekend.  |
| 05JAN03         7                         Date delayed due to weekend.   |
| 06JAN03      456                                                         |
| 07JAN03      456                                                         |
| 08JAN03      456                                                         |
| 09JAN03      456                                                         |
| 10JAN03      456    BC                                                   |
| 12JAN03         7                         Date delayed due to weekend.   |
| 13JAN03      456                                                         |
| 14JAN03      456                                                         |
| 15JAN03      456                                                         |
| 16JAN03      456                                                         |
| 17JAN03      456    BC                                                   |
| 19JAN03         7                         Date delayed due to weekend.   |
| 20JAN03      456                                                         |
| 21JAN03      456                                                         |
| 22JAN03      456                                                         |
| 23JAN03      456                                                         |
| 24JAN03      456    BC                                                   |
| 26JAN03         7                         Date delayed due to weekend.   |
| 27JAN03      456                                                         |
| 28JAN03      456                                                         |
| 29JAN03      456                                                         |
| 30JAN03      456                                                         |
| 31JAN03      456    BC                    Date delayed due to weekend.   |
| 02FEB03         7                                                        |
| 03FEB03      456                                                         |
| 04FEB03      456                                                         |
| 05FEB03      456                                                         |
| 06FEB03      456                                                         |
| 07FEB03      456     C                                                   |
| 08FEB03         7                                                        |
| 09FEB03         7                                                        |
| 10FEB03      456                                                         |
| 11FEB03      456                                                         |
| 12FEB03      456                                                         |
| 13FEB03      456                                                         |
| 14FEB03      456     C                                                   |
| 17FEB03        6                                                         |
| 18FEB03        6                                                         |
| 19FEB03        6                                                         |
| 20FEB03        6                                                         |
| 21FEB03        6     C                                                   |
| 24FEB03        6                                                         |
| 25FEB03        6                                                         |
| 26FEB03        6                                                         |
| 27FEB03        6                                                         |
| 28FEB03        6     C                                                   |
| 03MAR03        6                                                         |
| 04MAR03        6                                                         |
| 05MAR03        6                                                         |
| 06MAR03        6                                                         |
| 07MAR03        6     C                                                   |
| 10MAR03        6                                                         |
| 11MAR03        6                                                         |
| 12MAR03        6                                                         |
| 13MAR03        6                                                         |
| 14MAR03        6     C                                                   |
| 17MAR03        6                                                         |
| 21MAR03              C                                                   |
| 28MAR03              C                                                   |
| 12APR03         78                                                       |
| 13APR03         78                                                       |
| 24MAY03         78                                                       |
| 25MAY03         78                                                       |
| 26MAY03     3456    BC                                                   |
| 30MAY03        6                                                         |
| 27JUN03        6                                                         |
| 30JUN03        6                                                         |
| 01JUL03        6                                                         |
| 02JUL03        6                                                         |
| 03JUL03        6                                                         |
| 04JUL03     3 56    BC                                                   |
| 28AUG03        6                                                         |
| 29AUG03        6                                                         |
| 30AUG03         78                                                       |
| 31AUG03         78                                                       |
| 01SEP03     3456    BC                                                   |
| 17NOV03        6                                                         |
| 18NOV03        6                                                         |
| 19NOV03        6                                                         |
| 20NOV03        6                                                         |
| 21NOV03        6                                                         |
| 24NOV03        6                                                         |
| 25NOV03        6                                                         |
| 26NOV03        6                                                         |
| 27NOV03     3456    BC                                                   |
| 28NOV03     3456    BC                                                   |
| 29NOV03          8                                                       |
| 30NOV03          8                                                       |
| 01DEC03        6                                                         |
| 02DEC03        6                                                         |
| 03DEC03        6                                                         |
| 04DEC03        6                                                         |
| 05DEC03        6                                                         |
| 08DEC03        6                                                         |
| 09DEC03        6                                                         |
| 10DEC03        6                                                         |
| 11DEC03        6                                                         |
| 12DEC03        6                                                         |
| 15DEC03      456                                                         |
| 16DEC03      456                                                         |
| 17DEC03      456                                                         |
| 18DEC03      456                                                         |
| 19DEC03      456                                                         |
| 20DEC03         7                                                        |
| 21DEC03         7                                                        |
| 22DEC03      456    BC                                                   |
| 23DEC03      456    BC                                                   |
| 24DEC03     3456    BC                                                   |
| 25DEC03     3456    BC                                                   |
| 26DEC03      456    BC                                                   |
| 27DEC03         7                                                        |
| 28DEC03         7                                                        |
| 29DEC03      456    BC                                                   |
| 30DEC03      456    BC                                                   |
| 31DEC03      456    BC                                                   |
| 01JAN04     3456    BC                                                   |
| 02JAN04      456    BC                                                   |
| 03JAN04         7                         Date advanced due to weekend.  |
| 04JAN04         7                                                        |
| 05JAN04      456                                                         |
| 06JAN04      456                                                         |
| 07JAN04      456                                                         |
| 08JAN04      456                                                         |
| 09JAN04      456    BC                                                   |
| 10JAN04         7                                                        |
| 11JAN04         7                                                        |
| 12JAN04      456                                                         |
| 13JAN04      456                                                         |
| 14JAN04      456                                                         |
| 15JAN04      456                                                         |
| 16JAN04      456    BC                                                   |
| 17JAN04         7                                                        |
| 18JAN04         7                                                        |
| 19JAN04      456                                                         |
| 20JAN04      456                                                         |
| 21JAN04      456                                                         |
| 22JAN04      456                                                         |
| 23JAN04      456    BC                                                   |
| 24JAN04         7                                                        |
| 25JAN04         7                                                        |
| 26JAN04      456                                                         |
| 27JAN04      456                                                         |
| 28JAN04      456                                                         |
| 29JAN04      456                                                         |
| 30JAN04      456    BC                                                   |
| 31JAN04         7                                                        |
| 01FEB04         7                                                        |
| 02FEB04      456                                                         |
| 03FEB04      456                                                         |
| 04FEB04      456                                                         |
| 05FEB04      456                                                         |
| 06FEB04      456    BC                                                   |
| 07FEB04         7                                                        |
| 08FEB04         7                                                        |
| 09FEB04      456                                                         |
| 10FEB04      456                                                         |
| 11FEB04      456                                                         |
| 12FEB04      456                                                         |
| 13FEB04      456    BC                                                   |
| 16FEB04        6                                                         |
| 17FEB04        6                                                         |
| 18FEB04        6                                                         |
| 19FEB04        6                                                         |
| 20FEB04        6    BC                                                   |
| 23FEB04        6                                                         |
| 24FEB04        6                                                         |
| 25FEB04        6                                                         |
| 26FEB04        6                                                         |
| 27FEB04        6    BC                                                   |
| 01MAR04        6                                                         |
| 02MAR04        6                                                         |
| 03MAR04        6                                                         |
| 04MAR04        6                                                         |
| 05MAR04        6    BC                                                   |
| 08MAR04        6                                                         |
| 09MAR04        6                                                         |
| 10MAR04        6                                                         |
| 11MAR04        6                                                         |
| 12MAR04        6    BC                                                   |
| 15MAR04        6                                                         |
| 17MAR04        6                                                         |
| 19MAR04             BC                                                   |
| 26MAR04             BC                                                   |
| 10APR04         78                                                       |
| 11APR04         78                                                       |
| 29MAY04         78                                                       |
| 30MAY04         78                                                       |
| 31MAY04     3456    BC                                                   |
| 04JUN04        6                                                         |
| 02JUL04        6                                                         |
| 05JUL04       56    B                                                    |
| 06JUL04        6                                                         |
| 07JUL04        6                                                         |
| 08JUL04        6                                                         |
| 09JUL04        6                                                         |
| 26AUG04        6                                                         |
| 27AUG04        6                                                         |
| 04SEP04         78                                                       |
| 05SEP04         78                                                       |
| 06SEP04     3456    BC                                                   |
| 15NOV04        6                                                         |
| 16NOV04        6                                                         |
| 17NOV04        6                                                         |
| 18NOV04        6                                                         |
| 19NOV04        6                                                         |
| 22NOV04        6                                                         |
| 23NOV04        6                                                         |
| 24NOV04        6                                                         |
| 25NOV04     3456    BC                                                   |
| 26NOV04     3456    BC                                                   |
| 27NOV04          8                                                       |
| 28NOV04          8                                                       |
| 29NOV04        6                                                         |
| 30NOV04        6                                                         |
| 01DEC04        6                                                         |
| 02DEC04        6                                                         |
| 03DEC04        6                                                         |
| 06DEC04        6                                                         |
| 07DEC04        6                                                         |
| 08DEC04        6                                                         |
| 09DEC04        6                                                         |
| 10DEC04        6                                                         |
| 13DEC04        6                                                         |
| 14DEC04        6                                                         |
| 15DEC04       56                                                         |
| 16DEC04       56                                                         |
| 17DEC04       56                                                         |
| 18DEC04         7                                                        |
| 19DEC04         7                                                        |
| 20DEC04      456    B                                                    |
| 21DEC04      456    B                                                    |
| 22DEC04      456    B                                                    |
| 23DEC04      456    BC                                                   |
| 24DEC04     3456    BC                                                   |
| 25DEC04         78                                                       |
| 26DEC04         78                                                       |
| 27DEC04      456    BC                                                   |
| 28DEC04      456    BC                                                   |
| 29DEC04      456    BC                                                   |
| 30DEC04      456    BC                                                   |
| 31DEC04      456    BC                                                   |
| 01JAN05         7                                                        |
| 02JAN05         7                                                        |
| 03JAN05      456                                                         |
| 04JAN05      456                                                         |
| 05JAN05      456                                                         |
| 06JAN05      456                                                         |
| 07JAN05      456                                                         |
| 08JAN05         7                                                        |
| 09JAN05         7                                                        |
| 10JAN05      456                                                         |
| 11JAN05      456                                                         |
| 12JAN05      456                                                         |
| 13JAN05      456                                                         |
| 14JAN05      456                                                         |
| 15JAN05         7                                                        |
| 16JAN05         7                                                        |
| 17JAN05      456                                                         |
| 18JAN05      456                                                         |
| 19JAN05      456                                                         |
| 20JAN05      456                                                         |
| 21JAN05      456                                                         |
| 22JAN05         7                                                        |
| 23JAN05         7                                                        |
| 24JAN05      456                                                         |
| 25JAN05      456                                                         |
| 26JAN05      456                                                         |
| 27JAN05      456                                                         |
| 28JAN05      456                                                         |
| 29JAN05         7                                                        |
| 30JAN05         7                                                        |
| 31JAN05      456                                                         |
| 01FEB05      456                                                         |
| 02FEB05      456                                                         |
| 03FEB05      456                                                         |
| 04FEB05      456                                                         |
| 05FEB05         7                                                        |
| 06FEB05         7                                                        |
| 07FEB05      456                                                         |
| 08FEB05      456                                                         |
| 09FEB05      456                                                         |
| 10FEB05      456                                                         |
| 11FEB05      456                                                         |
| 12FEB05         7                                                        |
| 13FEB05         7                                                        |
| 14FEB05       56                                                         |
| 15FEB05        6                                                         |
| 16FEB05        6                                                         |
| 17FEB05        6                                                         |
| 18FEB05        6                                                         |
| 21FEB05        6                                                         |
| 22FEB05        6                                                         |
| 23FEB05        6                                                         |
| 24FEB05        6                                                         |
| 25FEB05        6                                                         |
| 28FEB05        6                                                         |
| 01MAR05        6                                                         |
| 02MAR05        6                                                         |
| 03MAR05        6                                                         |
| 04MAR05        6                                                         |
| 07MAR05        6                                                         |
| 08MAR05        6                                                         |
| 09MAR05        6                                                         |
| 10MAR05        6                                                         |
| 11MAR05        6                                                         |
| 14MAR05        6                                                         |
| 15MAR05        6                                                         |
| 17MAR05        6                                                         |
| 09APR05         7                                                        |
| 10APR05         7                                                        |
| 28MAY05         7                                                        |
| 29MAY05         7                                                        |
| 30MAY05      4 6                                                         |
| 03JUN05        6                                                         |
| 01JUL05        6                                                         |
| 04JUL05       56                                                         |
| 05JUL05        6                                                         |
| 06JUL05        6                                                         |
| 07JUL05        6                                                         |
| 08JUL05        6                                                         |
| 25AUG05        6                                                         |
| 26AUG05        6                                                         |
| 05SEP05      456                                                         |
---------- -------------------------------- --------------------------------
 A total of 491 Holidays are defined.

-----------------------------------------------
| BAD HOLIDAYS AND EXCEPTIONS IN CALENDARS    |
| CAL  DATE                NOTE               |
!---- -------  -------------------------------+
|  3  04JUL01  Holiday before Project Start   |
|  4  24NOV05  Holiday after Project Finish   |
|  4  19DEC05  Holiday after Project Finish   |
|  4  26DEC05  Holiday after Project Finish   |
|  4  02JAN06  Holiday after Project Finish   |
|  5  01JAN01  Holiday before Project Start   |
|  5  28MAY01  Holiday before Project Start   |
|  5  04JUL01  Holiday before Project Start   |
|  5  24NOV05  Holiday after Project Finish   |
|  5  15DEC05  Holiday after Project Finish   |
|  5  19DEC05  Holiday after Project Finish   |
|  5  26DEC05  Holiday after Project Finish   |
|  5  02JAN06  Holiday after Project Finish   |
|  5  09JAN06  Holiday after Project Finish   |
|  5  16JAN06  Holiday after Project Finish   |
|  5  23JAN06  Holiday after Project Finish   |
|  5  30JAN06  Holiday after Project Finish   |
|  5  01FEB06  Holiday after Project Finish   |
|  5  06FEB06  Holiday after Project Finish   |
|  5  13FEB06  Holiday after Project Finish   |
|  6  02JUL01  Holiday before Project Start   |
|  6  15NOV05  Holiday after Project Finish   |
|  6  21NOV05  Holiday after Project Finish   |
|  6  28NOV05  Holiday after Project Finish   |
|  6  01DEC05  Holiday after Project Finish   |
|  6  05DEC05  Holiday after Project Finish   |
|  6  12DEC05  Holiday after Project Finish   |
|  6  19DEC05  Holiday after Project Finish   |
|  6  26DEC05  Holiday after Project Finish   |
|  7  14APR01  Holiday before Project Start   |
|  7  26MAY01  Holiday before Project Start   |
|  7  17DEC05  Holiday after Project Finish   |
|  7  24DEC05  Holiday after Project Finish   |
|  7  31DEC05  Holiday after Project Finish   |
|  7  01JAN06  Holiday after Project Finish   |
|  B  05JAN01  Holiday before Project Start   |
|  B  12JAN01  Holiday before Project Start   |
|  B  19JAN01  Holiday before Project Start   |
|  B  26JAN01  Holiday before Project Start   |
|  B  02FEB01  Holiday before Project Start   |
|  B  09FEB01  Holiday before Project Start   |
|  B  16FEB01  Holiday before Project Start   |
|  B  23FEB01  Holiday before Project Start   |
|  B  02MAR01  Holiday before Project Start   |
|  B  09MAR01  Holiday before Project Start   |
|  B  16MAR01  Holiday before Project Start   |
|  B  23MAR01  Holiday before Project Start   |
|  B  30MAR01  Holiday before Project Start   |
|  B  04JUL01  Holiday before Project Start   |
|  C  04JUL01  Holiday before Project Start   |
----- -------  --------------------------------
 50 bad Holidays and Exceptions to calendars exist.
    NOTE: Holidays after Project Finish may be useful if the project is
        extended.  It is not incorrect to include them in any case.
    NOTE: Dates were advanced or delayed to the nearest workday due to the
        current setting in Global Calendars.  To stop P3 from moving the
        holiday, deselect the option box under Tools, Calendars, Global
        Calendar, Standard.


AUTOCOST RULES CHECK

    NOTE: You have not entered an Identifier to verify review of Autocost
        Rules.  This is not required, but is a good practice.  Suggest that
        you enter your initials or any 4 character name to indicate who
        is responsible for the current settings.  You can do this by
        selecting Tools, Options, Autocost Rules, Identifier.

    NOTE: You have not entered a date to verify your last review of Autocost
        Rules.  This is not required but is good practice.  Suggest that you
        enter the date of last review or update of the Autocost Rules. You
        can do this by selecting Tools, Options, Autocaost Rules, Date.

    Rule 1: Link remaining duration and schedule percent complete? Yes
        NOTE: This is the standard setting and should be used unless using
            nonlinear resource distributions. 

    Rule #2: Freeze resource units per time period? No
        NOTE: This is a non-standard setting that adjusts workcrew size
            in response to earned progress so as to meet planned finish.
                In either case, this setting has no effect on your schedule
                unless you are using resources.

    Rule #3a: Calculation for estimate to complete? Subtract actual from EAC
        NOTE: Use this method on fixed-price contracts, as it doesn't allow
            you to exceed your budget.

    Rule #3b: Allow 'negative estimate to complete'? No
        CAUTION: With this setting, P3 will not allow a negative calculation
            Instead, it will automatically set 'Estimate to Complete' = 0
            and change your 'Estimate at Completion' = 'Actual to Date.'

    Rule #4a: When Quantities change, recompute Budget Costs? No
        NOTE: This is the standard setting. Use this when you do not
            track costs or when the budget is known.

    Rule #4b: When Quantities change, recompute Actual Costs? Yes
        CAUTION: Only use this setting when tracking costs but Actual Costs
            are not tabulated.  It is dangerous to estimate actuals.

    Rule #4c: When Quantities change, recompute Est. to Complete Costs? Yes
        NOTE: This is the standard setting. Estimates to complete should
            be related to quantities remaining.

    Rule #5a: Update % complete against budget to recompute Budget? Yes
        CAUTION: Only use this setting when tracking costs but the budget
            isn't fixed.

    Rule #5b: Update % complete against budget to recompute Cost? Yes
        CAUTION: Only use this setting when tracking costs but Actual Costs
            are not tabulated.  It is dangerous to estimate actuals.

    Rule #6: Actual linked to date and actual this period? Yes
        NOTE: Use this setting if you are tracking costs per update period.

    Rule #7: Budget linked to EAC for non-progressed acts? Yes
        CAUTION: This setting should only be used during the planning stages
            of a project.  Until set to off, P3 will not calculate variance.

    Rule #8: Variance is calculated as: Budget minus Estimate At Completion.
        NOTE: This is the default setting that displays variances as
            negative values.

    Recalculate and Store Cost during each schedule computation? No
        NOTE: This is the correct setting if your project does not calculate
            costs or if it does not use non-linear resource distributions or
            costs associated with Hammocks or Expected Finish Constraints.

    Apply the above rules by Cell or Resource? Cell
        NOTE: This is the default setting.  It will register your entries as
            you move your cursor from field to field.

CPM RULES CHECK

    Scheduling Method is set to Retained Logic.
        NOTE: This is the normal method for predicting status with out-of
            sequence progress.

    Schedule Method is also set to Contiguous Activities.
        CAUTION: This is the standard setting but will produce different
            results for activity chains identified in later Interruptible
            Activities Report.  Use this setting for projects that wait 
            until all resources may be employed without a break.

    Total Float Calculation uses Start Dates to calculate Total Float.
        NOTE: This will result in the same answer except for interruptible
            activities and Hammock activities.  Interruptible activities
            work better using Finish Dates and Hammock activities work
            better using the Start Dates setting.

================================ ACTIVITIES ================================

------------------------- ACTIVITY STANDARDS CHECK -------------------------
There are a greater number of activities than allowed by the standard.
The maximum duration of some activities is greater than allowed by standards
Tasks (not milestones) with zero duration are used in violation of standards
Start Milestone Activities are used in violation of standards.
Standard Start Flag Activities are not used on this project.
Standard Finish Flag Activities are not used on this project.
Hammock Activities are used in violation of standards.
Activity Descriptions are not left-justified, in violation of standards.
----------------------------------------------------------------------------

    There are a total of 5023 activities in this schedule.
    Listed by category type, the totals are;
        Fixed Duration CPM Activity:
            Tasks             = 4981 
        Resource-driven Duration CPM Activities:
            Independent       = 0 
            Meeting           = 0 
        Zero Duration Mileposts:
            Start Milestones  = 25 
            Finish Milestones = 10 
            Start Flags       = 0 
            Finish Flags      = 0 
        Summary (Non-CPM) Duration Activities:
            Hammocks          = 7 
            WBS               = 0 

    CAUTION: Many contracts specify the maximum or minimum number of
        activities allowed in the schedule.  For this purpose, the first
        two categories above are usually totaled = 4981 activities.

  Many specifications limit the percentage of activities that can be
  critical or near-critical in the Baseline Schedule.  A typical upper
  limit is a maximum of 30% critical and 50% critical or near-critical.

    Critical Activities = 3.98%
    Critical and Near-
    Critical Activities = 4.76% (based upon Total Float less than 11 .)

Of the 4981 CPM-type activities in the schedule,
        Average duration of these activities was 11.31 Days.
        Mean of the durations was 449.00 Days.
        Standard Deviation of the difference was 22.31 Days.

----------------------------------------------------------------------------
| ACTIVITY DURATION HISTOGRAM (excluding Milestones)                       |
| DURATION   COUNT  GRAPH                                                  |
!---------- ------  -------------------------------------------------------+
|     0         31  #                                                      |
|    1-5      2604  #######################################################|
|    6-10      454  ##########                                             |
|   11-15     1139  #########################                              |
|   16-20      131  ###                                                    |
|   21-25       87  ##                                                     |
|   26-30      368  ########                                               |
|   31-35        5  #                                                      |
|   36-40       11  #                                                      |
|   41-45        1  #                                                      |
|   46-50       17  #                                                      |
|   51-55       11  #                                                      |
|   56-60       43  #                                                      |
|   61-65        2  #                                                      |
|   66-70        2  #                                                      |
|   71-75        3  #                                                      |
|   76-80        6  #                                                      |
|   81-85        1  #                                                      |
|   86-90       23  #                                                      |
|   91-95        1  #                                                      |
|   96-100       5  #                                                      |
|  101-105       0                                                         |
|  106-110       2  #                                                      |
|  111-115       0                                                         |
|  116-120       3  #                                                      |
|  121-125       0                                                         |
|  126-130       0                                                         |
|  131-135       0                                                         |
|  136-140       6  #                                                      |
|  141-145       0                                                         |
|  146-150       1  #                                                      |
|  151-155       1  #                                                      |
|  156-160      13  #                                                      |
|  161-165       0                                                         |
|  166-170       1  #                                                      |
|  171-175       0                                                         |
|  176-180       1  #                                                      |
|  181-185       0                                                         |
|  186-190       0                                                         |
|  191-195       0                                                         |
|  196-200       2  #                                                      |
|  201-205       0                                                         |
|  206-210       1  #                                                      |
|  211-215       0                                                         |
|  216-220       0                                                         |
|  221-225       0                                                         |
|  226-230       0                                                         |
|  231-235       1  #                                                      |
|  236-240       0                                                         |
|  241-245       0                                                         |
|  246-250       0                                                         |
|  251-255       0                                                         |
|  256-260       0                                                         |
|  261-265       0                                                         |
|  266-270       1  #                                                      |
|  271-275       0                                                         |
|  276-280       2  #                                                      |
|  281-285       0                                                         |
|  286-290       0                                                         |
|  291-295       0                                                         |
|  296-300       0                                                         |
|  301-305       0                                                         |
|  306-310       0                                                         |
|  311-315       0                                                         |
|  316-320       0                                                         |
|  321-325       0                                                         |
|  326-330       0                                                         |
|  331-335       0                                                         |
|  336-340       0                                                         |
|  341-345       0                                                         |
|  346-350       0                                                         |
|  351-355       0                                                         |
|  356-360       0                                                         |
|  361-365       0                                                         |
|  366-370       0                                                         |
|  371-375       0                                                         |
|  376-380       0                                                         |
|  381-385       0                                                         |
|  386-390       0                                                         |
|  391-395       0                                                         |
|  396-400       0                                                         |
|  401-405       0                                                         |
|  406-410       0                                                         |
|  411-415       0                                                         |
|  416-420       0                                                         |
|  421-425       0                                                         |
|  426-430       0                                                         |
|  431-435       0                                                         |
|  436-440       0                                                         |
|  441-445       0                                                         |
|  446-450       0                                                         |
|  451-455       0                                                         |
|  456-460       0                                                         |
|  461-465       0                                                         |
|  466-470       0                                                         |
|  471-475       0                                                         |
|  476-480       0                                                         |
|  481-485       0                                                         |
|  486-490       0                                                         |
|  491-495       0                                                         |
|  496-500       0                                                         |
|  501-505       0                                                         |
|  506-510       0                                                         |
|  511-515       0                                                         |
|  516-520       0                                                         |
|  521-525       0                                                         |
|  526-530       0                                                         |
|  531-535       0                                                         |
|  536-540       0                                                         |
|  541-545       0                                                         |
|  546-550       0                                                         |
|  551-555       0                                                         |
|  556-560       0                                                         |
|  561-565       0                                                         |
|  566-570       0                                                         |
|  571-575       0                                                         |
|  576-580       0                                                         |
|  581-585       0                                                         |
|  586-590       0                                                         |
|  591-595       0                                                         |
|  596-600       0                                                         |
|  601-605       0                                                         |
|  606-610       0                                                         |
|  611-615       0                                                         |
|  616-620       0                                                         |
|  621-625       0                                                         |
|  626-630       0                                                         |
|  631-635       0                                                         |
|  636-640       0                                                         |
|  641-645       0                                                         |
|  646-650       0                                                         |
|  651-655       0                                                         |
|  656-660       0                                                         |
|  661-665       0                                                         |
|  666-670       0                                                         |
|  671-675       0                                                         |
|  676-680       0                                                         |
|  681-685       0                                                         |
|  686-690       0                                                         |
|  691-695       0                                                         |
|  696-700       0                                                         |
|  701-705       0                                                         |
|  706-710       0                                                         |
|  711-715       0                                                         |
|  716-720       0                                                         |
|  721-725       0                                                         |
|  726-730       0                                                         |
|  731-735       0                                                         |
|  736-740       0                                                         |
|  741-745       0                                                         |
|  746-750       0                                                         |
|  751-755       0                                                         |
|  756-760       0                                                         |
|  761-765       0                                                         |
|  766-770       0                                                         |
|  771-775       0                                                         |
|  776-780       0                                                         |
|  781-785       0                                                         |
|  786-790       0                                                         |
|  791-795       0                                                         |
|  796-800       0                                                         |
|  801-805       0                                                         |
|  806-810       0                                                         |
|  811-815       0                                                         |
|  816-820       0                                                         |
|  821-825       0                                                         |
|  826-830       0                                                         |
|  831-835       0                                                         |
|  836-840       0                                                         |
|  841-845       0                                                         |
|  846-850       0                                                         |
|  851-855       0                                                         |
|  856-860       0                                                         |
|  861-865       0                                                         |
|  866-870       0                                                         |
|  871-875       0                                                         |
|  876-880       0                                                         |
|  881-885       0                                                         |
|  886-890       0                                                         |
|  891-895       0                                                         |
|  896-900       1  #                                                      |
----------------------------------------------------------------------------
 4981 of Tasks and Resource Activities (Non-Milestone) are represented above.
 2322 activities are 1 to 1 Days long.
 The shortest duration is 0 Days.
 The longest duration is 898 Days.
    NOTE: Many contracts specify the minimum or maximum allowable durations
        of activities included in the schedule.  It is best to not consider
        milestones or summary activities when qualifying durations.  The 
        analysis above only considers Task, Independent, and Meeting type
        activities and excludes all others.

----------------------------------------------------------------------------
| ACTIVITY DURATIONS GREATER THAN 10                                       |
|   ACT     DURATION FLOAT  ACT TYPE  TITLE                                |
+---------- ======== ----- ---------- -------------------------------------+
|EC17TGL008       12  1050 Task       Miscellaneous Power Devices          |
|EC17TGL011       27  1033 Task       Getaway Ductbanks                    |
|EC17TGL012       74   986 Task       Install ductbank with conduit        |
|EC17TGL014       46  1016 Task        AC Metering Equipment/Panels/ATS    |
|EC17TGL015       17   850 Task       Install Substation Battery System    |
|EC17TGL022       90   841 Task       Factory Fabrication for Transformers |
|EC17TGL025       46   841 Task       Receive & Install Transformers       |
|EC17TGL028       60   850 Task       Factory Fabrication for DC Switchgea |
|EC17TGL031       50   850 Task       Receive & Install DC Switchgear      |
|EC17TGL034       80   865 Task       Factory Fabrication for Rectifier    |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 1899 activities had long durations.
    CAUTION: Many specifications require activities to be defined with dur-
        ations less than a set number.  The intent of this requirement is to
        allow for better monitoring and control of the work described by the
        activity.  Typically, the reviewer is allowed to wave this require-
        ment in the case of Hammocks or deliveries, etc.

----------------------------------------------------------------------------
| SUSPICIOUS ACTIVITY DURATIONS                                            |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- ======== ----- ------------------------------------------------+
|EC17TGL008       12  1050 Miscellaneous Power Devices                     |
|EC17TGL011       27  1033 Getaway Ductbanks                               |
|EC17TGL012       74   986 Install ductbank with conduit                   |
|EC17TGL013        8  1054 Install Lighting Fixtures                       |
|EC17TGL014       46  1016  AC Metering Equipment/Panels/ATS               |
|EC17TGL015       17   850 Install Substation Battery System               |
|EC17TGL018        8  1042 RTU/SCADA System                                |
|EC17TGL025       46   841 Receive & Install Transformers                  |
|EC17TGL043       52   865 Receive & Install Medium Voltage Switchgear     |
|EC17TGL044        8   865 Install Copper Bus & Complete Innerconnects     |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 529 activities had suspicious activity durations.
    CAUTION: Some schedulers arbitrarily modify activity durations to make
        various near-critical logic chains match total durations exactly,
        thus artificially producing multiple critical paths.  The above
        listed activities have 'odd' durations, which should be
        investigated further, especially if they are critical.

----------------------------------------------------------------------------
| SUSPICIOUS REMAINING DURATIONS                                           |
|   ACT     ORIG. REMAIN  %  TITLE                                         |
+---------- ----- ===== ---- ----------------------------------------------+
|EMSMT02320    15    30    0 SMT-2050 Temp Earth Ret Strc -54th St Sta. - F|
----------------------------------------------------------------------------
 1 activities had suspicious remaining durations.
    CAUTION: Remaining Duration for unstarted activities should equal the
        Original Duration.  In no case should it be greater than Original
        Duration without an explanation.

----------------------------------------------------------------------------
| ACTIVITIES MISSING DESCRIPTIONS                                          |
|   ACT        TYPE     START   FINISH % CMP FLOAT DURATION                |
+---------- ---------- ------- ------- ----- ----- ------------------------+
|SPSMT01090 Task       16JUL01 16JUL01     0     1                         |
----------------------------------------------------------------------------
 1 activities were missing descriptions.
    CAUTION: All activities should have descriptive titles.  This title
        serves as a form of Scope Of Work definition and thus further
        defines the contract.

 Notice To Proceed is on 16JUL01.

----------------------------------------------------------------------------
| UNUSUAL NUMBER OF 'MOBILIZATION' ACTIVITIES                              |
|   ACT      START   FINISH TITLE                                          |
+---------- ------- ------- ===============================================+
|PAMOB00010 17JUL01-16JUL01 Mobilization Initial                           |
|PAMOB00011 16OCT01-16OCT01 Mobilization 5%                                |
|PAMOB00021 16JAN02-16JAN02 Mobilization 20%                               |
|PAMOB00031 19SEP02-19SEP02 Mobilization 45%                               |
|PAMOB00041 19NOV02-19NOV02 Mobilization 50%                               |
|PAMOB00051 19JAN03-19JAN03 Mobilization 60%                               |
|PAMOB00061 21MAR03-21MAR03 Mobilization 70%                               |
|PAMOB00071 21MAY03-21MAY03 Mobilization 80%                               |
|PAMOB00081 21JUL03-21JUL03 Mobilization 90%                               |
|PAMOB00091 13OCT05-13OCT05 Mobilization 100%                              |
----------------------------------------------------------------------------
 10 activities had 'MOBILIZE' in their descriptions.

 0 activities had 'SUBSTANTIAL COMPLETION' in their descriptions.
    CAUTION: There does not appear to be a Substantial Completion in this
        schedule. Regardless of whether it is called out by specification,
        it is widely recognized legally as the termination point for
        the assessment of Liquidated Damages and thus should be included.

----------------------------------------------------------------------------
| ACTIVITIES WITH WORK PERCENTAGES IN THEIR TITLE                          |
|   ACT     STR DATE FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|PAMOB00011 16OCT01      0 Mobilization 5%                                 |
|PAMOB00021 16JAN02      0 Mobilization 20%                                |
|PAMOB00031 19SEP02      0 Mobilization 45%                                |
|PAMOB00041 19NOV02      0 Mobilization 50%                                |
|PAMOB00051 19JAN03      0 Mobilization 60%                                |
|PAMOB00061 21MAR03      0 Mobilization 70%                                |
|PAMOB00071 21MAY03      0 Mobilization 80%                                |
|PAMOB00081 21JUL03      0 Mobilization 90%                                |
|PAMOB00091 13OCT05      0 Mobilization 100%                               |
----------------------------------------------------------------------------
 9 activities use work percentages in their titles.
    CAUTION: The above activities are described in terms of a percentage of
        a task.  This is poor scheduling practice as it cannot be accurately
        statused.  Suggest that you use physical lengths of progress such as
        "INSTALL CULVERT, 0 - 100 METERS" or "POUR FOUNDATION, 1-3 GRIDLINE".

----------------------------------------------------------------------------
| POSSIBLE REVIEW OR APPROVAL ACTIVITIES                                   |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|EC17TGL021       10   841 Approval Time for Transformers                  |
|EC17TGL027       10   850 Approval Time for DC Switchgear                 |
|EC17TGL033       10   865 Approval Time for Recitifer                     |
|EC17TGL039       10   865 Approval Time for Medium Voltage Switchgear     |
|EC54TGL140       10   921 Approval Time for Transformers                  |
|EC54TGL145        6   921 Review & Connect to Existing DC Switchgear      |
|EC54TGL146        6   921 Review & Connect to Existing Rectifiers         |
|EC54TGL147        4   921 Review & Connect to Existing Medium Voltage Swgr|
|ECHARGL063       10   936 Approval Time for Transformers                  |
|ECHARGL069       10   954 Approval Time for DC Switchgear                 |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 429 review or approval activities exist.
    CAUTION: You should check the above activities to ensure that the time
        allotted is within the specified minimums.  You should also
        scrutinize any activity which lists work responsibilities for the
        Owner or A/E as this might compromise you legally later.

----------------------------------------------------------------------------
| ACTIVITIES POSSIBLY DEALING WITH UTILITIES                               |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|EC54CGL281        5  1077 Relocate Ameritech Phone Service                |
|EC54YGL328        5   934 Pole Bases                                      |
|EC54YGL331        6   934 Erect light poles and install fixtures          |
|EC54YGL333        7   749 Pole Bases                                      |
|EC54YGL336        8   749 Erect light poles and install fixtures          |
|EC54YGL402       22   841 Light Pole Bases                                |
|EC54YGL403       36   841 Site Lighting Poles & Fixtures                  |
|ECKOSGL312        5   750 Relocate Ameritech Phone Service                |
|ECPOLTL256        5   842 Relocate Ameritech Phone Service                |
|EM343XX104        5   344 TEMP R.ROUND - 343 - SHORE TOWERS               |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 40 utility activities exist.
    CAUTION: Typically, utility companies are considered 'third-parties.'
        They are not under the control of either the Owner or Contractor.
        Delays caused by the utility company are typically considered as
        excusable and sometimes compensible by the Owner, even if the owner
        had no direct hand in the cause.  Check to see that the time allowed
        is per specification.  Ideally, it would be nice to not have these
        activities not on the critical path, but often they are.

----------------------------------------------------------------------------
| MAJOR MATERIALS DELIVERY ACTIVITIES                                      |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|EC17TGL024        2   841 Deliver Transformers to Jobsite                 |
|EC17TGL030        2   850 Deliver DC Switchgear to Jobsite                |
|EC17TGL036        2   865 Deliver Rectifier to Jobsite                    |
|EC17TGL042        2   865 Deliver Medium Voltage Switchgear to Jobsite    |
|EC54TGL143        2   921 Deliver Transformers to Jobsite                 |
|ECHARGL066        2   936 Deliver Transformers to Jobsite                 |
|ECHARGL072        2   954 Deliver DC Switchgear to Jobsite                |
|ECHARGL078        2   944 Deliver Rectifier to Jobsite                    |
|ECHARGL084        2   944 Deliver Medium Voltage Switchgear to Jobsite    |
|ECHERGL109        2   911 Deliver DC Switchgear to Jobsite                |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 27 major material delivery activities exist.
    CAUTION: You should check the above activities to ensure all important
        pieces of long-lead items are accounted for.  You should also check
        that such activities are scheduled based on 7-days per week (not
        workday) schedules.

----------------------------------------------------------------------------
| ACTIVITIES DEALING WITH TEMPORARY ISSUES                                 |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|EC17TGL004        5   893 Temporary Power & Lighting                      |
|EC343XX100       30   399 TEMP ELEC KEELER TO BELT BRIDGE                 |
|EC343XX110        2   120 TEMP R.ROUND 343  TEMP ELEC TRACK POWER         |
|EC398SB100        2   333 LAR-50TH -411 TO 398 TEMP ELEC                  |
|EC54CGL269       15  1067 Temporary Power & Lighting                      |
|EC54TGL125        5  1067 Temporary Power & Lighting                      |
|EC54YGL385       30   584 Temporary Power & Lighting                      |
|EC54YGL423       30   999 Temporary Power & Lighting                      |
|ECBSMGL370        2  1064 Temporary Power & Lighting                      |
|ECBSWGL339        2  1019 Temporary Power & Lighting                      |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 85 activities dealing with temporary issues exist.
    CAUTION: You should check the above activities to ensure all proposed
        actions are acceptable.  Sometimes, Contractors plan to create
        temporary barriers, access points, or structures which would
        conflict with Owner Operations or safety rules in effect. Approval
        of this in a schedule may constitute an approval of the plan.

----------------------------------------------------------------------------
| DUPLICATE ACTIVITY DESCRIPTIONS                                          |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ================================================+
|EC000090          1  1081 Substn.-Elect.-Des Mtg.                         |
|ECALL010          1  1081 Substn.-Elect.-Des Mtg.                         |
|                                                                          |
|EC0010            0  1082 Milestone 4-1: Signal Block Diagram             |
|PAM/S00010        0  1444 Milestone 4-1: Signal Block Diagram             |
|                                                                          |
|EC107TW265        2    52 SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|EC108TW270        2    52 SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|                                                                          |
|EC107TW266        2    52 SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
|EC108TW271        2    52 SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
|                                                                          |
|EC108TW255        2    52 SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER   |
|EC109TW260        2    52 SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER   |
|                                                                          |
|EC108TW256        2    52 SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM       |
|EC109TW261        2    52 SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM       |
|                                                                          |
----------------------------------------------------------------------------
 12 duplicate activity descriptions exist.
    CAUTION: Activities with duplicate descriptions are confusing to track.
        Even though they may be coded for different areas, this is not
        always clear on print-outs.  Suggest that you start each description
        with 'AREA A - (description)' instead.

----------------------------------------------------------------------------
| MILESTONES CODED AS ACTIVITIES                                           |
|  ACT ID      TYPE     DUR  TITLE                                         |
+---------- ---------- ----- ----------------------------------------------+
|EC0010     Task           0 Milestone 4-1: Signal Block Diagram           |
|EM343NB170 Task           0 KEEL. S. RET.WL - 343 - FENCE                 |
|EM343SB258 Task           0 KEEL WALL N. - 342+50 - FENCE                 |
|EM357XX110 Task           0 KOSTNER XING - 356+50 - ASPHALT               |
|EM357XX112 Task           0 KOSTNER XING - 356+50 - CURB & GUTTER         |
|EM357XX114 Task           0 KOSTNER XING - 356+50 - SIDEWALK              |
|EM357XX116 Task           0 KOSTNER XING - 356+50 - WATERLINE             |
|EM414XX118 Task           0 BUSWAY - 414 - CURB AND GUTTER                |
|EM414XX120 Task           0 BUSWAY - 414 - SIDEWALK                       |
|EM414XX136 Task           0 BUSWAY - 414 - GUARD RAIL                     |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 31 such activities were found.
    NOTE: The above activities should have durations or be coded as 
        milestones.  Otherwise you have to deal with an early finish that
        is earlier than the early start and that can give you headaches.

----------------------------------------------------------------------------
| BASELINE MILESTONES                                                      |
|  ACT ID      TYPE     DATE  TITLE                                        |
+---------- --------- ------- ---------------------------------------------+
|PAM/S00010 Milestone 30OCT01 Milestone 4-1: Signal Block Diagram          |
|PAM/S00090 Milestone 13JUN03 Milestone 2-1: TW, Struct., & Station        |
|PAM/S00100 Milestone 04FEB03 Milestone 3-5: Substantial Compl.            |
|PAM/S00110 Milestone 13OCT05 Milestone 5-0: Project Completion            |
|PAM/S00240 Milestone 04JAN02 Milestone 1-1: 17th Str. Substn. finish      |
|PAM/S00250 Milestone 16JUL01 Milestone 1-1:17th Str. Substn. start        |
|PAM/S00260 Milestone 13MAY02 Milestone 1-2: Hermitage Substn. finish      |
|PAM/S00270 Milestone 05JAN02 Milestone 1-2: Hermitage Substn. start       |
|PAM/S00280 Milestone 28OCT02 Milestone 1-3: Substantil Compl.             |
|PAM/S00290 Milestone 12SEP03 Milestone 2-1: TW, Struct., & Station        |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 35 milestones found.
    NOTE: The only milestones that should be in a Baseline Schedule are
        contractually required ones.  Verify that the above list is
        reasonable and inclusive.

----------------------------------------------------------------------------
| ACTIVITY DISTRIBUTION HISTOGRAM (using 1/2 Float)                        |
|   MONTH   ACTIVE  GRAPH                                                  |
!---------- ------  -------------------------------------------------------+
| Jul 2001       3  #                                                      |
| Aug 2001       4  #                                                      |
| Sep 2001      13  ##                                                     |
| Oct 2001      28  ###                                                    |
| Nov 2001      39  ####                                                   |
| Dec 2001      92  ##########                                             |
| Jan 2002     297  ##############################                         |
| Feb 2002     308  ###############################                        |
| Mar 2002     241  ########################                               |
| Apr 2002     176  ##################                                     |
| May 2002     180  ##################                                     |
| Jun 2002     176  ##################                                     |
| Jul 2002     236  ########################                               |
| Aug 2002     299  ##############################                         |
| Sep 2002     279  ############################                           |
| Oct 2002     318  ################################                       |
| Nov 2002     396  #######################################                |
| Dec 2002     460  ##############################################         |
| Jan 2003     560  #######################################################|
| Feb 2003     370  #####################################                  |
| Mar 2003     301  ##############################                         |
| Apr 2003     195  ####################                                   |
| May 2003     209  #####################                                  |
| Jun 2003     273  ###########################                            |
| Jul 2003     270  ###########################                            |
| Aug 2003     266  ###########################                            |
| Sep 2003     278  ############################                           |
| Oct 2003     246  #########################                              |
| Nov 2003     149  ###############                                        |
| Dec 2003     138  ##############                                         |
| Jan 2004     153  ################                                       |
| Feb 2004      88  #########                                              |
| Mar 2004     119  ############                                           |
| Apr 2004      64  #######                                                |
| May 2004      12  ##                                                     |
| Jun 2004       6  #                                                      |
| Jul 2004       6  #                                                      |
| Aug 2004       6  #                                                      |
| Sep 2004       7  #                                                      |
| Oct 2004       3  #                                                      |
| Nov 2004       2  #                                                      |
| Dec 2004       2  #                                                      |
| Jan 2005       2  #                                                      |
| Feb 2005       2  #                                                      |
| Mar 2005       2  #                                                      |
| Apr 2005       2  #                                                      |
| May 2005       1  #                                                      |
| Jun 2005       1  #                                                      |
| Jul 2005       2  #                                                      |
| Aug 2005       2  #                                                      |
| Sep 2005       1  #                                                      |
| Oct 2005       2  #                                                      |
----------------------------------------------------------------------------
 7285 activities are planned to be active during the above months.
    NOTE: You should confirm that the schedule is roughly equally detailed
        from the start to the finish of the project.  The above curve should
        be somewhat flat and balanced on both ends.  A lower second half
        might indicate an under-developed finish plan.

        A schedule with an underdeveloped ending indicates that the Contractor
        has not fully taken into account all issues and is thus less accurate.
        It won't do you any good to be on schedule just to find out that the
        finish did not provide enought time to complete.

========================== ACTIVITY CODE ANALYSIS ==========================

-------------------------- CODING STANDARDS CHECK --------------------------
Activity ID Codes are used in violation of standards.
Activity Code Field Definitions are changed in violation of standards.
Activity Code Field Definitions are changed in violation of standards.
WBS Codes are changed in violation of standards.
----------------------------------------------------------------------------

Activity Code Check:

The following code definitions are blank:
    Activity Code "TO BENT",
        Title for code "54090" is missing.
        Title for code "54091" is missing.
        Title for code "55013" is missing.
        Title for code "55023" is missing.
        Title for code "55038" is missing.
        Title for code "55039" is missing.
        Title for code "55040" is missing.
        Title for code "55041" is missing.
        Title for code "55044" is missing.
        Title for code "55045" is missing.
        Title for code "55046" is missing.
        Title for code "55047" is missing.
        Title for code "55048" is missing.
        Title for code "55049" is missing.
        Title for code "55050" is missing.
        Title for code "55051" is missing.
        Title for code "55052" is missing.
        Title for code "55053" is missing.
        Title for code "55054" is missing.
        Title for code "55055" is missing.
        Title for code "55056" is missing.
        Title for code "56036" is missing.
        Title for code "56057" is missing.
        Title for code "57010" is missing.
        Title for code "57014" is missing.
    Activity Code "FROM BENT",
        Title for code "54090" is missing.
        Title for code "54091" is missing.
        Title for code "55013" is missing.
        Title for code "55023" is missing.
        Title for code "55038" is missing.
        Title for code "55039" is missing.
        Title for code "55040" is missing.
        Title for code "55041" is missing.
        Title for code "55044" is missing.
        Title for code "55045" is missing.
        Title for code "55046" is missing.
        Title for code "55047" is missing.
        Title for code "55048" is missing.
        Title for code "55049" is missing.
        Title for code "55050" is missing.
        Title for code "55051" is missing.
        Title for code "55052" is missing.
        Title for code "55053" is missing.
        Title for code "55054" is missing.
        Title for code "55055" is missing.
        Title for code "55056" is missing.
        Title for code "56036" is missing.
        Title for code "56057" is missing.
        Title for code "57010" is missing.
        Title for code "57014" is missing.
    Activity Code "TYPE OF WORK",
        Title for code "BLT" is missing.
        Title for code "CAN" is missing.
        Title for code "COL" is missing.
        Title for code "CWA" is missing.
        Title for code "D/W" is missing.
        Title for code "FPR" is missing.
        Title for code "GRX" is missing.
        Title for code "LDS" is missing.
        Title for code "MIL" is missing.
        Title for code "PAI" is missing.
        Title for code "PLT" is missing.
        Title for code "RCA" is missing.
        Title for code "RST" is missing.
        Title for code "SBA" is missing.
        Title for code "SHO" is missing.
        Title for code "SMT" is missing.
        Title for code "SPE" is missing.
        Title for code "SSL" is missing.
        Title for code "STR" is missing.
        Title for code "STS" is missing.
        Title for code "TIE" is missing.
        Title for code "TMP" is missing.
        Title for code "TRA" is missing.
        Title for code "TTP" is missing.
        Title for code "TTS" is missing.
        Title for code "TW " is missing.
    Activity Code "WORK TYPE",
        Title for code "264" is missing.
    Activity Code "LOCATION-CTA",
        Title for code "GEN " is missing.
        Title for code "HER " is missing.
    Activity Code "SLOW ZONE TYPE",
        Title for code "1  " is missing.
        Title for code "2  " is missing.
        Title for code "3  " is missing.
        Title for code "4  " is missing.
        Title for code "K/D" is missing.
    Activity Code "Responsibility",
        Title for code "K/D  " is missing.
    Activity Code "Spec. Division",
        Title for code "03300" is missing.
        Title for code "05101" is missing.
         [List trimed for demostration]
        Title for code "9901    " is missing.
        Title for code "9901.10 " is missing.
    Activity Code "Units",
        Title for code "BF" is missing.
        Title for code "CY" is missing.
        Title for code "EA" is missing.
        Title for code "LB" is missing.
        Title for code "LF" is missing.
        Title for code "LS" is missing.
        Title for code "SF" is missing.
        Title for code "SY" is missing.
        Title for code "TF" is missing.
        Title for code "TN" is missing.
    Field ID Code "LOC. - Primary",
        Title for code "ALL" is missing.
        Title for code "GL0" is missing.
        Title for code "M/S" is missing.
        Title for code "O&P" is missing.
    Field ID Code "LOC. - Secondary",
        Title for code "LW" is missing.
        Title for code "NM" is missing.
    ------------------------------
     656 code titles are missing.
        ERROR: Code Titles are automatically used in reports and plots
            whenever you group or page break based upon this field.  As a
            default, if the Field Title is blank P3 will only print the
            actual code value.

Suggest you delete unused ID Field "NUMBER".

Suggest you delete unused Code Field "SECOND TIER SUB".

Suggest you delete unused Code Field "Phase".

    Duplicate Code Titles for Code PLF and Code TPL.
    Duplicate Code Titles for Code DOU  and Code DOUG.
    Duplicate Code Titles for Code MBE and Code WBE.
    Duplicate Code Titles for Code EA and Code EC.
    Duplicate Code Titles for Code EA and Code ED.
    Duplicate Code Titles for Code EC and Code ED.
    Duplicate Code Titles for Code BTB and Code TOB.
    -------------------------------------
     7 duplicate code titles exist.
    ERROR: The same code field description has been used for two different
        codes in the same category.  One of these should be deleted to
        prevent mistakes and confusion.

----------------------------------------------------------------------------
| MISSING ACTIVITY ID FIELD DEFINITIONS                                    |
|   ACT     ID FIELD NAME  ACTIVITY TITLE                                  |
+---------- ============== ------------------------------------------------+
|EC000090   Project ID     Substn.-Elect.-Des Mtg.                         |
|EC0010     Project ID     Milestone 4-1: Signal Block Diagram             |
|EC105TW275 Project ID     SP TRK-#9 TO - Lake Conn TR1  TRACTION POWER    |
|EC105TW276 Project ID     SP TRK-#9 TO - Lake Conn TR1  SIGNAL/COM        |
|EC107TW265 Project ID     SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|EC107TW266 Project ID     SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
|EC108TW255 Project ID     SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER   |
|EC108TW256 Project ID     SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM       |
|EC108TW270 Project ID     SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|EC108TW271 Project ID     SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 12327 Activity ID Fields have missing code definitions.
    ERROR: The above activities have entries in the listed field that do
        not match any of the legal values listed in the Activity ID Field
        Dictionary.  Enter and define the above codes or correct.

----------------------------------------------------------------------------
| BLANK ACTIVITY CODES                                                     |
|   ACT       CODE FIELD   ACTIVITY TITLE                                  |
+---------- ============== ------------------------------------------------+
|EC000090   TO BENT        Substn.-Elect.-Des Mtg.                         |
|EC0010     TO BENT        Milestone 4-1: Signal Block Diagram             |
|EC105TW275 TO BENT        SP TRK-#9 TO - Lake Conn TR1  TRACTION POWER    |
|EC105TW276 TO BENT        SP TRK-#9 TO - Lake Conn TR1  SIGNAL/COM        |
|EC107TW265 TO BENT        SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|EC107TW266 TO BENT        SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
|EC108TW255 TO BENT        SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER   |
|EC108TW256 TO BENT        SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM       |
|EC108TW270 TO BENT        SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER   |
|EC108TW271 TO BENT        SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM       |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 34260 blank codes exist in this project.
    ERROR: It is easy to miss entering a code field when building a
        schedule.  It is important that all activities have a code so that
        they won't be overlooked in reports, filters, and views.  Suggest
        that you look for a similar activity and use the code found there.
        If no code applies, consider 'GENERAL' or 'OVERVIEW.'
    NOTE: Any Activty Code Fields that are complety unused will not be
        reported upon in the above listing.

----------------------------------------------------------------------------
| ACTIVITY CODES NOT FOUND IN DICTIONARY                                   |
|   ACT      CATEGORY     CODE    ACTIVITY TITLE                           |
+---------- ---------- ========== -----------------------------------------+
|EC121TL565 TO BENT         52006 ELEV ST-POLK  18TH ST TRACTION POWER     |
|EC121TL566 TO BENT         52006 ELEV ST-POLK  18TH ST SIGNAL             |
|EC122TL560 TO BENT         52010 ELEV ST-POLK  18TH ST TRACTION POWER     |
|EC122TL561 TO BENT         52010 ELEV ST-POLK  18TH ST SIGNAL             |
|EC124TL555 TO BENT         52012 ELEV ST-POLK  18TH ST TRACTION POWER     |
|EC124TL556 TO BENT         52012 ELEV ST-POLK  18TH ST SIGNAL             |
|EC126TL550 TO BENT         52016 ELEV ST-POLK  18TH ST TRACTION POWER     |
|EC126TL551 TO BENT         52016 ELEV ST-POLK  18TH ST SIGNAL             |
|EC127TL540 TO BENT         52021 ELEV ST-POLK  18TH ST TRACTION POWER     |
|EC127TL541 TO BENT         52021 ELEV ST-POLK  18TH ST SIGNAL             |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 3302 codes were not found in the dictionary.
    ERROR: You can have P3 automatically validate added Activity IDs to
        verify that the Activity ID Code matches one in the dictionary so
        that you do not have this situation.

EXPANDED ACTIVITY ID FIELD LAYOUT (# Activities):
    Project ID
        (    0) Electrical                                      
        (  833) Electrical                                      
        (    0) Electrical                                      
        (  761) Embankment Section                              
        (   43) Project Administration                          
        (  844) Substructure - Elevated Section                 
        (  485) Super Structure - Elevated Section              
        ( 2057) Stations & Buildings                            
    LOC. - Primary
        (   84) 17th Street Substation                          
        (    9) 18th Street Station                             
        (  137) Belt Line Bridge                                
        (    7) Laramie St. to 50th St.                         
        (   34) Laramie Street Area                             
        (   32) 54th St. - Laramie St. (Station Area 425-411)   
        (   19) Busway                                          
        (    7) 54th Street Area                                
        (    7) 54th & Cermak Station                           
        (  102) 54th and Cermak                                 
        (  215) 54th Yard                                       
        (    8) Administration                                  
        (    1) Code "       ALL"
        (   15) Vehicle Wash Facility                           
        (   43) Track and Signal                                
        (   13) Signalman's Facility                            
        (   59) Switchman's Facility                            
        (   29) Transportation Office Building                  
        (  126) California Station                              
        (  110) Central Park                                    
        (  125) Damen Station                                   
        (   29) Douglas Substation                              
        (    0) Engineering                                     
        (    0) Code "       GL0"
        (   82) Harding Substation                              
        (   50) Hermitage Substation                            
        (  127) Kedzie Station                                  
        (   85) Kostner Station                                 
        (   24) Code "       M/S"
        (    0) Milestone                                       
        (   11) Mobilization                                    
        (    0) Code "       O&P"
        (    7) PAULINA SUBSTATION                              
        (   57) Polk Station                                    
        (  122) Pulaski Station                                 
        (    0) Relay House                                     
        ( 1197) Submittal                                       
        (   58) Transportation Office Building                  
        (    1) Utility                                         
        (  119) Western Station                                 
    LOC. - Secondary
        (    0) Fare Collect. #2                                
        (   61) Phase 1E                                        
        (   37) Phase 1W                                        
        (  461) Ground Level                                    
        (  199) Code "        LW"
        (   82) North Bound                                     
        (  136) Code "        NM"
        (   32) Phase 2                                         
        (   32) Phase 3                                         
        (  128) South Bound                                     
        (  953) Station House                                   
        (   17) Station                                         
        (  613) Track Level                                     

    NOTE: Look through the above list for under-represented codes.  This
        might indicate missing activities or a lack of proper detail.
        Nearly identical descriptions might be in error and will lead to
        confusion.  Missing codes may indicate missing work.

EXPANDED ACTIVITY CODE FIELD LAYOUT (# Activities):
    TO BENT
        (    5) Code "     54090"
        (    2) Code "     54091"
        (    2) Code "     55013"
        (    2) Code "     55023"
        (    5) Code "     55038"
        (    2) Code "     55039"
        (    2) Code "     55040"
        (    5) Code "     55041"
        (    9) Code "     55044"
        (    2) Code "     55045"
        (    2) Code "     55046"
        (    5) Code "     55047"
        (    2) Code "     55048"
        (    3) Code "     55049"
        (   14) Code "     55050"
        (    2) Code "     55051"
        (    4) Code "     55052"
        (    2) Code "     55053"
        (    5) Code "     55054"
        (    5) Code "     55055"
        (    2) Code "     55056"
        (    5) Code "     56036"
        (    2) Code "     56057"
        (    6) Code "     57010"
        (    8) Code "     57014"
    FROM BENT
        (    6) Code "     54090"
        (    4) Code "     54091"
        (    2) Code "     55013"
        (    2) Code "     55023"
        (    4) Code "     55038"
        (    2) Code "     55039"
        (    2) Code "     55040"
        (    5) Code "     55041"
        (    5) Code "     55044"
        (    2) Code "     55045"
        (    2) Code "     55046"
        (    9) Code "     55047"
        (    3) Code "     55048"
        (    2) Code "     55049"
        (    7) Code "     55050"
        (    2) Code "     55051"
        (    5) Code "     55052"
        (    2) Code "     55053"
        (    5) Code "     55054"
        (    6) Code "     55055"
        (    2) Code "     55056"
        (    6) Code "     56036"
        (    7) Code "     56057"
        (    7) Code "     57010"
        (   10) Code "     57014"
    TYPE OF WORK
        (   10) ADMINISTRATION                                  
        (    0) ALL AREAS                                       
        (    0) AMERITECH                                       
        (   97) BALLASTED TRACK WORK                            
        (    0) Code "       BLT"
        (   31) BRIDGE STEEL                                    
        (   85) COLUMN ADJUSTMENTS                              
        (  340) CAISSONS                                        
        (   17) Code "       CAN"
        (   12) CUT AND THROW                                   
        (    0) Code "       COL"
        (    0) COMM-ED                                         
        (   15) Code "       CWA"
        (   75) Code "       D/W"
        (   48) DUCTBANK                                        
        (  101) DEMOLITION                                      
        (    0) DESIGN                                          
        (   12) ELEVATOR                                        
        (   94) STATION ELECTRICAL                              
        (    0) ELEVATED TRACK WORK                             
        (    7) ESCALATOR                                       
        (   72) FOUNDATION                                      
        (   54) FIBER GLASS                                     
        (   73) Finish Work                                     
        (   17) Flatwork                                        
        (   13) FENCING                                         
        (   22) Code "       FPR"
        (   86) GRADING                                         
        (    1) Code "       GRX"
        (   39) HVAC                                            
        (    1) Code "       LDS"
        (   44) MASONRY                                         
        (    1) Code "       MIL"
        (   46) MISCELLANEOUS                                   
        (   81) Misc. Metal                                     
        (    2) MOBILIZATION                                    
        (   26) MILESTONE                                       
        (    6) OTHER UTILITY                                   
        (   30) Code "       PAI"
        (   31) Paving                                          
        (    0) PERMIT                                          
        (   26) Plumbing                                        
        (    3) TEMP PLATFORM                                   
        (    0) Code "       PLT"
        (   14) PAINTING                                        
        (    0) POLE WORK                                       
        (   28) Code "       RCA"
        (    8) REMOVALS                                        
        (    0) RETAINING WALL CONSTRUCTION                     
        (    8) Code "       RST"
        (    0) STRUCTURAL STEEL & TRACK WORK                   
        (  502) SIGNAL / COMMUNICATIONS                         
        (   13) Code "       SBA"
        (    1) STRUCTURE BACKFILL                              
        (   40) SHORING - TYPE 1                                
        (   24) SHORING - TYPE 2                                
        (   69) SHORING - TYPE 3                                
        (    0) Code "       SHO"
        (    0) Code "       SMT"
        (   28) SUPPORT OF EXCAVATION                           
        (   10) Slab on grade                                   
        (  118) Code "       SPE"
        (    0) SPREAD FOOTINGS                                 
        (   44) Code "       SSL"
        (   12) STATION STRUCTURAL STEEL                        
        (   25) SPECIAL TRACK WORK                              
        (  169) MAINLINE STRUCTURAL STEEL                       
        (    2) Code "       STR"
        (   31) Code "       STS"
        (   33) STRUCTURE EXCAVATION                            
        (  355) SUBSTRUCTURE                                    
        (  157) SUBSTATION                                      
        (    0) Code "       TIE"
        (   31) ELEVATED TRACK WORK ON EXISTING STEEL           
        (  102) Code "       TMP"
        (   22) TEMP PLATFORM                                   
        (  200) TRACTION POWER                                  
        (    1) Code "       TRA"
        (    6) Code "       TTP"
        (    7) Code "       TTS"
        (    0) Code "       TW "
        (   72) UTILITIES                                       
        (  105) WALL                                            
    COMPONENT
        (   40) Administration                                  
        (  613) Architectural                                   
        (    9) Building Type of Work                           
        (   83) Column Adjustments                              
        (  338) Caissons                                        
        (  588) Concrete Work                                   
        ( 1055) Electrical Work                                 
        (  107) Mechanical                                      
        ( 1180) Submittals                                      
        (    4) Structural Steel                                
        (  137) Station Structural Steel                        
        (  278) Structural Steel & Track Installation           
        (  383) Sitework                                        
        (  190) Track Work                                      
        (    0) Utility Work                                    
        (    2) Yard Work                                       
    WORK TYPE
        (    1) Code "       264"
        (    5) CAR WASHER BUILDING                             
        (  778) BENTS                                           
        (   78) SUBSTATION BUILDING                             
        (  792) STATION HOUSE                                   
        (   43) SIGNALMAN'S BUILDING                            
        (   44) SWITCHMAN'S BUILDING                            
        (    0) BUS TURNAROUND                                  
        (   58) TRANSPORTATION BUILDING                         
        (   22) CANOPY                                          
        (    0) COMMUNICATION WORK                              
        (    0) DEMO                                            
        (    0) ASBESTOS ABATEMENT                              
        (    0) LEAD PAINT ABATEMENT                            
        (    0) SUBSTATION EQUIPMENT                            
        (    0) UNDERGROUND STORAGE TANK WORK                   
        (   42) FOUNDATIONS                                     
        (    0) KILDARE AVE GRADE CROSSING                      
        (    0) 54TH AVE GRADE CROSSING                         
        (    0) KOSTNER AVE GRADE CROSSING                      
        (    0) KILBOURNE GRADE CROSSING                        
        (    0) 47TH AVE GRADE CROSSING                         
        (    0) 47TH COURT GRADE CROSSING                       
        (    0) CICERO AVE GRADE CROSSING                       
        (    0) 49TH AVE GRADE CROSSING                         
        (    0) 50TH AVE GRADE CROSSING                         
        (    0) LARAMIE GRADE CROSSING                          
        (  552) GENERAL WORK                                    
        (    0) PERMITS                                         
        (   14) PLATFORM                                        
        (    0) PROCUREMENT                                     
        (    0) PAULINA JUNCTION RELAY HOUSE                    
        (    0) KILBOURNE RELAY HOUSE                           
        (    0) 50TH AVE RELAY HOUSE                            
        (    0) 54TH AVE RELAY HOUSE                            
        (    0) LOOMIS STREET RELAY HOUSE                       
        (    0) HARRISON STREET RELAY HOUSE                     
        (    0) 17TH STREET RELAY HOUSE                         
        (    0) 18TH STREET RELAY HOUSE                         
        (    0) HOYNE/LEAVITT RELAY HOUSE                       
        (    0) ALBANY AVE RELAY HOUSE                          
        (    0) CENTRAL PARK RELAY HOUSE                        
        (    0) PULASKI RELAY HOUSE                             
        ( 1167) SUBMITTALS                                      
        (  222) SUPERSTRUCTURE                                  
        (    0) TESTING AND INSPECTION                          
        (    0) TRACTION POWER                                  
        (    1) TEMP PLATFORM                                   
        (    0) TEMPORARY TRAFIC CONTROL                        
        (    0) TEMPORARY PLATFORM WORK                         
        (    0) TEMPORARY SIGNAL WORK                           
        (  197) TRACKWORK                                       
        (   16) UTILITIES & SITEWORK                            
        (    0) 54TH YARD - GENERAL                             
    LOCATION-CTA
        (   44) 17TH STREET SUBSTATION                          
        (   12) 18TH STREET STATION                             
        (  134) FROM 18TH STATION TO DAMEN STATION              
        (  148) 54TH STREET STATION                             
        (    0) 54TH STREET SUBSTATION                          
        (  242) 54TH YARD                                       
        (  145) BELT BRIDGE                                     
        (   47) SIGNALMAN'S FACILITY                            
        (   59) SWITCHMAN'S FACILITY                            
        (   86) TRANSPORTATION OFFICE BUILDING                  
        (  223) CALIFORNIA STATION                              
        (  140) FROM CALIF. STATION TO KEDZIE STATION           
        (  196) CENTRAL PARK STATION                            
        (   49) CICERO STATION (BELT BRIDGE TO 54TH ST)         
        (  262) DAMEN STATION                                   
        (   75) FROM DAMEN STATION TO WESTERN STATION           
        (    7) DOUGLAS SUBSTATION                              
        (   22) DOUGLAS SUBSTATION                              
        (    6) Code "      GEN "
        (   40) HARDING SUBSTATION                              
        (   39) Code "      HER "
        (   14) Hermitage Substation                            
        (  234) KEDZIE STATION                                  
        (   72) FROM KEDZIE STATION TO CP STATION               
        (  196) KOSTNER STATION (KEELER ABUT. TO BELT BRIDGE)   
        (    9) LAKE CONNECTOR                                  
        (    2) Mobilization                                    
        (  144) ODGEN BRIDGE (FROM CP STATION TO PULASKI STATION
        (   65) INCLINE TO POLK STATION                         
        (   27) POLK STATION                                    
        (  238) FROM POLK STATION TO 18TH STATION               
        (  233) PULASKI STATION                                 
        (   59) FROM PULASKI STATION THRU KEELER BRIDGE         
        (  164) Sysem Wide                                      
        (    0) VEHICLE WASH STATION                            
        (  229) WESTERN STATION                                 
        (   52) FROM WESTERN STATION TO CALIF. STATION          
    WORK PACKAGE
        (    0) CONSTRUCTION CONTRACT ADMINISTRATION            
        (    0) CTA FORCE ACCOUNT                               
        (    0) CONSULTANTS                                     
        (    0) CONTINGENCIES                                   
        (  276) CPBL1 - SUBSTATIONS                             
        ( 2175) CPBL2 - ELEVATED STATIONS & STRUCTURE           
        ( 1126) CPBL3 - BALLAST SECTION                         
        (  376) CPBL4 - SIGNAL AND COMMUNICATIONS               
        (    0) CPBL5 - ARTWORK                                 
        (    0) CONTRACTURAL TECH. SUPPORT                      
        (    0) FINANCE COSTS                                   
        (   32) GENERAL CONDITIONS                              
        (    0) OWNER CONTROLLED INS. PROGRAM                   
        (    0) PROJECT ADMINISTRATION                          
        (    0) PA1 - COMMONWEALTH EDISON                       
        (    0) PA2 - TRAFFIC SIGNAL RELOCATION                 
        (    0) PA3 - STREET LIGHT RELOCATION                   
        (    0) PA4 - LANDSCAPING                               
        (    0) PA5 - OTHER UTILITIES                           
        (    0) PA6 - AMERITECH                                 
        (    0) PA7 - FARE CONTROL EQUIPMENT                    
        (    0) PA8 - SIGNAL TECH SUPPORT                       
        (    0) PA9 - OTHER RAILROAD FLAGGING                   
        (    0) PROPERTY COSTS                                  
        (    0) PROGRAM MANAGER                                 
        (    0) RELOCATION                                      
        (    0) SAFETY                                          
    PROJECT IDENT
        (    0) ART WORK                                        
        (    0) BID AND AWARD                                   
        ( 4997) CONSTRUCTION                                    
        (    0) FINAL ENGINEERING                               
        (    0) OTHER, FINANCING AND CONTIGENCY                 
        (    0) PROJECT ADMINISTRATION                          
        (    0) PRELIMINARY ENGINEERING                         
        (    0) REAL ESTATE                                     
    INTERIM M. S.
        (    0) 17TH SUBSTATION COMPLETE                        
        (    0) HERMITAGE SUBSTATION COMPLETE                   
        (    0) COMPL DAMEN STATION FROM 54025-54049 NTP+810    
        (    0) COMPL WESTERN STATION FROM 54064-54091 NTP+810  
        (    0) COMPL CALIF STATION FROM 54122-55008 NTP+810    
        (    0) COMPL KEDZIE STATION FROM 55049-56021 NTP+810   
        (    0) COMPL CP STATION FROM 56039-56057 NTP+810       
        (    0) COMPL PULASKI STATION FROM 56101-57014 NTP+810  
        (    0) COMPL BARRIER FENCE @ 54TH ST. NTP+200          
        (    0) TEMPORARY INTERLOCKING @ 53RD ST. - 21 DAYS     
        (    0) COMPL 54TH ST. STATION & BUSWAY NTP+610         
        (    0) COMPL 54TH ST. YARD FOR 80 CAR STORAGE NTP+910  
        (    0) SHUT DOWN 54TH ST. YARD - 56 DAYS               
        (    0) SUBMIT SIGNAL BLOCK DIAGRAM FOR CPBL-4 NTP+105  
    CHANGE ORDER
        (    0) ORIGINAL CONTRACT WORK                          
        (    0) CHANGE ORDER #1                                 
        (    0) CHANGE ORDER #2                                 
        (    0) CHANGE ORDER #3                                 
        (    1) CHANGE ORDER #4                                 
    D/W/M - BE
        (    0) MINORITY BUSINESS ENTERPRISE                    
        (    0) MINORITY BUSINESS ENTERPRISE                    
    SLOW ZONE TYPE
        (   90) Code "       1  "
        (   98) Code "       2  "
        (   86) Code "       3  "
        (   77) Code "       4  "
        (    0) CONSTRUCTION SLOW ZONE                          
        (    0) INFRASTRUCTURE SLOW ZONE                        
        (    8) Code "       K/D"
        (    0) TEMPORARY FLAGGING ZONE                         
    Responsibility
        (  498) ALDERIDGE ELECTRIC                              
        (    0) AMERITECH                                       
        (    0) CITY BUILDING DEPT.                             
        (    0) CITY SEWER DEPT                                 
        (    0) CITY WATER DEPT                                 
        (    0) COMMONWEALTH EDISON                             
        (    1) CHICAGO TRANSIT AUTHORITY                       
        (  327) DIVANE BROTHERS ELECTRICAL                      
        ( 3365) Code "     K/D  "
        (    5) KIEWIT/DELGATO AJV                              
        (  796) SUBCONTRACTOR - NOT ASSIGNED                    
    Spec. Division
        (    0) Code "     03300"
         [list trimed for demonstration]
        (    3) Code "  9901    "
        (   14) Code "  9901.10 "
        (    2) MISC                                            
    Units
        (   13) Code "        BF"
        (  561) Code "        CY"
        ( 1003) Code "        EA"
        (   26) Code "        LB"
        (   59) Code "        LF"
        ( 2466) Code "        LS"
        (  362) Code "        SF"
        (   17) Code "        SY"
        (   34) Code "        TF"
        (   53) Code "        TN"

    NOTE: Look through the above list for under-represented codes.  This
        might indicate missing activities or a lack of proper detail.
        Nearly identical descriptions might be in error and will lead to
        confusion.  Missing codes may indicate missing work.

WBS Code Check:

No Work Breakdown (WBS) Assignments exist.
    NOTE: Use of WBS assignments is becoming increasingly more prevalent,
        especially in large, enterprise scheduling situations.  It has the
        built-in ability to summarize groups of activities without adding
        additional logical relationships, such as required by hammocks.

============================== RELATIONSHIPS ===============================

----------------------- RELATIONSHIP STANDARDS CHECK -----------------------
Lags used on this project are larger than the maximum used in the standard.
Odd relationship pairs (not SS/FF pairs) are used in violation of standards.
Activity pairs have up to 2  relationships in violation of standards.
----------------------------------------------------------------------------

 This project has a total of 7899 relationships.

 0 relationships are bogus.
 0 Hammock Activities are missing required relationships.
 0 Hammock Activities have ignored relationships.
    There are no logical predecessors to NOTICE TO PROCEED.
    No early activities were found not related to NOTICE TO PROCEED.
----------------------------------------------------------------------------
| ACTIVITIES WITHOUT PREDECESSORS                                          |
|   ACT       START  FLOAT TITLE                                           |
+---------- -------- ----- ------------------------------------------------+
|EC000090    16JUL01  1081 Substn.-Elect.-Des Mtg.                         |
|EC0010      16JUL01  1082 Milestone 4-1: Signal Block Diagram             |
|EC17TGL003  16JUL01   879 Preparation work @ Jobsite                      |
|EC17TGL005  16JUL01   879 Substation Design Meeting                       |
|EC18TGL498  16JUL01  1023 Equipment Racks                                 |
|EC372XX176  16JUL01  1007 BELT BRIDGE AREA - traction power               |
|EC54CGL268  16JUL01  1072 Preparation work @ Jobsite                      |
|EC54CGL269  16JUL01  1067 Temporary Power & Lighting                      |
|EC54CGL271  16JUL01  1067 ComEd Service Changes & Coordination            |
|EC54CGL281  16JUL01  1077 Relocate Ameritech Phone Service                |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 44 activities were found without logical predecessors.
    CAUTION: A perfect schedule will only have one activity without a
        logical predecessor and that activity should be Notice To Proceed.
        Schedules created this way are easier to manage and use for delay
        analysis.  This also prevents activities that start too early.

----------------------------------------------------------------------------
| ACTIVITIES WITHOUT SUCCESSORS                                            |
|   ACT      FINISH  FLOAT TITLE                                           |
+---------- -------- ----- ------------------------------------------------+
|EC000090    16JUL01  1081 Substn.-Elect.-Des Mtg.                         |
|EC0010      13JUL01  1082 Milestone 4-1: Signal Block Diagram             |
|EC17TGL007  17OCT01  1015 ComEd Service Changes & Coordination            |
|EC17TGL008  28AUG01  1050 Miscellaneous Power Devices                     |
|EC17TGL009  16AUG01  1058 ITC/Local Control Panels                        |
|EC17TGL011  21SEP01  1033 Getaway Ductbanks                               |
|EC17TGL012  29NOV01   986 Install ductbank with conduit                   |
|EC17TGL013  22AUG01  1054 Install Lighting Fixtures                       |
|EC17TGL014  16OCT01  1016  AC Metering Equipment/Panels/ATS               |
|EC17TGL015  13JUN02   850 Install Substation Battery System               |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 248 activities were found without logical successors.
    CAUTION: A perfect schedule will only have one activity without a
        logical successor and that activity should be Project Complete.
        Schedules created this way are easier to manage and use for delay
        analysis. This also prevents activities with incorrect float values.

----------------------------------------------------------------------------
| SUBMITTAL ACTIVITIES WITHOUT SUCCESSOR REVIEW ACTIVITIES                 |
|   ACT     DURATION FLOAT TITLE                                           |
+---------- -------- ----- ------------------------------------------------+
|EMSMTKE005        1  1531 Prepare/Submit Keeler Bridge Dwg                |
|PAMOB00020      100  1450 Submittals                                      |
|SBSMT00490       29   159 Column Adj. - Work Plan/Submittals - Prepare    |
|SBSMT00530       29   159 Column Adj. - Work Plan/Submittals- Approve     |
|SBSMT00540       20    24 Caissons - Work Plan/Submittals - Prepare       |
|SBSMT00550       15    24 Caissons - Work Plan/Submittals - Approve       |
|SPSMT00100       20   735 Track Work - Work Plan/Submittals- Prepare      |
|SPSMT00110       15   735 Track Work - Work Plan/Submittals- Approve      |
|SPSMT01000       90   210 Prepare/Submit Shop Dwg-PUL2                    |
|SPSMT01030       90   195 Prepare/Submit Shop Dwg-PUL1                    |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 11 SUBMITTAL activities have no REVIEW activity successors.
    CAUTION: Every submittal activity should normally be immediately follow-
        ed by a review activity.  This ensures that sufficient time is al-
        lotted between the submittal and the need for the submitted items.
        The review activity should have a delivery or actual use successor.

----------------------------------------------------------------------------
| REVIEW ACTIVITIES WITH MISSING SUCCESSORS                                |
|   ACT      FINISH  FLOAT TITLE                                           |
+---------- -------- ----- ------------------------------------------------+
|ECHERGL104  22OCT01  1038 Review/Connect to Existing Transformers         |
|STSMTRE425  27AUG01  1051 REVIEW MECHANICAL INSULATION                    |
----------------------------------------------------------------------------
 2 REVIEW activities were found without logical successors.
    CAUTION: Every review activity should logically lead to a portion of
        the schedule where the submittal is required in order to continue.
        This will allow you to determine the float time available for that
        review.  Critical reviews can often be expedited with advance
        notice to the reviewer as long as criticality is known beforehand.

    CAUTION: Don't forget to include fabrication and delivery time as a
        successor to REVIEW if the material is not available off-the-shelf
        from a local source.

----------------------------------------------------------------------------
| MULTIPLE NEAR-CRITICAL PATH ACTIVITIES                                   |
|   ACT     # PATHS  FLOAT TITLE                                           |
+---------- -------- ----- ------------------------------------------------+
|ECPOLTL107        2     0 SIGNAL/COM REMOVALS                             |
|ECSWTL127         2     0 SCADA/CONTROL CENTER                            |
|PAMOB00011        2     0 Mobilization 5%                                 |
|PAMOB00021        2     0 Mobilization 20%                                |
|PAMOB00031        3     0 Mobilization 45%                                |
|PAMOB00041        2     0 Mobilization 50%                                |
|PAMOB00051        3     0 Mobilization 60%                                |
|PAMOB00061        4     0 Mobilization 70%                                |
|PAMOB00081        2     0 Mobilization 90%                                |
|PAMOB00091        2     0 Mobilization 100%                               |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 More than 11 multiple, independent near-critical activities found.
    NOTE: Project Critical Float is  0 and any activity with a float
        value within 10 of this was considered as near-critical.
        As this is a Baseline Schedule, A Project Critical Float of 0 was used.
    CAUTION: CPM networks should not have multiple critical paths without
        through justification.  Some Contractors adjust durations, logic, 
        and lead times so as to artificially create multiple paths.  This
        increases the number of critical activities which increases the 
        potential that any Owner-caused delay will look like a delay to the
        project.  Detail analysis of the above activities is recommended.

 0  out of a possible of 0 relationship chains are interruptible.
----------------------------------------------------------------------------
| ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS (NOT SS & FF PAIRS)         |
| PRED ACT  SUCC ACT   RELS.    TITLE                                      |
+---------- ---------- -------- -------------------------------------------+
|SB342T3118 -------       FS SS SPREAD FTGS-57020 TP 3                     |
|           SB32910100 2 Rels.  COL/CAP - PIER-56120 TP 10                 |
|                                                                          |
----------------------------------------------------------------------------
 1 multiple relationship is found.
    ERROR: Two activities that share more than one relationship is highly
        unusual. The only exception to this rule is if a Start-To-Start (SS)
        relationship is used with a Finish-To-Finish (FF) relationship. Any
        othe combination, or when more than two relationships are used is 
        likely to be an error.

 0 apparent odd relationships found.
----------------------------------------------------------------------------
| ODD LAGS OR LEADS USED                                                   |
| PRED ACT  SUCC ACT    LAG REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|EC17TGL003 ---------- ---- --- Preparation work @ Jobsite                 |
|           EC17TGL004    2  FS Temporary Power & Lighting                 |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL008    3  FS Miscellaneous Power Devices                |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL009    3  FS ITC/Local Control Panels                   |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL010    2  FS Rough In Work @ Substation                 |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL011    5  FS Getaway Ductbanks                          |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL012    5  FS Install ductbank with conduit              |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL013    3  FS Install Lighting Fixtures                  |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL014    3  FS  AC Metering Equipment/Panels/ATS          |
|                                                                          |
|EC17TGL004 ---------- ---- --- Temporary Power & Lighting                 |
|           EC17TGL016    3  FS Substation Telephone System                |
|                                                                          |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 85 odd lags are listed above.
    NOTE: Lags and Leads are time intervals imposed between two activities.
        They are legitimately used to describe linked activities which are
        staggered or to represent a time interval, say for curing concrete.

        They can be also used to 'hide' float or otherwise artificially
        expand a project schedule without being visible on plots or in most
        reports. Negative lags can hide an unworkable project schedule by
        shortening it without changing activity durations.

    CAUTION: It is highly unusual for Start-to-Start (SS) or Finish-to-
        Finish (FF) relationships to have negative lags.  Recommend further
        investigation into the reasoning behind such timing.

    CAUTION: It is highly unusual for Finish-to-Start (FS) relationships to
        have positive lags.  Recommend that you have the creator of the
        schedule document what that lead represents.

        You must consider the calendar when using lags.  Lags use the
        calendar of the proceeding act.  In the case of concrete curing (a
        7-day/week event,) the lag would use the calendar of the concrete
        pour, which is probably a 5-day/week event.  Just expanding the
        length by 7/5 does not fully consider where in the week it falls.

        Lags make for poor long-lead times.  You cannot status a lag or
        periodically review its progress.  For lags of long duration (such
        as the delivery of a major piece of equipment,) it would be better
        to create an activity that would show-up on reports and would need
        to be statused every update.

    CAUTION: While lags and leads have legitimate uses, any such time inter-
        val over 5 should be individually investigated.

----------------------------------------------------------------------------
| ALL OTHER LAGS OR LEADS (OTHER THAN ODD) USED                            |
| PRED ACT  SUCC ACT    LAG REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing|
|           EC17TGL007    1  SS ComEd Service Changes & Coordination       |
|                                                                          |
|EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing|
|           EC17TGL020    1  SS Transformer Shop Dwgs                      |
|                                                                          |
|EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing|
|           EC17TGL026    1  SS DC Switchgear Shop Dwgs                    |
|                                                                          |
|EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing|
|           EC17TGL032    1  SS Rectifier Shop Dwgs                        |
|                                                                          |
|EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing|
|           EC17TGL038    1  SS Medium Voltage Switchgear Shop Dwgs        |
|                                                                          |
|EM17TXX110 ---------- ---- --- 17th - SUBSTN - LAG PILE                   |
|           EM17TXX120    5  SS 17th - SUBSTN - STRUCTURE EXC              |
|                                                                          |
|EM343SB206 ---------- ---- --- KEEL WALL N. - 342+50 - ANCHOR PILE        |
|           EM343SB210   -5  FS KEEL WALL N. - 342+50 - DEMO EXIST WALL    |
|                                                                          |
|EM343SB208 ---------- ---- --- KEEL WALL N. - 342+50 - STR. EXC.          |
|           EM343SB210   -5  FS KEEL WALL N. - 342+50 - DEMO EXIST WALL    |
|                                                                          |
|EM412ST106 ---------- ---- --- 54TH STR. STA - 412 to 424 - F&P  WALLS    |
|           EM412ST128   -5  FS 54TH STR. STA - 412 to 424 - F&P PLATFORMS |
|                                                                          |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 533  'standard' lags were found.
    NOTE: While usually considered acceptable for use in schedules, lags and
        leads should always be reviewed for reasonableness.  In other words,
        there should be a reason for having each lag.  If that reason is not
        apparent to you, then you should ask for it.

----------------------------------------------------------------------------
| NON-OVERLAPPING LAGS USED                                                |
| PRED ACT  SUCC ACT    LAG REL TITLE                                      |
+---------- ---------- ---- --- -------------------------------------------+
|EM17TXX110 ---- DUR =    3 --- 17th - SUBSTN - LAG PILE                   |
|           EM17TXX120    5  SS 17th - SUBSTN - STRUCTURE EXC              |
|                                                                          |
|STCALSH025 ---- DUR =    1 --- BLDG INSUL-VAPOR BAR                       |
|           STCALSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
|STCENSH025 ---- DUR =    2 --- BLDG INSUL-VAPOR BAR                       |
|           STCENSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
|STDAMSH025 ---- DUR =    1 --- BLDG INSUL-VAPOR BAR                       |
|           STDAMSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
|STKEDSH025 ---- DUR =    1 --- BLDG INSUL-VAPOR BAR                       |
|           STKEDSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
|STPULSH025 ---- DUR =    1 --- BLDG INSUL-VAPOR BAR                       |
|           STPULSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
|STWESSH025 ---- DUR =    1 --- BLDG INSUL-VAPOR BAR                       |
|           STWESSH101   -3  FS CIP CONC-STATION  -SLABS                   |
|                                                                          |
----------------------------------------------------------------------------
 7 non-overlapping lags are listed above.
    NOTE: Lags are typically used to show the overlapping nature of two
        activities.  If the lag used is too great, the activities will no
        longer overlap in time.  This may be an entry error.  Otherwise,
        suggest that you convert to a different relationship that better
        describes the intended relationship.

----------------------------------------------------------------------------
| ACTIVITIES WITHOUT A FINISH RELATIONSHIP                                 |
| ACT                FLOAT  TITLE                                          |
+---------- -------- ----- ------------------------------------------------+
|EC17TGL006            841 17th Street Substation Installation Drawings    |
|EC203TL415            231 ELEV ST-DAM-STATION  (TR2) TRACTION POWER       |
|EC203TL417            231 ELEV ST-DAM-STATION  (TR2) SIGNAL               |
|EC203TL420            217 ELEV ST-DAM-STATION  (TR1) TRACTION POWER       |
|EC203TL422            217 ELEV ST-DAM-STATION  (TR1) SIGNAL               |
|EC305TL140            273 ELEV ST-CP STATION (TR2) TRACTION POWER         |
|EC305TL141            273 ELEV ST-CP STATION (TR2) SIGNAL                 |
|EC54TGL127            921 54th Street Substation Installation Drawings    |
|EC54YGL394            907 ComEd Ductbanks                                 |
|EC54YGL422            674 Prep work @ Site                                |
| *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH ***            |
----------------------------------------------------------------------------
 257 Activities are missing Finish Relationships.
    NOTE: The above activities do not have any constraint on completion,
        other than perhaps their start day.  With the existing configuration
        a shortening or lengthing of the activity's duration will have no
        effect on project completion.  Confirm that no succeeding activity
        is limited by this completion of this activity or add a FS or FF 
        relationship to the appropriate activity.
================================ CONSTRAINTS ===============================

------------------------ CONSTRAINT STANDARDS CHECK ------------------------
Hammocks are used in violation of standards.
----------------------------------------------------------------------------

 0 constraints are bogus.

----------------------------------------------------------------------------
| BASELINE SCHEDULE CONSTRAINTS                                            |
| ACT       C-TYPE  DATE    TITLE                                          |
+---------- ------ ------- ------------------------------------------------+
|EC343XX100  SNET   1OCT01 TEMP ELEC KEELER TO BELT BRIDGE                 |
|EC3721W384  SNET   1OCT01 MJ BRD PH 1W TRACTION POWER                     |
|EC412SB250  SNET  17SEP01 LAR-54TH - 411 to 425 traction power            |
|EM343XX102  SNET  29APR02 TEMP R.ROUND - 343 - FOOTINGS                   |
|EM349NB100  SNET  27APR02 KILDARE XING NB - 349 - W/END REPL              |
|EM398SB100  SNET  17SEP01 LAR-50TH - 411 to 398 - Exc. Track              |
|EM412SB200  SNET  10SEP01 N. FENCE WALL - Rem Exist Fence - 424 to 410    |
|EM54Y3B344  SNET  11JUL02 STAGE 3B - 54TH YARD - EXCAVATION               |
|EMBSWXX100  SNET  15OCT01 SWITCHMAN'S FAC. -  DEMO SWITCH FAC.            |
|EMSMTXX010  SNET   1AUG01 MJ BRD - STR. STL. - SHOP DWGS - PREPARE        |
|EMSMTXX200  SNET   6AUG01 N. FENCE WALL - WORK PLAN/SUB - PREPARE         |
|PAADM00020  SNET  16JUL01 Notice To Proceed                               |
|SB342T3104  SNET   5NOV01 SPREAD FTGS-57027 TP 3                          |
|SBSMTXX100  SNET  13AUG01 COL/CAP - SHOP DWG/WORK PLAN - PREPARE          |
|SBSMTXX130  SNET  20AUG01 SPREAD FTGS - SHORING PLAN - PREPARE            |
|SP212TP090  SNET  24SEP01 TEMP PLTFM WEST/DAM-Inst Below                  |
|SP256TP070  SNET  24SEP01 TEMP PLTFM CAL-Inst Below                       |
|SP295TP030  SNET  24SEP01 TEMP PLTFM CP-Inst Below                        |
|SP337TP010  SNET  24SEP01 TEMP PLTFM PUL-Inst Below                       |
----------------------------------------------------------------------------
 19 constraints were found in the project.
    CAUTION: Baseline Schedules should only contain constraints that are
        specifically called out in the plans and specifications.  Otherwise,
        this can be thought of as the Contractor is "reserving float" (which
        is typically not allowed.)
    NOTE: If the Contractor resists removing non-contractual constraints,
        from the Baseline Schedule, the prudent Scheduler will note each 
        such constraint in the review of the baseline and state that the
        Owner reserves the right to temporarily delete any such constraint
        when evaluating the effects of delays.

 0 activities were coded for Zero Free Float.
 0 Zero Total Float constraints were found in the project.
 0 active Expected Finish constraints were found in the project.
 0 improper Expected Finish constraints were found in the project.
 0 Mandatory Start/Finish constraints were found in the project.
 0 active START ON constraints were found in the project.
================================ COST CHECKS ===============================

--------------------------- COST STANDARDS CHECK ---------------------------
Cost Records are used in violation of standards.
Cost Records for Task-type activities are used in violation of standards.
----------------------------------------------------------------------------

There are no cost accounts in this project to check.
There appears to be cost information under Resources.
================================ LOG CHECKS ================================

------------------------- LOG FILE STANDARDS CHECK -------------------------
Standard Log Records are not used on this project.
----------------------------------------------------------------------------

No Logs were found in the schedule.
============================== END OF REPORT ===============================
 Analysis complete at 16:56:24.

Return to SA Pro Overview.