Schedule
Analyzer Professional
Copyright Ron
Winter 2003
Sample Baseline
Checker Report - Lists Limited to First 10 Entries
SA PRO BASELINE CHECKER ============================ | Version 2.78 | ============================ Copyright by Ron Winter 1998/2003 This report was prepared by Ron Winter Consulting LLC. BASELINE: BL00 Analysis Date: 07-01-2003 at 16:15:28 Schedule used for Coding Standards = C:\P3WIN\PROJECTS\242Med\514A Company Name = Unnamed Joint Venture Project Title = Unnamed Project Report Title = (nothing on record.) CAUTION: You should enter a Report Title under Tools, Tabular, Reports, Options: Center Heading. It will be printed in the middle center of the header in tabular reports. Project Version = Baseline Project Start = 16JUL01 Project Early Finish = 13OCT05 =========================== SCHEDULE STATISTICS ============================ ----------------------- STATISTICAL STANDARDS CHECK ------------------------ This project does not use Imposed Finish Dates in violation of standards. Calendar Start Date does not match Standard. Calendar 2 Description has been changed. Calendar 3 has been added. Calendar 4 has been added. Calendar 5 has been added. Calendar 6 has been added. Calendar 7 has been added. Calendar 8 has been added. Calendar 9 has been added. Calendar A has been added. Calendar B has been added. Calendar C has been added. Some Calendar Holidays have been deleted. The total number of calendar holidays changed form 28 to 432 . Rule 4a: When Quantities change, recompute Budget Costs has been changed. The Total Float Calculation rule has been changed. ---------------------------------------------------------------------------- CALENDAR CHECK CAUTION: This project uses an Imposed Finish Date of 10/13/2005 . This setting will not allow for the addition of activities after Substantial Completion (such as Punchlist) without messing-up float calculations for the whole project. Recommend that you constrain the Late Finish of the activity that describes Substantial Completion instead of using this feature. You can remove this Imposed Finished Date under Project Overview under the heading of 'Project must finish by'. Project computes durations in Days. NOTE: This project calculates durations in Days. This is the standard setting, offering a balance between accuracy and maintainability. The only way to change this unit of measurement is to copy the schedule and define the new unit during the process. NOTE: The start day for the week (Monday) is used for reporting on a weekly timescale and to determine when weekends occur for Calendar 1. This setting can be changed once defined by selection Data, Calendars, Global Calendar, Standard. The following calendars are defined: ---------------------------------------- Global Calendar, Calendar 1 CAUTION: Calendar Title is missing. Calendar 2 7-Days/Week Calendar 3 5-Days/Wk, H Calendar 4 5D/Wk H/W Calendar 5 5 Days -H/Winter Calendar 6 PAINT 5D/CTA/W Calendar 7 WEnd - H/CTA/WIN Calendar 8 WEnd/H Calendar 9 6 DAYS Calendar A Wend - Day Shift Calendar B 5DAY/W-4DAY (H) Calendar C 5DAY/W-4DAY (SB) ---------------------------------------- A total of 12 calendars are defined. CAUTION: You are missing some calendar titles. The use of descripive titles helps you to identify the correct one when assigning activity calendars, preventing mistakes. ---------------------------------------------------------------------------- | PROJECT WEEKEND LISTING | | DAY CALENDAR WHICH HAS THAT WEEKEND NOTES | !--------- -------------------------------- -------------------------------+ | 123456789ABC List of all active calendars. | | MONDAY 78 A Note: Unusual day for weekend. | | TUESDAY 78 A Note: Unusual day for weekend. | | WEDNESDAY 78 A Note: Unusual day for weekend. | | THURSDAY 78 A Note: Unusual day for weekend. | | FRIDAY 78 A Note: Unusual day for weekend. | | SATURDAY 1 3456 BC | | SUNDAY 1 3456 9 BC | ---------- -------------------------------- -------------------------------- HOLIDAY CHECK: CAUTION: According to settings, holidays will automatically be moved to the nearest workday if they fall on non-workdays (weekends.) ---------------------------------------------------------------------------- | PROJECT HOLIDAY LISTING | | DATE CALENDAR WHICH HAS THAT HOLIDAY NOTES | !--------- -------------------------------- -------------------------------+ | *123456789ABC List of all active calendars. | | 30AUG01 56 | | 31AUG01 56 | | 01SEP01 78 | | 02SEP01 78 | | 03SEP01 3456 BC | | 15NOV01 6 | | 16NOV01 6 | | 19NOV01 6 | | 20NOV01 6 | | 21NOV01 6 | | 22NOV01 3456 BC | | 23NOV01 3456 BC | | 24NOV01 8 | | 25NOV01 8 | | 26NOV01 6 | | 27NOV01 6 | | 28NOV01 6 | | 29NOV01 6 | | 30NOV01 6 | | 03DEC01 6 | | 04DEC01 6 | | 05DEC01 6 | | 06DEC01 6 | | 07DEC01 6 | | 10DEC01 6 | | 11DEC01 6 | | 12DEC01 6 | | 13DEC01 6 | | 14DEC01 6 | | 17DEC01 456 | | 18DEC01 456 | | 19DEC01 456 | | 20DEC01 456 | | 21DEC01 456 | | 22DEC01 78 | | 23DEC01 78 | | 24DEC01 3456 BC | | 25DEC01 3456 BC | | 26DEC01 456 BC | | 27DEC01 456 BC | | 28DEC01 456 BC | | 29DEC01 7 | | 30DEC01 7 | | 31DEC01 456 BC | | 01JAN02 3456 BC | | 02JAN02 456 BC | | 03JAN02 456 BC | | 04JAN02 456 BC | | 05JAN02 7 | | 06JAN02 7 Date delayed due to weekend. | | 07JAN02 456 | | 08JAN02 456 | | 09JAN02 456 | | 10JAN02 456 | | 11JAN02 456 BC | | 13JAN02 7 Date delayed due to weekend. | | 14JAN02 456 | | 15JAN02 456 | | 16JAN02 456 | | 17JAN02 456 | | 18JAN02 456 BC | | 20JAN02 7 Date delayed due to weekend. | | 21JAN02 456 | | 22JAN02 456 | | 23JAN02 456 | | 24JAN02 456 | | 25JAN02 456 BC | | 27JAN02 7 Date delayed due to weekend. | | 28JAN02 456 | | 29JAN02 456 | | 30JAN02 456 | | 31JAN02 456 | | 01FEB02 456 BC | | 04FEB02 456 | | 05FEB02 456 | | 06FEB02 456 | | 07FEB02 456 | | 08FEB02 456 BC | | 09FEB02 7 | | 10FEB02 7 | | 11FEB02 456 | | 12FEB02 456 | | 13FEB02 456 | | 14FEB02 456 | | 15FEB02 4 6 BC | | 18FEB02 6 | | 19FEB02 6 | | 20FEB02 6 | | 21FEB02 6 | | 22FEB02 6 BC | | 25FEB02 6 | | 26FEB02 6 | | 27FEB02 6 | | 28FEB02 6 | | 01MAR02 6 BC | | 04MAR02 6 | | 05MAR02 6 | | 06MAR02 6 | | 07MAR02 6 | | 08MAR02 6 BC | | 11MAR02 6 | | 12MAR02 6 | | 13MAR02 6 | | 14MAR02 6 | | 15MAR02 6 BC | | 22MAR02 BC | | 29MAR02 BC | | 13APR02 78 | | 14APR02 78 | | 25MAY02 78 | | 26MAY02 78 | | 27MAY02 3456 BC | | 31MAY02 6 | | 28JUN02 6 | | 01JUL02 6 | | 02JUL02 6 | | 03JUL02 6 | | 04JUL02 3 56 BC | | 05JUL02 6 B | | 29AUG02 6 | | 30AUG02 6 | | 31AUG02 78 | | 01SEP02 78 | | 02SEP02 3456 BC | | 15NOV02 6 | | 18NOV02 6 | | 19NOV02 6 | | 20NOV02 6 | | 21NOV02 6 | | 22NOV02 6 | | 25NOV02 6 | | 26NOV02 6 | | 27NOV02 6 | | 28NOV02 3456 BC | | 29NOV02 3456 BC | | 30NOV02 8 | | 01DEC02 8 | | 02DEC02 6 | | 03DEC02 6 | | 04DEC02 6 | | 05DEC02 6 | | 06DEC02 6 | | 09DEC02 6 | | 10DEC02 6 | | 11DEC02 6 | | 12DEC02 6 | | 13DEC02 6 | | 16DEC02 456 | | 17DEC02 456 | | 18DEC02 456 | | 19DEC02 456 | | 20DEC02 456 | | 21DEC02 7 | | 22DEC02 7 | | 23DEC02 456 BC | | 24DEC02 3456 BC | | 25DEC02 3456 BC | | 26DEC02 456 BC | | 27DEC02 456 BC | | 28DEC02 7 | | 29DEC02 7 | | 30DEC02 456 BC | | 31DEC02 456 BC | | 01JAN03 3456 BC | | 02JAN03 456 BC | | 03JAN03 456 BC | | 04JAN03 7 Date advanced due to weekend. | | 05JAN03 7 Date delayed due to weekend. | | 06JAN03 456 | | 07JAN03 456 | | 08JAN03 456 | | 09JAN03 456 | | 10JAN03 456 BC | | 12JAN03 7 Date delayed due to weekend. | | 13JAN03 456 | | 14JAN03 456 | | 15JAN03 456 | | 16JAN03 456 | | 17JAN03 456 BC | | 19JAN03 7 Date delayed due to weekend. | | 20JAN03 456 | | 21JAN03 456 | | 22JAN03 456 | | 23JAN03 456 | | 24JAN03 456 BC | | 26JAN03 7 Date delayed due to weekend. | | 27JAN03 456 | | 28JAN03 456 | | 29JAN03 456 | | 30JAN03 456 | | 31JAN03 456 BC Date delayed due to weekend. | | 02FEB03 7 | | 03FEB03 456 | | 04FEB03 456 | | 05FEB03 456 | | 06FEB03 456 | | 07FEB03 456 C | | 08FEB03 7 | | 09FEB03 7 | | 10FEB03 456 | | 11FEB03 456 | | 12FEB03 456 | | 13FEB03 456 | | 14FEB03 456 C | | 17FEB03 6 | | 18FEB03 6 | | 19FEB03 6 | | 20FEB03 6 | | 21FEB03 6 C | | 24FEB03 6 | | 25FEB03 6 | | 26FEB03 6 | | 27FEB03 6 | | 28FEB03 6 C | | 03MAR03 6 | | 04MAR03 6 | | 05MAR03 6 | | 06MAR03 6 | | 07MAR03 6 C | | 10MAR03 6 | | 11MAR03 6 | | 12MAR03 6 | | 13MAR03 6 | | 14MAR03 6 C | | 17MAR03 6 | | 21MAR03 C | | 28MAR03 C | | 12APR03 78 | | 13APR03 78 | | 24MAY03 78 | | 25MAY03 78 | | 26MAY03 3456 BC | | 30MAY03 6 | | 27JUN03 6 | | 30JUN03 6 | | 01JUL03 6 | | 02JUL03 6 | | 03JUL03 6 | | 04JUL03 3 56 BC | | 28AUG03 6 | | 29AUG03 6 | | 30AUG03 78 | | 31AUG03 78 | | 01SEP03 3456 BC | | 17NOV03 6 | | 18NOV03 6 | | 19NOV03 6 | | 20NOV03 6 | | 21NOV03 6 | | 24NOV03 6 | | 25NOV03 6 | | 26NOV03 6 | | 27NOV03 3456 BC | | 28NOV03 3456 BC | | 29NOV03 8 | | 30NOV03 8 | | 01DEC03 6 | | 02DEC03 6 | | 03DEC03 6 | | 04DEC03 6 | | 05DEC03 6 | | 08DEC03 6 | | 09DEC03 6 | | 10DEC03 6 | | 11DEC03 6 | | 12DEC03 6 | | 15DEC03 456 | | 16DEC03 456 | | 17DEC03 456 | | 18DEC03 456 | | 19DEC03 456 | | 20DEC03 7 | | 21DEC03 7 | | 22DEC03 456 BC | | 23DEC03 456 BC | | 24DEC03 3456 BC | | 25DEC03 3456 BC | | 26DEC03 456 BC | | 27DEC03 7 | | 28DEC03 7 | | 29DEC03 456 BC | | 30DEC03 456 BC | | 31DEC03 456 BC | | 01JAN04 3456 BC | | 02JAN04 456 BC | | 03JAN04 7 Date advanced due to weekend. | | 04JAN04 7 | | 05JAN04 456 | | 06JAN04 456 | | 07JAN04 456 | | 08JAN04 456 | | 09JAN04 456 BC | | 10JAN04 7 | | 11JAN04 7 | | 12JAN04 456 | | 13JAN04 456 | | 14JAN04 456 | | 15JAN04 456 | | 16JAN04 456 BC | | 17JAN04 7 | | 18JAN04 7 | | 19JAN04 456 | | 20JAN04 456 | | 21JAN04 456 | | 22JAN04 456 | | 23JAN04 456 BC | | 24JAN04 7 | | 25JAN04 7 | | 26JAN04 456 | | 27JAN04 456 | | 28JAN04 456 | | 29JAN04 456 | | 30JAN04 456 BC | | 31JAN04 7 | | 01FEB04 7 | | 02FEB04 456 | | 03FEB04 456 | | 04FEB04 456 | | 05FEB04 456 | | 06FEB04 456 BC | | 07FEB04 7 | | 08FEB04 7 | | 09FEB04 456 | | 10FEB04 456 | | 11FEB04 456 | | 12FEB04 456 | | 13FEB04 456 BC | | 16FEB04 6 | | 17FEB04 6 | | 18FEB04 6 | | 19FEB04 6 | | 20FEB04 6 BC | | 23FEB04 6 | | 24FEB04 6 | | 25FEB04 6 | | 26FEB04 6 | | 27FEB04 6 BC | | 01MAR04 6 | | 02MAR04 6 | | 03MAR04 6 | | 04MAR04 6 | | 05MAR04 6 BC | | 08MAR04 6 | | 09MAR04 6 | | 10MAR04 6 | | 11MAR04 6 | | 12MAR04 6 BC | | 15MAR04 6 | | 17MAR04 6 | | 19MAR04 BC | | 26MAR04 BC | | 10APR04 78 | | 11APR04 78 | | 29MAY04 78 | | 30MAY04 78 | | 31MAY04 3456 BC | | 04JUN04 6 | | 02JUL04 6 | | 05JUL04 56 B | | 06JUL04 6 | | 07JUL04 6 | | 08JUL04 6 | | 09JUL04 6 | | 26AUG04 6 | | 27AUG04 6 | | 04SEP04 78 | | 05SEP04 78 | | 06SEP04 3456 BC | | 15NOV04 6 | | 16NOV04 6 | | 17NOV04 6 | | 18NOV04 6 | | 19NOV04 6 | | 22NOV04 6 | | 23NOV04 6 | | 24NOV04 6 | | 25NOV04 3456 BC | | 26NOV04 3456 BC | | 27NOV04 8 | | 28NOV04 8 | | 29NOV04 6 | | 30NOV04 6 | | 01DEC04 6 | | 02DEC04 6 | | 03DEC04 6 | | 06DEC04 6 | | 07DEC04 6 | | 08DEC04 6 | | 09DEC04 6 | | 10DEC04 6 | | 13DEC04 6 | | 14DEC04 6 | | 15DEC04 56 | | 16DEC04 56 | | 17DEC04 56 | | 18DEC04 7 | | 19DEC04 7 | | 20DEC04 456 B | | 21DEC04 456 B | | 22DEC04 456 B | | 23DEC04 456 BC | | 24DEC04 3456 BC | | 25DEC04 78 | | 26DEC04 78 | | 27DEC04 456 BC | | 28DEC04 456 BC | | 29DEC04 456 BC | | 30DEC04 456 BC | | 31DEC04 456 BC | | 01JAN05 7 | | 02JAN05 7 | | 03JAN05 456 | | 04JAN05 456 | | 05JAN05 456 | | 06JAN05 456 | | 07JAN05 456 | | 08JAN05 7 | | 09JAN05 7 | | 10JAN05 456 | | 11JAN05 456 | | 12JAN05 456 | | 13JAN05 456 | | 14JAN05 456 | | 15JAN05 7 | | 16JAN05 7 | | 17JAN05 456 | | 18JAN05 456 | | 19JAN05 456 | | 20JAN05 456 | | 21JAN05 456 | | 22JAN05 7 | | 23JAN05 7 | | 24JAN05 456 | | 25JAN05 456 | | 26JAN05 456 | | 27JAN05 456 | | 28JAN05 456 | | 29JAN05 7 | | 30JAN05 7 | | 31JAN05 456 | | 01FEB05 456 | | 02FEB05 456 | | 03FEB05 456 | | 04FEB05 456 | | 05FEB05 7 | | 06FEB05 7 | | 07FEB05 456 | | 08FEB05 456 | | 09FEB05 456 | | 10FEB05 456 | | 11FEB05 456 | | 12FEB05 7 | | 13FEB05 7 | | 14FEB05 56 | | 15FEB05 6 | | 16FEB05 6 | | 17FEB05 6 | | 18FEB05 6 | | 21FEB05 6 | | 22FEB05 6 | | 23FEB05 6 | | 24FEB05 6 | | 25FEB05 6 | | 28FEB05 6 | | 01MAR05 6 | | 02MAR05 6 | | 03MAR05 6 | | 04MAR05 6 | | 07MAR05 6 | | 08MAR05 6 | | 09MAR05 6 | | 10MAR05 6 | | 11MAR05 6 | | 14MAR05 6 | | 15MAR05 6 | | 17MAR05 6 | | 09APR05 7 | | 10APR05 7 | | 28MAY05 7 | | 29MAY05 7 | | 30MAY05 4 6 | | 03JUN05 6 | | 01JUL05 6 | | 04JUL05 56 | | 05JUL05 6 | | 06JUL05 6 | | 07JUL05 6 | | 08JUL05 6 | | 25AUG05 6 | | 26AUG05 6 | | 05SEP05 456 | ---------- -------------------------------- -------------------------------- A total of 491 Holidays are defined. ----------------------------------------------- | BAD HOLIDAYS AND EXCEPTIONS IN CALENDARS | | CAL DATE NOTE | !---- ------- -------------------------------+ | 3 04JUL01 Holiday before Project Start | | 4 24NOV05 Holiday after Project Finish | | 4 19DEC05 Holiday after Project Finish | | 4 26DEC05 Holiday after Project Finish | | 4 02JAN06 Holiday after Project Finish | | 5 01JAN01 Holiday before Project Start | | 5 28MAY01 Holiday before Project Start | | 5 04JUL01 Holiday before Project Start | | 5 24NOV05 Holiday after Project Finish | | 5 15DEC05 Holiday after Project Finish | | 5 19DEC05 Holiday after Project Finish | | 5 26DEC05 Holiday after Project Finish | | 5 02JAN06 Holiday after Project Finish | | 5 09JAN06 Holiday after Project Finish | | 5 16JAN06 Holiday after Project Finish | | 5 23JAN06 Holiday after Project Finish | | 5 30JAN06 Holiday after Project Finish | | 5 01FEB06 Holiday after Project Finish | | 5 06FEB06 Holiday after Project Finish | | 5 13FEB06 Holiday after Project Finish | | 6 02JUL01 Holiday before Project Start | | 6 15NOV05 Holiday after Project Finish | | 6 21NOV05 Holiday after Project Finish | | 6 28NOV05 Holiday after Project Finish | | 6 01DEC05 Holiday after Project Finish | | 6 05DEC05 Holiday after Project Finish | | 6 12DEC05 Holiday after Project Finish | | 6 19DEC05 Holiday after Project Finish | | 6 26DEC05 Holiday after Project Finish | | 7 14APR01 Holiday before Project Start | | 7 26MAY01 Holiday before Project Start | | 7 17DEC05 Holiday after Project Finish | | 7 24DEC05 Holiday after Project Finish | | 7 31DEC05 Holiday after Project Finish | | 7 01JAN06 Holiday after Project Finish | | B 05JAN01 Holiday before Project Start | | B 12JAN01 Holiday before Project Start | | B 19JAN01 Holiday before Project Start | | B 26JAN01 Holiday before Project Start | | B 02FEB01 Holiday before Project Start | | B 09FEB01 Holiday before Project Start | | B 16FEB01 Holiday before Project Start | | B 23FEB01 Holiday before Project Start | | B 02MAR01 Holiday before Project Start | | B 09MAR01 Holiday before Project Start | | B 16MAR01 Holiday before Project Start | | B 23MAR01 Holiday before Project Start | | B 30MAR01 Holiday before Project Start | | B 04JUL01 Holiday before Project Start | | C 04JUL01 Holiday before Project Start | ----- ------- -------------------------------- 50 bad Holidays and Exceptions to calendars exist. NOTE: Holidays after Project Finish may be useful if the project is extended. It is not incorrect to include them in any case. NOTE: Dates were advanced or delayed to the nearest workday due to the current setting in Global Calendars. To stop P3 from moving the holiday, deselect the option box under Tools, Calendars, Global Calendar, Standard. AUTOCOST RULES CHECK NOTE: You have not entered an Identifier to verify review of Autocost Rules. This is not required, but is a good practice. Suggest that you enter your initials or any 4 character name to indicate who is responsible for the current settings. You can do this by selecting Tools, Options, Autocost Rules, Identifier. NOTE: You have not entered a date to verify your last review of Autocost Rules. This is not required but is good practice. Suggest that you enter the date of last review or update of the Autocost Rules. You can do this by selecting Tools, Options, Autocaost Rules, Date. Rule 1: Link remaining duration and schedule percent complete? Yes NOTE: This is the standard setting and should be used unless using nonlinear resource distributions. Rule #2: Freeze resource units per time period? No NOTE: This is a non-standard setting that adjusts workcrew size in response to earned progress so as to meet planned finish. In either case, this setting has no effect on your schedule unless you are using resources. Rule #3a: Calculation for estimate to complete? Subtract actual from EAC NOTE: Use this method on fixed-price contracts, as it doesn't allow you to exceed your budget. Rule #3b: Allow 'negative estimate to complete'? No CAUTION: With this setting, P3 will not allow a negative calculation Instead, it will automatically set 'Estimate to Complete' = 0 and change your 'Estimate at Completion' = 'Actual to Date.' Rule #4a: When Quantities change, recompute Budget Costs? No NOTE: This is the standard setting. Use this when you do not track costs or when the budget is known. Rule #4b: When Quantities change, recompute Actual Costs? Yes CAUTION: Only use this setting when tracking costs but Actual Costs are not tabulated. It is dangerous to estimate actuals. Rule #4c: When Quantities change, recompute Est. to Complete Costs? Yes NOTE: This is the standard setting. Estimates to complete should be related to quantities remaining. Rule #5a: Update % complete against budget to recompute Budget? Yes CAUTION: Only use this setting when tracking costs but the budget isn't fixed. Rule #5b: Update % complete against budget to recompute Cost? Yes CAUTION: Only use this setting when tracking costs but Actual Costs are not tabulated. It is dangerous to estimate actuals. Rule #6: Actual linked to date and actual this period? Yes NOTE: Use this setting if you are tracking costs per update period. Rule #7: Budget linked to EAC for non-progressed acts? Yes CAUTION: This setting should only be used during the planning stages of a project. Until set to off, P3 will not calculate variance. Rule #8: Variance is calculated as: Budget minus Estimate At Completion. NOTE: This is the default setting that displays variances as negative values. Recalculate and Store Cost during each schedule computation? No NOTE: This is the correct setting if your project does not calculate costs or if it does not use non-linear resource distributions or costs associated with Hammocks or Expected Finish Constraints. Apply the above rules by Cell or Resource? Cell NOTE: This is the default setting. It will register your entries as you move your cursor from field to field. CPM RULES CHECK Scheduling Method is set to Retained Logic. NOTE: This is the normal method for predicting status with out-of sequence progress. Schedule Method is also set to Contiguous Activities. CAUTION: This is the standard setting but will produce different results for activity chains identified in later Interruptible Activities Report. Use this setting for projects that wait until all resources may be employed without a break. Total Float Calculation uses Start Dates to calculate Total Float. NOTE: This will result in the same answer except for interruptible activities and Hammock activities. Interruptible activities work better using Finish Dates and Hammock activities work better using the Start Dates setting. ================================ ACTIVITIES ================================ ------------------------- ACTIVITY STANDARDS CHECK ------------------------- There are a greater number of activities than allowed by the standard. The maximum duration of some activities is greater than allowed by standards Tasks (not milestones) with zero duration are used in violation of standards Start Milestone Activities are used in violation of standards. Standard Start Flag Activities are not used on this project. Standard Finish Flag Activities are not used on this project. Hammock Activities are used in violation of standards. Activity Descriptions are not left-justified, in violation of standards. ---------------------------------------------------------------------------- There are a total of 5023 activities in this schedule. Listed by category type, the totals are; Fixed Duration CPM Activity: Tasks = 4981 Resource-driven Duration CPM Activities: Independent = 0 Meeting = 0 Zero Duration Mileposts: Start Milestones = 25 Finish Milestones = 10 Start Flags = 0 Finish Flags = 0 Summary (Non-CPM) Duration Activities: Hammocks = 7 WBS = 0 CAUTION: Many contracts specify the maximum or minimum number of activities allowed in the schedule. For this purpose, the first two categories above are usually totaled = 4981 activities. Many specifications limit the percentage of activities that can be critical or near-critical in the Baseline Schedule. A typical upper limit is a maximum of 30% critical and 50% critical or near-critical. Critical Activities = 3.98% Critical and Near- Critical Activities = 4.76% (based upon Total Float less than 11 .) Of the 4981 CPM-type activities in the schedule, Average duration of these activities was 11.31 Days. Mean of the durations was 449.00 Days. Standard Deviation of the difference was 22.31 Days. ---------------------------------------------------------------------------- | ACTIVITY DURATION HISTOGRAM (excluding Milestones) | | DURATION COUNT GRAPH | !---------- ------ -------------------------------------------------------+ | 0 31 # | | 1-5 2604 #######################################################| | 6-10 454 ########## | | 11-15 1139 ######################### | | 16-20 131 ### | | 21-25 87 ## | | 26-30 368 ######## | | 31-35 5 # | | 36-40 11 # | | 41-45 1 # | | 46-50 17 # | | 51-55 11 # | | 56-60 43 # | | 61-65 2 # | | 66-70 2 # | | 71-75 3 # | | 76-80 6 # | | 81-85 1 # | | 86-90 23 # | | 91-95 1 # | | 96-100 5 # | | 101-105 0 | | 106-110 2 # | | 111-115 0 | | 116-120 3 # | | 121-125 0 | | 126-130 0 | | 131-135 0 | | 136-140 6 # | | 141-145 0 | | 146-150 1 # | | 151-155 1 # | | 156-160 13 # | | 161-165 0 | | 166-170 1 # | | 171-175 0 | | 176-180 1 # | | 181-185 0 | | 186-190 0 | | 191-195 0 | | 196-200 2 # | | 201-205 0 | | 206-210 1 # | | 211-215 0 | | 216-220 0 | | 221-225 0 | | 226-230 0 | | 231-235 1 # | | 236-240 0 | | 241-245 0 | | 246-250 0 | | 251-255 0 | | 256-260 0 | | 261-265 0 | | 266-270 1 # | | 271-275 0 | | 276-280 2 # | | 281-285 0 | | 286-290 0 | | 291-295 0 | | 296-300 0 | | 301-305 0 | | 306-310 0 | | 311-315 0 | | 316-320 0 | | 321-325 0 | | 326-330 0 | | 331-335 0 | | 336-340 0 | | 341-345 0 | | 346-350 0 | | 351-355 0 | | 356-360 0 | | 361-365 0 | | 366-370 0 | | 371-375 0 | | 376-380 0 | | 381-385 0 | | 386-390 0 | | 391-395 0 | | 396-400 0 | | 401-405 0 | | 406-410 0 | | 411-415 0 | | 416-420 0 | | 421-425 0 | | 426-430 0 | | 431-435 0 | | 436-440 0 | | 441-445 0 | | 446-450 0 | | 451-455 0 | | 456-460 0 | | 461-465 0 | | 466-470 0 | | 471-475 0 | | 476-480 0 | | 481-485 0 | | 486-490 0 | | 491-495 0 | | 496-500 0 | | 501-505 0 | | 506-510 0 | | 511-515 0 | | 516-520 0 | | 521-525 0 | | 526-530 0 | | 531-535 0 | | 536-540 0 | | 541-545 0 | | 546-550 0 | | 551-555 0 | | 556-560 0 | | 561-565 0 | | 566-570 0 | | 571-575 0 | | 576-580 0 | | 581-585 0 | | 586-590 0 | | 591-595 0 | | 596-600 0 | | 601-605 0 | | 606-610 0 | | 611-615 0 | | 616-620 0 | | 621-625 0 | | 626-630 0 | | 631-635 0 | | 636-640 0 | | 641-645 0 | | 646-650 0 | | 651-655 0 | | 656-660 0 | | 661-665 0 | | 666-670 0 | | 671-675 0 | | 676-680 0 | | 681-685 0 | | 686-690 0 | | 691-695 0 | | 696-700 0 | | 701-705 0 | | 706-710 0 | | 711-715 0 | | 716-720 0 | | 721-725 0 | | 726-730 0 | | 731-735 0 | | 736-740 0 | | 741-745 0 | | 746-750 0 | | 751-755 0 | | 756-760 0 | | 761-765 0 | | 766-770 0 | | 771-775 0 | | 776-780 0 | | 781-785 0 | | 786-790 0 | | 791-795 0 | | 796-800 0 | | 801-805 0 | | 806-810 0 | | 811-815 0 | | 816-820 0 | | 821-825 0 | | 826-830 0 | | 831-835 0 | | 836-840 0 | | 841-845 0 | | 846-850 0 | | 851-855 0 | | 856-860 0 | | 861-865 0 | | 866-870 0 | | 871-875 0 | | 876-880 0 | | 881-885 0 | | 886-890 0 | | 891-895 0 | | 896-900 1 # | ---------------------------------------------------------------------------- 4981 of Tasks and Resource Activities (Non-Milestone) are represented above. 2322 activities are 1 to 1 Days long. The shortest duration is 0 Days. The longest duration is 898 Days. NOTE: Many contracts specify the minimum or maximum allowable durations of activities included in the schedule. It is best to not consider milestones or summary activities when qualifying durations. The analysis above only considers Task, Independent, and Meeting type activities and excludes all others. ---------------------------------------------------------------------------- | ACTIVITY DURATIONS GREATER THAN 10 | | ACT DURATION FLOAT ACT TYPE TITLE | +---------- ======== ----- ---------- -------------------------------------+ |EC17TGL008 12 1050 Task Miscellaneous Power Devices | |EC17TGL011 27 1033 Task Getaway Ductbanks | |EC17TGL012 74 986 Task Install ductbank with conduit | |EC17TGL014 46 1016 Task AC Metering Equipment/Panels/ATS | |EC17TGL015 17 850 Task Install Substation Battery System | |EC17TGL022 90 841 Task Factory Fabrication for Transformers | |EC17TGL025 46 841 Task Receive & Install Transformers | |EC17TGL028 60 850 Task Factory Fabrication for DC Switchgea | |EC17TGL031 50 850 Task Receive & Install DC Switchgear | |EC17TGL034 80 865 Task Factory Fabrication for Rectifier | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 1899 activities had long durations. CAUTION: Many specifications require activities to be defined with dur- ations less than a set number. The intent of this requirement is to allow for better monitoring and control of the work described by the activity. Typically, the reviewer is allowed to wave this require- ment in the case of Hammocks or deliveries, etc. ---------------------------------------------------------------------------- | SUSPICIOUS ACTIVITY DURATIONS | | ACT DURATION FLOAT TITLE | +---------- ======== ----- ------------------------------------------------+ |EC17TGL008 12 1050 Miscellaneous Power Devices | |EC17TGL011 27 1033 Getaway Ductbanks | |EC17TGL012 74 986 Install ductbank with conduit | |EC17TGL013 8 1054 Install Lighting Fixtures | |EC17TGL014 46 1016 AC Metering Equipment/Panels/ATS | |EC17TGL015 17 850 Install Substation Battery System | |EC17TGL018 8 1042 RTU/SCADA System | |EC17TGL025 46 841 Receive & Install Transformers | |EC17TGL043 52 865 Receive & Install Medium Voltage Switchgear | |EC17TGL044 8 865 Install Copper Bus & Complete Innerconnects | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 529 activities had suspicious activity durations. CAUTION: Some schedulers arbitrarily modify activity durations to make various near-critical logic chains match total durations exactly, thus artificially producing multiple critical paths. The above listed activities have 'odd' durations, which should be investigated further, especially if they are critical. ---------------------------------------------------------------------------- | SUSPICIOUS REMAINING DURATIONS | | ACT ORIG. REMAIN % TITLE | +---------- ----- ===== ---- ----------------------------------------------+ |EMSMT02320 15 30 0 SMT-2050 Temp Earth Ret Strc -54th St Sta. - F| ---------------------------------------------------------------------------- 1 activities had suspicious remaining durations. CAUTION: Remaining Duration for unstarted activities should equal the Original Duration. In no case should it be greater than Original Duration without an explanation. ---------------------------------------------------------------------------- | ACTIVITIES MISSING DESCRIPTIONS | | ACT TYPE START FINISH % CMP FLOAT DURATION | +---------- ---------- ------- ------- ----- ----- ------------------------+ |SPSMT01090 Task 16JUL01 16JUL01 0 1 | ---------------------------------------------------------------------------- 1 activities were missing descriptions. CAUTION: All activities should have descriptive titles. This title serves as a form of Scope Of Work definition and thus further defines the contract. Notice To Proceed is on 16JUL01. ---------------------------------------------------------------------------- | UNUSUAL NUMBER OF 'MOBILIZATION' ACTIVITIES | | ACT START FINISH TITLE | +---------- ------- ------- ===============================================+ |PAMOB00010 17JUL01-16JUL01 Mobilization Initial | |PAMOB00011 16OCT01-16OCT01 Mobilization 5% | |PAMOB00021 16JAN02-16JAN02 Mobilization 20% | |PAMOB00031 19SEP02-19SEP02 Mobilization 45% | |PAMOB00041 19NOV02-19NOV02 Mobilization 50% | |PAMOB00051 19JAN03-19JAN03 Mobilization 60% | |PAMOB00061 21MAR03-21MAR03 Mobilization 70% | |PAMOB00071 21MAY03-21MAY03 Mobilization 80% | |PAMOB00081 21JUL03-21JUL03 Mobilization 90% | |PAMOB00091 13OCT05-13OCT05 Mobilization 100% | ---------------------------------------------------------------------------- 10 activities had 'MOBILIZE' in their descriptions. 0 activities had 'SUBSTANTIAL COMPLETION' in their descriptions. CAUTION: There does not appear to be a Substantial Completion in this schedule. Regardless of whether it is called out by specification, it is widely recognized legally as the termination point for the assessment of Liquidated Damages and thus should be included. ---------------------------------------------------------------------------- | ACTIVITIES WITH WORK PERCENTAGES IN THEIR TITLE | | ACT STR DATE FLOAT TITLE | +---------- -------- ----- ================================================+ |PAMOB00011 16OCT01 0 Mobilization 5% | |PAMOB00021 16JAN02 0 Mobilization 20% | |PAMOB00031 19SEP02 0 Mobilization 45% | |PAMOB00041 19NOV02 0 Mobilization 50% | |PAMOB00051 19JAN03 0 Mobilization 60% | |PAMOB00061 21MAR03 0 Mobilization 70% | |PAMOB00071 21MAY03 0 Mobilization 80% | |PAMOB00081 21JUL03 0 Mobilization 90% | |PAMOB00091 13OCT05 0 Mobilization 100% | ---------------------------------------------------------------------------- 9 activities use work percentages in their titles. CAUTION: The above activities are described in terms of a percentage of a task. This is poor scheduling practice as it cannot be accurately statused. Suggest that you use physical lengths of progress such as "INSTALL CULVERT, 0 - 100 METERS" or "POUR FOUNDATION, 1-3 GRIDLINE". ---------------------------------------------------------------------------- | POSSIBLE REVIEW OR APPROVAL ACTIVITIES | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ================================================+ |EC17TGL021 10 841 Approval Time for Transformers | |EC17TGL027 10 850 Approval Time for DC Switchgear | |EC17TGL033 10 865 Approval Time for Recitifer | |EC17TGL039 10 865 Approval Time for Medium Voltage Switchgear | |EC54TGL140 10 921 Approval Time for Transformers | |EC54TGL145 6 921 Review & Connect to Existing DC Switchgear | |EC54TGL146 6 921 Review & Connect to Existing Rectifiers | |EC54TGL147 4 921 Review & Connect to Existing Medium Voltage Swgr| |ECHARGL063 10 936 Approval Time for Transformers | |ECHARGL069 10 954 Approval Time for DC Switchgear | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 429 review or approval activities exist. CAUTION: You should check the above activities to ensure that the time allotted is within the specified minimums. You should also scrutinize any activity which lists work responsibilities for the Owner or A/E as this might compromise you legally later. ---------------------------------------------------------------------------- | ACTIVITIES POSSIBLY DEALING WITH UTILITIES | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ================================================+ |EC54CGL281 5 1077 Relocate Ameritech Phone Service | |EC54YGL328 5 934 Pole Bases | |EC54YGL331 6 934 Erect light poles and install fixtures | |EC54YGL333 7 749 Pole Bases | |EC54YGL336 8 749 Erect light poles and install fixtures | |EC54YGL402 22 841 Light Pole Bases | |EC54YGL403 36 841 Site Lighting Poles & Fixtures | |ECKOSGL312 5 750 Relocate Ameritech Phone Service | |ECPOLTL256 5 842 Relocate Ameritech Phone Service | |EM343XX104 5 344 TEMP R.ROUND - 343 - SHORE TOWERS | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 40 utility activities exist. CAUTION: Typically, utility companies are considered 'third-parties.' They are not under the control of either the Owner or Contractor. Delays caused by the utility company are typically considered as excusable and sometimes compensible by the Owner, even if the owner had no direct hand in the cause. Check to see that the time allowed is per specification. Ideally, it would be nice to not have these activities not on the critical path, but often they are. ---------------------------------------------------------------------------- | MAJOR MATERIALS DELIVERY ACTIVITIES | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ================================================+ |EC17TGL024 2 841 Deliver Transformers to Jobsite | |EC17TGL030 2 850 Deliver DC Switchgear to Jobsite | |EC17TGL036 2 865 Deliver Rectifier to Jobsite | |EC17TGL042 2 865 Deliver Medium Voltage Switchgear to Jobsite | |EC54TGL143 2 921 Deliver Transformers to Jobsite | |ECHARGL066 2 936 Deliver Transformers to Jobsite | |ECHARGL072 2 954 Deliver DC Switchgear to Jobsite | |ECHARGL078 2 944 Deliver Rectifier to Jobsite | |ECHARGL084 2 944 Deliver Medium Voltage Switchgear to Jobsite | |ECHERGL109 2 911 Deliver DC Switchgear to Jobsite | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 27 major material delivery activities exist. CAUTION: You should check the above activities to ensure all important pieces of long-lead items are accounted for. You should also check that such activities are scheduled based on 7-days per week (not workday) schedules. ---------------------------------------------------------------------------- | ACTIVITIES DEALING WITH TEMPORARY ISSUES | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ================================================+ |EC17TGL004 5 893 Temporary Power & Lighting | |EC343XX100 30 399 TEMP ELEC KEELER TO BELT BRIDGE | |EC343XX110 2 120 TEMP R.ROUND 343 TEMP ELEC TRACK POWER | |EC398SB100 2 333 LAR-50TH -411 TO 398 TEMP ELEC | |EC54CGL269 15 1067 Temporary Power & Lighting | |EC54TGL125 5 1067 Temporary Power & Lighting | |EC54YGL385 30 584 Temporary Power & Lighting | |EC54YGL423 30 999 Temporary Power & Lighting | |ECBSMGL370 2 1064 Temporary Power & Lighting | |ECBSWGL339 2 1019 Temporary Power & Lighting | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 85 activities dealing with temporary issues exist. CAUTION: You should check the above activities to ensure all proposed actions are acceptable. Sometimes, Contractors plan to create temporary barriers, access points, or structures which would conflict with Owner Operations or safety rules in effect. Approval of this in a schedule may constitute an approval of the plan. ---------------------------------------------------------------------------- | DUPLICATE ACTIVITY DESCRIPTIONS | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ================================================+ |EC000090 1 1081 Substn.-Elect.-Des Mtg. | |ECALL010 1 1081 Substn.-Elect.-Des Mtg. | | | |EC0010 0 1082 Milestone 4-1: Signal Block Diagram | |PAM/S00010 0 1444 Milestone 4-1: Signal Block Diagram | | | |EC107TW265 2 52 SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | |EC108TW270 2 52 SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | | | |EC107TW266 2 52 SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | |EC108TW271 2 52 SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | | | |EC108TW255 2 52 SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER | |EC109TW260 2 52 SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER | | | |EC108TW256 2 52 SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM | |EC109TW261 2 52 SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM | | | ---------------------------------------------------------------------------- 12 duplicate activity descriptions exist. CAUTION: Activities with duplicate descriptions are confusing to track. Even though they may be coded for different areas, this is not always clear on print-outs. Suggest that you start each description with 'AREA A - (description)' instead. ---------------------------------------------------------------------------- | MILESTONES CODED AS ACTIVITIES | | ACT ID TYPE DUR TITLE | +---------- ---------- ----- ----------------------------------------------+ |EC0010 Task 0 Milestone 4-1: Signal Block Diagram | |EM343NB170 Task 0 KEEL. S. RET.WL - 343 - FENCE | |EM343SB258 Task 0 KEEL WALL N. - 342+50 - FENCE | |EM357XX110 Task 0 KOSTNER XING - 356+50 - ASPHALT | |EM357XX112 Task 0 KOSTNER XING - 356+50 - CURB & GUTTER | |EM357XX114 Task 0 KOSTNER XING - 356+50 - SIDEWALK | |EM357XX116 Task 0 KOSTNER XING - 356+50 - WATERLINE | |EM414XX118 Task 0 BUSWAY - 414 - CURB AND GUTTER | |EM414XX120 Task 0 BUSWAY - 414 - SIDEWALK | |EM414XX136 Task 0 BUSWAY - 414 - GUARD RAIL | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 31 such activities were found. NOTE: The above activities should have durations or be coded as milestones. Otherwise you have to deal with an early finish that is earlier than the early start and that can give you headaches. ---------------------------------------------------------------------------- | BASELINE MILESTONES | | ACT ID TYPE DATE TITLE | +---------- --------- ------- ---------------------------------------------+ |PAM/S00010 Milestone 30OCT01 Milestone 4-1: Signal Block Diagram | |PAM/S00090 Milestone 13JUN03 Milestone 2-1: TW, Struct., & Station | |PAM/S00100 Milestone 04FEB03 Milestone 3-5: Substantial Compl. | |PAM/S00110 Milestone 13OCT05 Milestone 5-0: Project Completion | |PAM/S00240 Milestone 04JAN02 Milestone 1-1: 17th Str. Substn. finish | |PAM/S00250 Milestone 16JUL01 Milestone 1-1:17th Str. Substn. start | |PAM/S00260 Milestone 13MAY02 Milestone 1-2: Hermitage Substn. finish | |PAM/S00270 Milestone 05JAN02 Milestone 1-2: Hermitage Substn. start | |PAM/S00280 Milestone 28OCT02 Milestone 1-3: Substantil Compl. | |PAM/S00290 Milestone 12SEP03 Milestone 2-1: TW, Struct., & Station | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 35 milestones found. NOTE: The only milestones that should be in a Baseline Schedule are contractually required ones. Verify that the above list is reasonable and inclusive. ---------------------------------------------------------------------------- | ACTIVITY DISTRIBUTION HISTOGRAM (using 1/2 Float) | | MONTH ACTIVE GRAPH | !---------- ------ -------------------------------------------------------+ | Jul 2001 3 # | | Aug 2001 4 # | | Sep 2001 13 ## | | Oct 2001 28 ### | | Nov 2001 39 #### | | Dec 2001 92 ########## | | Jan 2002 297 ############################## | | Feb 2002 308 ############################### | | Mar 2002 241 ######################## | | Apr 2002 176 ################## | | May 2002 180 ################## | | Jun 2002 176 ################## | | Jul 2002 236 ######################## | | Aug 2002 299 ############################## | | Sep 2002 279 ############################ | | Oct 2002 318 ################################ | | Nov 2002 396 ####################################### | | Dec 2002 460 ############################################## | | Jan 2003 560 #######################################################| | Feb 2003 370 ##################################### | | Mar 2003 301 ############################## | | Apr 2003 195 #################### | | May 2003 209 ##################### | | Jun 2003 273 ########################### | | Jul 2003 270 ########################### | | Aug 2003 266 ########################### | | Sep 2003 278 ############################ | | Oct 2003 246 ######################### | | Nov 2003 149 ############### | | Dec 2003 138 ############## | | Jan 2004 153 ################ | | Feb 2004 88 ######### | | Mar 2004 119 ############ | | Apr 2004 64 ####### | | May 2004 12 ## | | Jun 2004 6 # | | Jul 2004 6 # | | Aug 2004 6 # | | Sep 2004 7 # | | Oct 2004 3 # | | Nov 2004 2 # | | Dec 2004 2 # | | Jan 2005 2 # | | Feb 2005 2 # | | Mar 2005 2 # | | Apr 2005 2 # | | May 2005 1 # | | Jun 2005 1 # | | Jul 2005 2 # | | Aug 2005 2 # | | Sep 2005 1 # | | Oct 2005 2 # | ---------------------------------------------------------------------------- 7285 activities are planned to be active during the above months. NOTE: You should confirm that the schedule is roughly equally detailed from the start to the finish of the project. The above curve should be somewhat flat and balanced on both ends. A lower second half might indicate an under-developed finish plan. A schedule with an underdeveloped ending indicates that the Contractor has not fully taken into account all issues and is thus less accurate. It won't do you any good to be on schedule just to find out that the finish did not provide enought time to complete. ========================== ACTIVITY CODE ANALYSIS ========================== -------------------------- CODING STANDARDS CHECK -------------------------- Activity ID Codes are used in violation of standards. Activity Code Field Definitions are changed in violation of standards. Activity Code Field Definitions are changed in violation of standards. WBS Codes are changed in violation of standards. ---------------------------------------------------------------------------- Activity Code Check: The following code definitions are blank: Activity Code "TO BENT", Title for code "54090" is missing. Title for code "54091" is missing. Title for code "55013" is missing. Title for code "55023" is missing. Title for code "55038" is missing. Title for code "55039" is missing. Title for code "55040" is missing. Title for code "55041" is missing. Title for code "55044" is missing. Title for code "55045" is missing. Title for code "55046" is missing. Title for code "55047" is missing. Title for code "55048" is missing. Title for code "55049" is missing. Title for code "55050" is missing. Title for code "55051" is missing. Title for code "55052" is missing. Title for code "55053" is missing. Title for code "55054" is missing. Title for code "55055" is missing. Title for code "55056" is missing. Title for code "56036" is missing. Title for code "56057" is missing. Title for code "57010" is missing. Title for code "57014" is missing. Activity Code "FROM BENT", Title for code "54090" is missing. Title for code "54091" is missing. Title for code "55013" is missing. Title for code "55023" is missing. Title for code "55038" is missing. Title for code "55039" is missing. Title for code "55040" is missing. Title for code "55041" is missing. Title for code "55044" is missing. Title for code "55045" is missing. Title for code "55046" is missing. Title for code "55047" is missing. Title for code "55048" is missing. Title for code "55049" is missing. Title for code "55050" is missing. Title for code "55051" is missing. Title for code "55052" is missing. Title for code "55053" is missing. Title for code "55054" is missing. Title for code "55055" is missing. Title for code "55056" is missing. Title for code "56036" is missing. Title for code "56057" is missing. Title for code "57010" is missing. Title for code "57014" is missing. Activity Code "TYPE OF WORK", Title for code "BLT" is missing. Title for code "CAN" is missing. Title for code "COL" is missing. Title for code "CWA" is missing. Title for code "D/W" is missing. Title for code "FPR" is missing. Title for code "GRX" is missing. Title for code "LDS" is missing. Title for code "MIL" is missing. Title for code "PAI" is missing. Title for code "PLT" is missing. Title for code "RCA" is missing. Title for code "RST" is missing. Title for code "SBA" is missing. Title for code "SHO" is missing. Title for code "SMT" is missing. Title for code "SPE" is missing. Title for code "SSL" is missing. Title for code "STR" is missing. Title for code "STS" is missing. Title for code "TIE" is missing. Title for code "TMP" is missing. Title for code "TRA" is missing. Title for code "TTP" is missing. Title for code "TTS" is missing. Title for code "TW " is missing. Activity Code "WORK TYPE", Title for code "264" is missing. Activity Code "LOCATION-CTA", Title for code "GEN " is missing. Title for code "HER " is missing. Activity Code "SLOW ZONE TYPE", Title for code "1 " is missing. Title for code "2 " is missing. Title for code "3 " is missing. Title for code "4 " is missing. Title for code "K/D" is missing. Activity Code "Responsibility", Title for code "K/D " is missing. Activity Code "Spec. Division", Title for code "03300" is missing. Title for code "05101" is missing. [List trimed for demostration] Title for code "9901 " is missing. Title for code "9901.10 " is missing. Activity Code "Units", Title for code "BF" is missing. Title for code "CY" is missing. Title for code "EA" is missing. Title for code "LB" is missing. Title for code "LF" is missing. Title for code "LS" is missing. Title for code "SF" is missing. Title for code "SY" is missing. Title for code "TF" is missing. Title for code "TN" is missing. Field ID Code "LOC. - Primary", Title for code "ALL" is missing. Title for code "GL0" is missing. Title for code "M/S" is missing. Title for code "O&P" is missing. Field ID Code "LOC. - Secondary", Title for code "LW" is missing. Title for code "NM" is missing. ------------------------------ 656 code titles are missing. ERROR: Code Titles are automatically used in reports and plots whenever you group or page break based upon this field. As a default, if the Field Title is blank P3 will only print the actual code value. Suggest you delete unused ID Field "NUMBER". Suggest you delete unused Code Field "SECOND TIER SUB". Suggest you delete unused Code Field "Phase". Duplicate Code Titles for Code PLF and Code TPL. Duplicate Code Titles for Code DOU and Code DOUG. Duplicate Code Titles for Code MBE and Code WBE. Duplicate Code Titles for Code EA and Code EC. Duplicate Code Titles for Code EA and Code ED. Duplicate Code Titles for Code EC and Code ED. Duplicate Code Titles for Code BTB and Code TOB. ------------------------------------- 7 duplicate code titles exist. ERROR: The same code field description has been used for two different codes in the same category. One of these should be deleted to prevent mistakes and confusion. ---------------------------------------------------------------------------- | MISSING ACTIVITY ID FIELD DEFINITIONS | | ACT ID FIELD NAME ACTIVITY TITLE | +---------- ============== ------------------------------------------------+ |EC000090 Project ID Substn.-Elect.-Des Mtg. | |EC0010 Project ID Milestone 4-1: Signal Block Diagram | |EC105TW275 Project ID SP TRK-#9 TO - Lake Conn TR1 TRACTION POWER | |EC105TW276 Project ID SP TRK-#9 TO - Lake Conn TR1 SIGNAL/COM | |EC107TW265 Project ID SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | |EC107TW266 Project ID SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | |EC108TW255 Project ID SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER | |EC108TW256 Project ID SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM | |EC108TW270 Project ID SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | |EC108TW271 Project ID SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 12327 Activity ID Fields have missing code definitions. ERROR: The above activities have entries in the listed field that do not match any of the legal values listed in the Activity ID Field Dictionary. Enter and define the above codes or correct. ---------------------------------------------------------------------------- | BLANK ACTIVITY CODES | | ACT CODE FIELD ACTIVITY TITLE | +---------- ============== ------------------------------------------------+ |EC000090 TO BENT Substn.-Elect.-Des Mtg. | |EC0010 TO BENT Milestone 4-1: Signal Block Diagram | |EC105TW275 TO BENT SP TRK-#9 TO - Lake Conn TR1 TRACTION POWER | |EC105TW276 TO BENT SP TRK-#9 TO - Lake Conn TR1 SIGNAL/COM | |EC107TW265 TO BENT SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | |EC107TW266 TO BENT SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | |EC108TW255 TO BENT SP TRK-#7 LH XO-Harrison TR1-2 TRACTION POWER | |EC108TW256 TO BENT SP TRK-#7 LH XO-Harrison TR1-2 SIGNAL/COM | |EC108TW270 TO BENT SP TRK-#7 RH XO-Harrison TR1-2 TRACTION POWER | |EC108TW271 TO BENT SP TRK-#7 RH XO-Harrison TR1-2 SIGNAL/COM | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 34260 blank codes exist in this project. ERROR: It is easy to miss entering a code field when building a schedule. It is important that all activities have a code so that they won't be overlooked in reports, filters, and views. Suggest that you look for a similar activity and use the code found there. If no code applies, consider 'GENERAL' or 'OVERVIEW.' NOTE: Any Activty Code Fields that are complety unused will not be reported upon in the above listing. ---------------------------------------------------------------------------- | ACTIVITY CODES NOT FOUND IN DICTIONARY | | ACT CATEGORY CODE ACTIVITY TITLE | +---------- ---------- ========== -----------------------------------------+ |EC121TL565 TO BENT 52006 ELEV ST-POLK 18TH ST TRACTION POWER | |EC121TL566 TO BENT 52006 ELEV ST-POLK 18TH ST SIGNAL | |EC122TL560 TO BENT 52010 ELEV ST-POLK 18TH ST TRACTION POWER | |EC122TL561 TO BENT 52010 ELEV ST-POLK 18TH ST SIGNAL | |EC124TL555 TO BENT 52012 ELEV ST-POLK 18TH ST TRACTION POWER | |EC124TL556 TO BENT 52012 ELEV ST-POLK 18TH ST SIGNAL | |EC126TL550 TO BENT 52016 ELEV ST-POLK 18TH ST TRACTION POWER | |EC126TL551 TO BENT 52016 ELEV ST-POLK 18TH ST SIGNAL | |EC127TL540 TO BENT 52021 ELEV ST-POLK 18TH ST TRACTION POWER | |EC127TL541 TO BENT 52021 ELEV ST-POLK 18TH ST SIGNAL | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 3302 codes were not found in the dictionary. ERROR: You can have P3 automatically validate added Activity IDs to verify that the Activity ID Code matches one in the dictionary so that you do not have this situation. EXPANDED ACTIVITY ID FIELD LAYOUT (# Activities): Project ID ( 0) Electrical ( 833) Electrical ( 0) Electrical ( 761) Embankment Section ( 43) Project Administration ( 844) Substructure - Elevated Section ( 485) Super Structure - Elevated Section ( 2057) Stations & Buildings LOC. - Primary ( 84) 17th Street Substation ( 9) 18th Street Station ( 137) Belt Line Bridge ( 7) Laramie St. to 50th St. ( 34) Laramie Street Area ( 32) 54th St. - Laramie St. (Station Area 425-411) ( 19) Busway ( 7) 54th Street Area ( 7) 54th & Cermak Station ( 102) 54th and Cermak ( 215) 54th Yard ( 8) Administration ( 1) Code " ALL" ( 15) Vehicle Wash Facility ( 43) Track and Signal ( 13) Signalman's Facility ( 59) Switchman's Facility ( 29) Transportation Office Building ( 126) California Station ( 110) Central Park ( 125) Damen Station ( 29) Douglas Substation ( 0) Engineering ( 0) Code " GL0" ( 82) Harding Substation ( 50) Hermitage Substation ( 127) Kedzie Station ( 85) Kostner Station ( 24) Code " M/S" ( 0) Milestone ( 11) Mobilization ( 0) Code " O&P" ( 7) PAULINA SUBSTATION ( 57) Polk Station ( 122) Pulaski Station ( 0) Relay House ( 1197) Submittal ( 58) Transportation Office Building ( 1) Utility ( 119) Western Station LOC. - Secondary ( 0) Fare Collect. #2 ( 61) Phase 1E ( 37) Phase 1W ( 461) Ground Level ( 199) Code " LW" ( 82) North Bound ( 136) Code " NM" ( 32) Phase 2 ( 32) Phase 3 ( 128) South Bound ( 953) Station House ( 17) Station ( 613) Track Level NOTE: Look through the above list for under-represented codes. This might indicate missing activities or a lack of proper detail. Nearly identical descriptions might be in error and will lead to confusion. Missing codes may indicate missing work. EXPANDED ACTIVITY CODE FIELD LAYOUT (# Activities): TO BENT ( 5) Code " 54090" ( 2) Code " 54091" ( 2) Code " 55013" ( 2) Code " 55023" ( 5) Code " 55038" ( 2) Code " 55039" ( 2) Code " 55040" ( 5) Code " 55041" ( 9) Code " 55044" ( 2) Code " 55045" ( 2) Code " 55046" ( 5) Code " 55047" ( 2) Code " 55048" ( 3) Code " 55049" ( 14) Code " 55050" ( 2) Code " 55051" ( 4) Code " 55052" ( 2) Code " 55053" ( 5) Code " 55054" ( 5) Code " 55055" ( 2) Code " 55056" ( 5) Code " 56036" ( 2) Code " 56057" ( 6) Code " 57010" ( 8) Code " 57014" FROM BENT ( 6) Code " 54090" ( 4) Code " 54091" ( 2) Code " 55013" ( 2) Code " 55023" ( 4) Code " 55038" ( 2) Code " 55039" ( 2) Code " 55040" ( 5) Code " 55041" ( 5) Code " 55044" ( 2) Code " 55045" ( 2) Code " 55046" ( 9) Code " 55047" ( 3) Code " 55048" ( 2) Code " 55049" ( 7) Code " 55050" ( 2) Code " 55051" ( 5) Code " 55052" ( 2) Code " 55053" ( 5) Code " 55054" ( 6) Code " 55055" ( 2) Code " 55056" ( 6) Code " 56036" ( 7) Code " 56057" ( 7) Code " 57010" ( 10) Code " 57014" TYPE OF WORK ( 10) ADMINISTRATION ( 0) ALL AREAS ( 0) AMERITECH ( 97) BALLASTED TRACK WORK ( 0) Code " BLT" ( 31) BRIDGE STEEL ( 85) COLUMN ADJUSTMENTS ( 340) CAISSONS ( 17) Code " CAN" ( 12) CUT AND THROW ( 0) Code " COL" ( 0) COMM-ED ( 15) Code " CWA" ( 75) Code " D/W" ( 48) DUCTBANK ( 101) DEMOLITION ( 0) DESIGN ( 12) ELEVATOR ( 94) STATION ELECTRICAL ( 0) ELEVATED TRACK WORK ( 7) ESCALATOR ( 72) FOUNDATION ( 54) FIBER GLASS ( 73) Finish Work ( 17) Flatwork ( 13) FENCING ( 22) Code " FPR" ( 86) GRADING ( 1) Code " GRX" ( 39) HVAC ( 1) Code " LDS" ( 44) MASONRY ( 1) Code " MIL" ( 46) MISCELLANEOUS ( 81) Misc. Metal ( 2) MOBILIZATION ( 26) MILESTONE ( 6) OTHER UTILITY ( 30) Code " PAI" ( 31) Paving ( 0) PERMIT ( 26) Plumbing ( 3) TEMP PLATFORM ( 0) Code " PLT" ( 14) PAINTING ( 0) POLE WORK ( 28) Code " RCA" ( 8) REMOVALS ( 0) RETAINING WALL CONSTRUCTION ( 8) Code " RST" ( 0) STRUCTURAL STEEL & TRACK WORK ( 502) SIGNAL / COMMUNICATIONS ( 13) Code " SBA" ( 1) STRUCTURE BACKFILL ( 40) SHORING - TYPE 1 ( 24) SHORING - TYPE 2 ( 69) SHORING - TYPE 3 ( 0) Code " SHO" ( 0) Code " SMT" ( 28) SUPPORT OF EXCAVATION ( 10) Slab on grade ( 118) Code " SPE" ( 0) SPREAD FOOTINGS ( 44) Code " SSL" ( 12) STATION STRUCTURAL STEEL ( 25) SPECIAL TRACK WORK ( 169) MAINLINE STRUCTURAL STEEL ( 2) Code " STR" ( 31) Code " STS" ( 33) STRUCTURE EXCAVATION ( 355) SUBSTRUCTURE ( 157) SUBSTATION ( 0) Code " TIE" ( 31) ELEVATED TRACK WORK ON EXISTING STEEL ( 102) Code " TMP" ( 22) TEMP PLATFORM ( 200) TRACTION POWER ( 1) Code " TRA" ( 6) Code " TTP" ( 7) Code " TTS" ( 0) Code " TW " ( 72) UTILITIES ( 105) WALL COMPONENT ( 40) Administration ( 613) Architectural ( 9) Building Type of Work ( 83) Column Adjustments ( 338) Caissons ( 588) Concrete Work ( 1055) Electrical Work ( 107) Mechanical ( 1180) Submittals ( 4) Structural Steel ( 137) Station Structural Steel ( 278) Structural Steel & Track Installation ( 383) Sitework ( 190) Track Work ( 0) Utility Work ( 2) Yard Work WORK TYPE ( 1) Code " 264" ( 5) CAR WASHER BUILDING ( 778) BENTS ( 78) SUBSTATION BUILDING ( 792) STATION HOUSE ( 43) SIGNALMAN'S BUILDING ( 44) SWITCHMAN'S BUILDING ( 0) BUS TURNAROUND ( 58) TRANSPORTATION BUILDING ( 22) CANOPY ( 0) COMMUNICATION WORK ( 0) DEMO ( 0) ASBESTOS ABATEMENT ( 0) LEAD PAINT ABATEMENT ( 0) SUBSTATION EQUIPMENT ( 0) UNDERGROUND STORAGE TANK WORK ( 42) FOUNDATIONS ( 0) KILDARE AVE GRADE CROSSING ( 0) 54TH AVE GRADE CROSSING ( 0) KOSTNER AVE GRADE CROSSING ( 0) KILBOURNE GRADE CROSSING ( 0) 47TH AVE GRADE CROSSING ( 0) 47TH COURT GRADE CROSSING ( 0) CICERO AVE GRADE CROSSING ( 0) 49TH AVE GRADE CROSSING ( 0) 50TH AVE GRADE CROSSING ( 0) LARAMIE GRADE CROSSING ( 552) GENERAL WORK ( 0) PERMITS ( 14) PLATFORM ( 0) PROCUREMENT ( 0) PAULINA JUNCTION RELAY HOUSE ( 0) KILBOURNE RELAY HOUSE ( 0) 50TH AVE RELAY HOUSE ( 0) 54TH AVE RELAY HOUSE ( 0) LOOMIS STREET RELAY HOUSE ( 0) HARRISON STREET RELAY HOUSE ( 0) 17TH STREET RELAY HOUSE ( 0) 18TH STREET RELAY HOUSE ( 0) HOYNE/LEAVITT RELAY HOUSE ( 0) ALBANY AVE RELAY HOUSE ( 0) CENTRAL PARK RELAY HOUSE ( 0) PULASKI RELAY HOUSE ( 1167) SUBMITTALS ( 222) SUPERSTRUCTURE ( 0) TESTING AND INSPECTION ( 0) TRACTION POWER ( 1) TEMP PLATFORM ( 0) TEMPORARY TRAFIC CONTROL ( 0) TEMPORARY PLATFORM WORK ( 0) TEMPORARY SIGNAL WORK ( 197) TRACKWORK ( 16) UTILITIES & SITEWORK ( 0) 54TH YARD - GENERAL LOCATION-CTA ( 44) 17TH STREET SUBSTATION ( 12) 18TH STREET STATION ( 134) FROM 18TH STATION TO DAMEN STATION ( 148) 54TH STREET STATION ( 0) 54TH STREET SUBSTATION ( 242) 54TH YARD ( 145) BELT BRIDGE ( 47) SIGNALMAN'S FACILITY ( 59) SWITCHMAN'S FACILITY ( 86) TRANSPORTATION OFFICE BUILDING ( 223) CALIFORNIA STATION ( 140) FROM CALIF. STATION TO KEDZIE STATION ( 196) CENTRAL PARK STATION ( 49) CICERO STATION (BELT BRIDGE TO 54TH ST) ( 262) DAMEN STATION ( 75) FROM DAMEN STATION TO WESTERN STATION ( 7) DOUGLAS SUBSTATION ( 22) DOUGLAS SUBSTATION ( 6) Code " GEN " ( 40) HARDING SUBSTATION ( 39) Code " HER " ( 14) Hermitage Substation ( 234) KEDZIE STATION ( 72) FROM KEDZIE STATION TO CP STATION ( 196) KOSTNER STATION (KEELER ABUT. TO BELT BRIDGE) ( 9) LAKE CONNECTOR ( 2) Mobilization ( 144) ODGEN BRIDGE (FROM CP STATION TO PULASKI STATION ( 65) INCLINE TO POLK STATION ( 27) POLK STATION ( 238) FROM POLK STATION TO 18TH STATION ( 233) PULASKI STATION ( 59) FROM PULASKI STATION THRU KEELER BRIDGE ( 164) Sysem Wide ( 0) VEHICLE WASH STATION ( 229) WESTERN STATION ( 52) FROM WESTERN STATION TO CALIF. STATION WORK PACKAGE ( 0) CONSTRUCTION CONTRACT ADMINISTRATION ( 0) CTA FORCE ACCOUNT ( 0) CONSULTANTS ( 0) CONTINGENCIES ( 276) CPBL1 - SUBSTATIONS ( 2175) CPBL2 - ELEVATED STATIONS & STRUCTURE ( 1126) CPBL3 - BALLAST SECTION ( 376) CPBL4 - SIGNAL AND COMMUNICATIONS ( 0) CPBL5 - ARTWORK ( 0) CONTRACTURAL TECH. SUPPORT ( 0) FINANCE COSTS ( 32) GENERAL CONDITIONS ( 0) OWNER CONTROLLED INS. PROGRAM ( 0) PROJECT ADMINISTRATION ( 0) PA1 - COMMONWEALTH EDISON ( 0) PA2 - TRAFFIC SIGNAL RELOCATION ( 0) PA3 - STREET LIGHT RELOCATION ( 0) PA4 - LANDSCAPING ( 0) PA5 - OTHER UTILITIES ( 0) PA6 - AMERITECH ( 0) PA7 - FARE CONTROL EQUIPMENT ( 0) PA8 - SIGNAL TECH SUPPORT ( 0) PA9 - OTHER RAILROAD FLAGGING ( 0) PROPERTY COSTS ( 0) PROGRAM MANAGER ( 0) RELOCATION ( 0) SAFETY PROJECT IDENT ( 0) ART WORK ( 0) BID AND AWARD ( 4997) CONSTRUCTION ( 0) FINAL ENGINEERING ( 0) OTHER, FINANCING AND CONTIGENCY ( 0) PROJECT ADMINISTRATION ( 0) PRELIMINARY ENGINEERING ( 0) REAL ESTATE INTERIM M. S. ( 0) 17TH SUBSTATION COMPLETE ( 0) HERMITAGE SUBSTATION COMPLETE ( 0) COMPL DAMEN STATION FROM 54025-54049 NTP+810 ( 0) COMPL WESTERN STATION FROM 54064-54091 NTP+810 ( 0) COMPL CALIF STATION FROM 54122-55008 NTP+810 ( 0) COMPL KEDZIE STATION FROM 55049-56021 NTP+810 ( 0) COMPL CP STATION FROM 56039-56057 NTP+810 ( 0) COMPL PULASKI STATION FROM 56101-57014 NTP+810 ( 0) COMPL BARRIER FENCE @ 54TH ST. NTP+200 ( 0) TEMPORARY INTERLOCKING @ 53RD ST. - 21 DAYS ( 0) COMPL 54TH ST. STATION & BUSWAY NTP+610 ( 0) COMPL 54TH ST. YARD FOR 80 CAR STORAGE NTP+910 ( 0) SHUT DOWN 54TH ST. YARD - 56 DAYS ( 0) SUBMIT SIGNAL BLOCK DIAGRAM FOR CPBL-4 NTP+105 CHANGE ORDER ( 0) ORIGINAL CONTRACT WORK ( 0) CHANGE ORDER #1 ( 0) CHANGE ORDER #2 ( 0) CHANGE ORDER #3 ( 1) CHANGE ORDER #4 D/W/M - BE ( 0) MINORITY BUSINESS ENTERPRISE ( 0) MINORITY BUSINESS ENTERPRISE SLOW ZONE TYPE ( 90) Code " 1 " ( 98) Code " 2 " ( 86) Code " 3 " ( 77) Code " 4 " ( 0) CONSTRUCTION SLOW ZONE ( 0) INFRASTRUCTURE SLOW ZONE ( 8) Code " K/D" ( 0) TEMPORARY FLAGGING ZONE Responsibility ( 498) ALDERIDGE ELECTRIC ( 0) AMERITECH ( 0) CITY BUILDING DEPT. ( 0) CITY SEWER DEPT ( 0) CITY WATER DEPT ( 0) COMMONWEALTH EDISON ( 1) CHICAGO TRANSIT AUTHORITY ( 327) DIVANE BROTHERS ELECTRICAL ( 3365) Code " K/D " ( 5) KIEWIT/DELGATO AJV ( 796) SUBCONTRACTOR - NOT ASSIGNED Spec. Division ( 0) Code " 03300" [list trimed for demonstration] ( 3) Code " 9901 " ( 14) Code " 9901.10 " ( 2) MISC Units ( 13) Code " BF" ( 561) Code " CY" ( 1003) Code " EA" ( 26) Code " LB" ( 59) Code " LF" ( 2466) Code " LS" ( 362) Code " SF" ( 17) Code " SY" ( 34) Code " TF" ( 53) Code " TN" NOTE: Look through the above list for under-represented codes. This might indicate missing activities or a lack of proper detail. Nearly identical descriptions might be in error and will lead to confusion. Missing codes may indicate missing work. WBS Code Check: No Work Breakdown (WBS) Assignments exist. NOTE: Use of WBS assignments is becoming increasingly more prevalent, especially in large, enterprise scheduling situations. It has the built-in ability to summarize groups of activities without adding additional logical relationships, such as required by hammocks. ============================== RELATIONSHIPS =============================== ----------------------- RELATIONSHIP STANDARDS CHECK ----------------------- Lags used on this project are larger than the maximum used in the standard. Odd relationship pairs (not SS/FF pairs) are used in violation of standards. Activity pairs have up to 2 relationships in violation of standards. ---------------------------------------------------------------------------- This project has a total of 7899 relationships. 0 relationships are bogus. 0 Hammock Activities are missing required relationships. 0 Hammock Activities have ignored relationships. There are no logical predecessors to NOTICE TO PROCEED. No early activities were found not related to NOTICE TO PROCEED. ---------------------------------------------------------------------------- | ACTIVITIES WITHOUT PREDECESSORS | | ACT START FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |EC000090 16JUL01 1081 Substn.-Elect.-Des Mtg. | |EC0010 16JUL01 1082 Milestone 4-1: Signal Block Diagram | |EC17TGL003 16JUL01 879 Preparation work @ Jobsite | |EC17TGL005 16JUL01 879 Substation Design Meeting | |EC18TGL498 16JUL01 1023 Equipment Racks | |EC372XX176 16JUL01 1007 BELT BRIDGE AREA - traction power | |EC54CGL268 16JUL01 1072 Preparation work @ Jobsite | |EC54CGL269 16JUL01 1067 Temporary Power & Lighting | |EC54CGL271 16JUL01 1067 ComEd Service Changes & Coordination | |EC54CGL281 16JUL01 1077 Relocate Ameritech Phone Service | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 44 activities were found without logical predecessors. CAUTION: A perfect schedule will only have one activity without a logical predecessor and that activity should be Notice To Proceed. Schedules created this way are easier to manage and use for delay analysis. This also prevents activities that start too early. ---------------------------------------------------------------------------- | ACTIVITIES WITHOUT SUCCESSORS | | ACT FINISH FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |EC000090 16JUL01 1081 Substn.-Elect.-Des Mtg. | |EC0010 13JUL01 1082 Milestone 4-1: Signal Block Diagram | |EC17TGL007 17OCT01 1015 ComEd Service Changes & Coordination | |EC17TGL008 28AUG01 1050 Miscellaneous Power Devices | |EC17TGL009 16AUG01 1058 ITC/Local Control Panels | |EC17TGL011 21SEP01 1033 Getaway Ductbanks | |EC17TGL012 29NOV01 986 Install ductbank with conduit | |EC17TGL013 22AUG01 1054 Install Lighting Fixtures | |EC17TGL014 16OCT01 1016 AC Metering Equipment/Panels/ATS | |EC17TGL015 13JUN02 850 Install Substation Battery System | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 248 activities were found without logical successors. CAUTION: A perfect schedule will only have one activity without a logical successor and that activity should be Project Complete. Schedules created this way are easier to manage and use for delay analysis. This also prevents activities with incorrect float values. ---------------------------------------------------------------------------- | SUBMITTAL ACTIVITIES WITHOUT SUCCESSOR REVIEW ACTIVITIES | | ACT DURATION FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |EMSMTKE005 1 1531 Prepare/Submit Keeler Bridge Dwg | |PAMOB00020 100 1450 Submittals | |SBSMT00490 29 159 Column Adj. - Work Plan/Submittals - Prepare | |SBSMT00530 29 159 Column Adj. - Work Plan/Submittals- Approve | |SBSMT00540 20 24 Caissons - Work Plan/Submittals - Prepare | |SBSMT00550 15 24 Caissons - Work Plan/Submittals - Approve | |SPSMT00100 20 735 Track Work - Work Plan/Submittals- Prepare | |SPSMT00110 15 735 Track Work - Work Plan/Submittals- Approve | |SPSMT01000 90 210 Prepare/Submit Shop Dwg-PUL2 | |SPSMT01030 90 195 Prepare/Submit Shop Dwg-PUL1 | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 11 SUBMITTAL activities have no REVIEW activity successors. CAUTION: Every submittal activity should normally be immediately follow- ed by a review activity. This ensures that sufficient time is al- lotted between the submittal and the need for the submitted items. The review activity should have a delivery or actual use successor. ---------------------------------------------------------------------------- | REVIEW ACTIVITIES WITH MISSING SUCCESSORS | | ACT FINISH FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |ECHERGL104 22OCT01 1038 Review/Connect to Existing Transformers | |STSMTRE425 27AUG01 1051 REVIEW MECHANICAL INSULATION | ---------------------------------------------------------------------------- 2 REVIEW activities were found without logical successors. CAUTION: Every review activity should logically lead to a portion of the schedule where the submittal is required in order to continue. This will allow you to determine the float time available for that review. Critical reviews can often be expedited with advance notice to the reviewer as long as criticality is known beforehand. CAUTION: Don't forget to include fabrication and delivery time as a successor to REVIEW if the material is not available off-the-shelf from a local source. ---------------------------------------------------------------------------- | MULTIPLE NEAR-CRITICAL PATH ACTIVITIES | | ACT # PATHS FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |ECPOLTL107 2 0 SIGNAL/COM REMOVALS | |ECSWTL127 2 0 SCADA/CONTROL CENTER | |PAMOB00011 2 0 Mobilization 5% | |PAMOB00021 2 0 Mobilization 20% | |PAMOB00031 3 0 Mobilization 45% | |PAMOB00041 2 0 Mobilization 50% | |PAMOB00051 3 0 Mobilization 60% | |PAMOB00061 4 0 Mobilization 70% | |PAMOB00081 2 0 Mobilization 90% | |PAMOB00091 2 0 Mobilization 100% | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- More than 11 multiple, independent near-critical activities found. NOTE: Project Critical Float is 0 and any activity with a float value within 10 of this was considered as near-critical. As this is a Baseline Schedule, A Project Critical Float of 0 was used. CAUTION: CPM networks should not have multiple critical paths without through justification. Some Contractors adjust durations, logic, and lead times so as to artificially create multiple paths. This increases the number of critical activities which increases the potential that any Owner-caused delay will look like a delay to the project. Detail analysis of the above activities is recommended. 0 out of a possible of 0 relationship chains are interruptible. ---------------------------------------------------------------------------- | ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS (NOT SS & FF PAIRS) | | PRED ACT SUCC ACT RELS. TITLE | +---------- ---------- -------- -------------------------------------------+ |SB342T3118 ------- FS SS SPREAD FTGS-57020 TP 3 | | SB32910100 2 Rels. COL/CAP - PIER-56120 TP 10 | | | ---------------------------------------------------------------------------- 1 multiple relationship is found. ERROR: Two activities that share more than one relationship is highly unusual. The only exception to this rule is if a Start-To-Start (SS) relationship is used with a Finish-To-Finish (FF) relationship. Any othe combination, or when more than two relationships are used is likely to be an error. 0 apparent odd relationships found. ---------------------------------------------------------------------------- | ODD LAGS OR LEADS USED | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |EC17TGL003 ---------- ---- --- Preparation work @ Jobsite | | EC17TGL004 2 FS Temporary Power & Lighting | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL008 3 FS Miscellaneous Power Devices | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL009 3 FS ITC/Local Control Panels | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL010 2 FS Rough In Work @ Substation | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL011 5 FS Getaway Ductbanks | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL012 5 FS Install ductbank with conduit | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL013 3 FS Install Lighting Fixtures | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL014 3 FS AC Metering Equipment/Panels/ATS | | | |EC17TGL004 ---------- ---- --- Temporary Power & Lighting | | EC17TGL016 3 FS Substation Telephone System | | | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 85 odd lags are listed above. NOTE: Lags and Leads are time intervals imposed between two activities. They are legitimately used to describe linked activities which are staggered or to represent a time interval, say for curing concrete. They can be also used to 'hide' float or otherwise artificially expand a project schedule without being visible on plots or in most reports. Negative lags can hide an unworkable project schedule by shortening it without changing activity durations. CAUTION: It is highly unusual for Start-to-Start (SS) or Finish-to- Finish (FF) relationships to have negative lags. Recommend further investigation into the reasoning behind such timing. CAUTION: It is highly unusual for Finish-to-Start (FS) relationships to have positive lags. Recommend that you have the creator of the schedule document what that lead represents. You must consider the calendar when using lags. Lags use the calendar of the proceeding act. In the case of concrete curing (a 7-day/week event,) the lag would use the calendar of the concrete pour, which is probably a 5-day/week event. Just expanding the length by 7/5 does not fully consider where in the week it falls. Lags make for poor long-lead times. You cannot status a lag or periodically review its progress. For lags of long duration (such as the delivery of a major piece of equipment,) it would be better to create an activity that would show-up on reports and would need to be statused every update. CAUTION: While lags and leads have legitimate uses, any such time inter- val over 5 should be individually investigated. ---------------------------------------------------------------------------- | ALL OTHER LAGS OR LEADS (OTHER THAN ODD) USED | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing| | EC17TGL007 1 SS ComEd Service Changes & Coordination | | | |EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing| | EC17TGL020 1 SS Transformer Shop Dwgs | | | |EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing| | EC17TGL026 1 SS DC Switchgear Shop Dwgs | | | |EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing| | EC17TGL032 1 SS Rectifier Shop Dwgs | | | |EC17TGL006 ---------- ---- --- 17th Street Substation Installation Drawing| | EC17TGL038 1 SS Medium Voltage Switchgear Shop Dwgs | | | |EM17TXX110 ---------- ---- --- 17th - SUBSTN - LAG PILE | | EM17TXX120 5 SS 17th - SUBSTN - STRUCTURE EXC | | | |EM343SB206 ---------- ---- --- KEEL WALL N. - 342+50 - ANCHOR PILE | | EM343SB210 -5 FS KEEL WALL N. - 342+50 - DEMO EXIST WALL | | | |EM343SB208 ---------- ---- --- KEEL WALL N. - 342+50 - STR. EXC. | | EM343SB210 -5 FS KEEL WALL N. - 342+50 - DEMO EXIST WALL | | | |EM412ST106 ---------- ---- --- 54TH STR. STA - 412 to 424 - F&P WALLS | | EM412ST128 -5 FS 54TH STR. STA - 412 to 424 - F&P PLATFORMS | | | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 533 'standard' lags were found. NOTE: While usually considered acceptable for use in schedules, lags and leads should always be reviewed for reasonableness. In other words, there should be a reason for having each lag. If that reason is not apparent to you, then you should ask for it. ---------------------------------------------------------------------------- | NON-OVERLAPPING LAGS USED | | PRED ACT SUCC ACT LAG REL TITLE | +---------- ---------- ---- --- -------------------------------------------+ |EM17TXX110 ---- DUR = 3 --- 17th - SUBSTN - LAG PILE | | EM17TXX120 5 SS 17th - SUBSTN - STRUCTURE EXC | | | |STCALSH025 ---- DUR = 1 --- BLDG INSUL-VAPOR BAR | | STCALSH101 -3 FS CIP CONC-STATION -SLABS | | | |STCENSH025 ---- DUR = 2 --- BLDG INSUL-VAPOR BAR | | STCENSH101 -3 FS CIP CONC-STATION -SLABS | | | |STDAMSH025 ---- DUR = 1 --- BLDG INSUL-VAPOR BAR | | STDAMSH101 -3 FS CIP CONC-STATION -SLABS | | | |STKEDSH025 ---- DUR = 1 --- BLDG INSUL-VAPOR BAR | | STKEDSH101 -3 FS CIP CONC-STATION -SLABS | | | |STPULSH025 ---- DUR = 1 --- BLDG INSUL-VAPOR BAR | | STPULSH101 -3 FS CIP CONC-STATION -SLABS | | | |STWESSH025 ---- DUR = 1 --- BLDG INSUL-VAPOR BAR | | STWESSH101 -3 FS CIP CONC-STATION -SLABS | | | ---------------------------------------------------------------------------- 7 non-overlapping lags are listed above. NOTE: Lags are typically used to show the overlapping nature of two activities. If the lag used is too great, the activities will no longer overlap in time. This may be an entry error. Otherwise, suggest that you convert to a different relationship that better describes the intended relationship. ---------------------------------------------------------------------------- | ACTIVITIES WITHOUT A FINISH RELATIONSHIP | | ACT FLOAT TITLE | +---------- -------- ----- ------------------------------------------------+ |EC17TGL006 841 17th Street Substation Installation Drawings | |EC203TL415 231 ELEV ST-DAM-STATION (TR2) TRACTION POWER | |EC203TL417 231 ELEV ST-DAM-STATION (TR2) SIGNAL | |EC203TL420 217 ELEV ST-DAM-STATION (TR1) TRACTION POWER | |EC203TL422 217 ELEV ST-DAM-STATION (TR1) SIGNAL | |EC305TL140 273 ELEV ST-CP STATION (TR2) TRACTION POWER | |EC305TL141 273 ELEV ST-CP STATION (TR2) SIGNAL | |EC54TGL127 921 54th Street Substation Installation Drawings | |EC54YGL394 907 ComEd Ductbanks | |EC54YGL422 674 Prep work @ Site | | *** REMAINING LIST OF ACTIVITIES TERMINATED DUE TO LENGTH *** | ---------------------------------------------------------------------------- 257 Activities are missing Finish Relationships. NOTE: The above activities do not have any constraint on completion, other than perhaps their start day. With the existing configuration a shortening or lengthing of the activity's duration will have no effect on project completion. Confirm that no succeeding activity is limited by this completion of this activity or add a FS or FF relationship to the appropriate activity. ================================ CONSTRAINTS =============================== ------------------------ CONSTRAINT STANDARDS CHECK ------------------------ Hammocks are used in violation of standards. ---------------------------------------------------------------------------- 0 constraints are bogus. ---------------------------------------------------------------------------- | BASELINE SCHEDULE CONSTRAINTS | | ACT C-TYPE DATE TITLE | +---------- ------ ------- ------------------------------------------------+ |EC343XX100 SNET 1OCT01 TEMP ELEC KEELER TO BELT BRIDGE | |EC3721W384 SNET 1OCT01 MJ BRD PH 1W TRACTION POWER | |EC412SB250 SNET 17SEP01 LAR-54TH - 411 to 425 traction power | |EM343XX102 SNET 29APR02 TEMP R.ROUND - 343 - FOOTINGS | |EM349NB100 SNET 27APR02 KILDARE XING NB - 349 - W/END REPL | |EM398SB100 SNET 17SEP01 LAR-50TH - 411 to 398 - Exc. Track | |EM412SB200 SNET 10SEP01 N. FENCE WALL - Rem Exist Fence - 424 to 410 | |EM54Y3B344 SNET 11JUL02 STAGE 3B - 54TH YARD - EXCAVATION | |EMBSWXX100 SNET 15OCT01 SWITCHMAN'S FAC. - DEMO SWITCH FAC. | |EMSMTXX010 SNET 1AUG01 MJ BRD - STR. STL. - SHOP DWGS - PREPARE | |EMSMTXX200 SNET 6AUG01 N. FENCE WALL - WORK PLAN/SUB - PREPARE | |PAADM00020 SNET 16JUL01 Notice To Proceed | |SB342T3104 SNET 5NOV01 SPREAD FTGS-57027 TP 3 | |SBSMTXX100 SNET 13AUG01 COL/CAP - SHOP DWG/WORK PLAN - PREPARE | |SBSMTXX130 SNET 20AUG01 SPREAD FTGS - SHORING PLAN - PREPARE | |SP212TP090 SNET 24SEP01 TEMP PLTFM WEST/DAM-Inst Below | |SP256TP070 SNET 24SEP01 TEMP PLTFM CAL-Inst Below | |SP295TP030 SNET 24SEP01 TEMP PLTFM CP-Inst Below | |SP337TP010 SNET 24SEP01 TEMP PLTFM PUL-Inst Below | ---------------------------------------------------------------------------- 19 constraints were found in the project. CAUTION: Baseline Schedules should only contain constraints that are specifically called out in the plans and specifications. Otherwise, this can be thought of as the Contractor is "reserving float" (which is typically not allowed.) NOTE: If the Contractor resists removing non-contractual constraints, from the Baseline Schedule, the prudent Scheduler will note each such constraint in the review of the baseline and state that the Owner reserves the right to temporarily delete any such constraint when evaluating the effects of delays. 0 activities were coded for Zero Free Float. 0 Zero Total Float constraints were found in the project. 0 active Expected Finish constraints were found in the project. 0 improper Expected Finish constraints were found in the project. 0 Mandatory Start/Finish constraints were found in the project. 0 active START ON constraints were found in the project. ================================ COST CHECKS =============================== --------------------------- COST STANDARDS CHECK --------------------------- Cost Records are used in violation of standards. Cost Records for Task-type activities are used in violation of standards. ---------------------------------------------------------------------------- There are no cost accounts in this project to check. There appears to be cost information under Resources. ================================ LOG CHECKS ================================ ------------------------- LOG FILE STANDARDS CHECK ------------------------- Standard Log Records are not used on this project. ---------------------------------------------------------------------------- No Logs were found in the schedule. ============================== END OF REPORT =============================== Analysis complete at 16:56:24.