Schedule Analyzer Upgrade Information

 
 
 
  Below is the entire update history of Schedule Analyzer for the Enterprise (SAe.) The current version is listed at the top. Registered, licensed Users are encouraged to look-up the version of their SAe software and reference the current updates here.
 
Key:
ALL: All SAe programs.
BASELINE: SAe Baseline Checker (released December 2003.)
DASHBOARD: SAe Dashboard (added May 2006.)
STEPS: File Transfer Steps Remover (added April 2005, removed June 2015.)
LOGGER: SAe Schedule Logger (added July 2007.)
LOGIC: SAe Logic League (created 2003 and added to SAe February 2008.)
LONGPATH: SAe Longest Path Software (released December 2003.)
UPDATE: SAe Update Checker (released December 2003.)
MENU: SAe Menu Program (released August 2011.)
REPORT: SAe Report Writer Program (released June 2015.)
POBS: SAe Purge POBS Program (released June 2015.)

CURRENT VERSION:
Version 4.53 (September 2023)
OVERVIEW: FIX DISCUSSIONS REPORT
Fixed the ADDED ACTIVITY DISCUSSIONS report 153 error after Primavera added a new column in the Discussion table in Version 22.
Version 4.52 (August 2023)
OVERVIEW: PREVENT OVERREPORTING OF SUBMIT WITHOUT REVIEW SUCCESSORS
BASELINE: Ignore Submit not followed by a REview if Submit is followed by Re-Submit.
Version 4.51 (August 2022)
OVERVIEW: FIXED ACTUAL DATES WITH INCORRECT TIMES REPORT
UPDATE: Fixed Actual Dates with Incorrect Times for calendars that cross into the next day.
Version 4.50 (March 2022)
OVERVIEW: BASELINE CHECKER PRINTS OUT VERY LONG ACTIVITY IDS
UPDATE: Fixed the ability to display very long activity IDs (more than 20 characters).
BASELINE: Fixed the Fractional Durations Report for activities without fixed duration types.
Version 4.49 (November 2021)
OVERVIEW: FIXED CALENDAR WORKDAY LISTING DUE TO P6 INTERNAL CHANGE
BASELINE: Fixed the listing of calendar workdays and hours..
UPDATE: Fixed the listing of calendar workdays and hours..
CALENDAR: Fixed the listing of calendar workdays and hours..
Version 4.48 (October 2021)
OVERVIEW: NEW BASELINE CHECKER REPORT
UPDATE: Added a check for mismatching times for data dates.
BASELINE: Added new REPATIONSHIP COMMENTS INCLUDED report.
Version 4.47 (August 2021)
OVERVIEW: REPORT WRITER UPGRADES
REPORT: Display the default printer in the Options screen.
REPORT: Bullet-proof close on Options screen.
ALL: Updated Jump to P6 function to trim jump speed between 1 and 1000.
Version 4.46 (July 2021)
OVERVIEW: UPDATED ALL BASELINE CHECKER CONSTRAINTS REPORTS
BASELINE: Updated 10 constraint reports to include Active/Inactive status for constraint.
BASELINE: Added new Constrained Critical Activities report.
Version 4.45 (May 2021)
OVERVIEW: UPDATED SAVE FUNCTION ON THE VIEW SCREEN
BASELINE: Improved reporting of number of activities per calendar.
ALL: Added informational warning when program options are changed.
ALL: Improved the File / Save feature of the View Screen.
Version 4.44 (March 2021)
OVERVIEW: ADDED ABILITY TO TURN OFF VOICE PROMPTS
ALL: Added option to turn off/on sounds played.
ALL: Improved View screen jump to P6 feature.
ALL: Updated manual and Help files.
MENU: Fixed Report Writer button display.
Version 4.43 (December 2020)
OVERVIEW: UPDATED ADMIN MANUAL
ALL: Updated the Admin manual to cover current Oracle logon options.
UPDATE: Prevented Error 5 in DELETED ACTIVITY NOTES (ACTIVITY REMAINS) report.
UPDATE: Condition unprintable memo log text.
UPDATE: If more than 26 schedules are being compared, condition the identifier for the extra schedules better.
BASELINE: Create spreadsheet for the entire report if the report is cut-off due to length.
UPDATE: Create spreadsheet for the entire report if the report is cut-off due to length.
BASELINE: Fixed lag printout in NEGATIVE LAGS Report.
BASELINE: Fixed title printout in spreadsheet report.
BASELINE: Allow Spreadsheet creation from the Diagnostics (Summary) screen.
UPDATE: Allow Spreadsheet creation from the Diagnostics (Summary) screen.
Version 4.42 (September 2020)
OVERVIEW: ADDED CONVERT TO CVS DATABASE FILE
ALL: Added save as CVS (database text) file to the View Report window functions for data mining.
DASHBOARD: Added convert report to CVS database format for report summary or activity details (data mining).
Version 4.41 (June 2020)
OVERVIEW: IMPROVED ACCURACY IN CALENDAR DATE CONVERSIONS
UPDATE: Improved accuracy in comparing calendar changes.
Version 4.40 (May 2020)
OVERVIEW: PURGE POBS UPDATE
POBS: Bullet-proofed for XER file ending unexpectedly.
Version 4.39 (January 2020)
OVERVIEW: REMOVED A LEGACY INSTALLER FILE
ALL: Removed MDAC 2.8 from the list of redistributables.
Version 4.38 (December 2019)
OVERVIEW: FIXED UPDATE CHECKER UDF REPORTING
UPDATE: Fixed the over-reporting of User Defined Field checks.
Version 4.37 (October2019)
OVERVIEW: NEW BASELINE CHECKER REPORT
BASELINE: Added MONTHLY MILESTONE Report.
REPORT: Added check to prevent reporting on deleted records.
ALL: Bullet-proofed View Screen to open inside of the viewable screen area.
Version 4.36 (September 2019)
OVERVIEW: IMPROVED OPENING SCREEN HANDLING
ALL: Bullet-proofed spreadsheet tab label naming.
ALL: Bullet-proofed screen positioning beyond viewable area.
ALL: Improved accuracy in creating spreadsheet tabs.
Version 4.35 (September 2019)
OVERVIEW: IMPROVED MULTI-RUN HANDLING
UPDATE: Improved Resource Leveling Settings check's accuracy (old schedules versus new).
ALL: Fixed picking old schedule when making multiple runs.
Version 4.34 (August 2019)
OVERVIEW: NEWLY FORMATTED HELP VIDEOS
UPDATE: Fixed formatting in MODIFIED RELATIONSHIP TYPES Report.
UPDATE: Added documenting missing relationship lag as NULL.
ALL: All newly re-formatted Help videos.
ALL: Bullet-proofed database timeout issues.
ALL: Fixed alignment problem with View Window progress bar.
BASELINE: Fixed hang-up with DCMA Baseline Check (4.31-4.34)
Version 4.33 (July 2019)
OVERVIEW: IMPROVED SPREADSHEET FUNCTION
UPDATE: Added progress reporting during Re-building Activity Database due to SQL ORDER issue repair.
UPDATE: Limited ACTIVITIES WITH DIMINISHING PROGRESS THIS PERIOD Report to only activities that have started.
ALL: Improved spreadsheet quality control (fixes overlapping reports due to Excel not being ready.)
Version 4.32 (May 2019)
OVERVIEW: UPDATE OF POBS
POBS: Fixed POBS purge.
Version 4.31 (May 2019)
OVERVIEW: ENHANCED RELATIONSHIP REPORTS
UPDATE: Added original duration printout to the MODIFIED RELATIONSHIPS report.
UPDATE: Added original duration printout to the MODIFIED LAGS report.
BASELINE: Added original duration printout to the NON-OVERLAPPING LAGS USED report.
BASELINE: Added original duration printout to the ODD LAGS OR LEADS USED report.
BASELINE: Added original duration printout to the ALL OTHER LAGS OR LEADS USED report.
BASELINE: Added original duration printout to the NEGATIVE LAGS USED report.
BASELINE: Added original duration printout to the ACTIVITIES ON REVERSE LOGICAL PATHS report.
BASELINE: Added remaining duration printout to the ACTIVE ACTIVITIES WITH INTERRUPTIBLE LOGIC RELATIONSHIPS report.
BASELINE: Added original duration printout to the FINISH-TO-START LAGS USED Report.
BASELINE: Fixed error in NON-OVERLAPPING LAGS Report.
Version 4.30 (May 2019)
OVERVIEW: IMPROVED FUNCTIONALITY OF OPENING SCREEN
ALL: Added ability to sort opening screen by any column.
ALL: Completely collapse opening screen tree of schedules if Open Collapsed is set.
ALL: Prevent screen opening outside of the current screen.
Version 4.29 (April 2019)
OVERVIEW: UPDATE OF POBS
BASELINE: Added Fix for international system date day/month reversal.
UPDATE: Added Fix for international system date day/month reversal.
POBS: Added purging of Risk Types to process.
Version 4.28 (March 2019)
OVERVIEW: UPDATE CHECKER FORMATTING IMPROVEMENTS
UPDATE: Improved formatting of Longest Path Findings Review.
UPDATE: Corrected the double-counting of Target longest path activities.
UPDATE: Improved spreadsheet functionality.
BASELINE: Improved spreadsheet functionality.
UPDATE: Improved the formatting of reports.
Version 4.27 (February 2019)
OVERVIEW: SPREADSHEET IMPROVEMENTS
ALL: Improved listing of projects order.
LONGPATH: Improved internal UDF management.
UPDATE: Added coded tabs to Update Checker spreadsheet.
BASELINE: Added Warnings/Cautions/Notes to the spreadsheet.
UPDATE: Added Warnings/Cautions/Notes to the spreadsheet.
Version 4.26 (December 2018)
OVERVIEW: LONGEST PATH IMPROVEMENTS
LONGPATH: Modified to make the numbers available to eForensic lag analysis.
LONGPATH: Fixed intermittent errors writing Logical Sequence Numbers to the database.
Version 4.25 (December 2018)
OVERVIEW: NEW CALENDAR FEATURES
ALL: Improved formatting saving a report to Word format.
ALL: Added option to automatically log in.
CALENDAR: Added View calendars of XER/XML Files.
CALENDAR: Added List any calendar in an XER or XML file.
CALENDAR: Added compare any calendar in the database to one in a XER or XML file.
Version 4.24 (October 2018)
ADDED PROGRAM SEARCH ON MAIN SCREEN
ALL: Added Ctrl-F search for program feature on the main screen.
Version 4.23 (July 2018)
OVERVIEW: SPREADSHEET ENHANCEMENTS
BASELINE: Large number of enhancements to spreadsheet function.
UPDATE: Large number of enhancements to spreadsheet function.
Version 4.22 (May 2018)
OVERVIEW: VIEW SCREEN IMPROVEMENTS
ALL: View screen formatting enhancements.
All: View screen suggests the correct Word file extension.
ALL: Upgrade to MDAC 2.8.
BASELINE: Added time-out escape to, RELATIONSHIPS BEFORE NTP Report if NTP is logically very late in the project.
All: Updated Splash Screen.
UPDATE: Fixed ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report from ignoring unstarted ones.
Version 4.21 (March 2018)
OVERVIEW: ADDED NEW LOGIC REPORT.
BASELINE: Added additional guidance to Merge Bias report.
BASELINE: Added Schedule Logic Density Report.
Version 4.20 (February 2018)
OVERVIEW: FIXED TASK TAG FEATURE.
BASELINE: Fixed Task Tag setup feature.
UPDATE: Fixed Task Tag setup feature.
DASHBOARD: Fixed Task Tag setup feature.
Version 4.19 (January 2018)
OVERVIEW: NEW BASELINE CHECKER REPORT.
BASELINE: Added Project Activity Codes have matching Global Activity Codes report.
ALL: Updated the Splash Screen.
Version 4.18 (October 2017)
OVERVIEW: IMPROVED FORMATTING BASELINE CHECKER REPORTS.
BASELINE: Cleaned-up 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report when list is too long to print.
BASELINE: Fixed Activity ID formatting error when Activity IDs have more than the maximum allowed characters.
BASELINE: Added notice about corrupt Activity IDs and reporting adjustment to accommodate this.
MENU: Fixed menu not passing command line parameters on to the next program.
ALL: Sped-up Limit By OBS by command line parameters.
ALL: Sped-up loading of the schedules to be selected list.
UPDATE: Minor report formatting changes made in the Administrative Review Section.
Version 4.17 (September 2017)
OVERVIEW: PREVENT ERROR WHEN SAe TRIES TO REVIEW EPPM DISCUSSION RECORDS.
BASELINE: Skip COMPLETE ACTIVITY DISCUSSIONS Report for EPPM databases.
UPDATE: Skip ADDED ACTIVITY DISCUSSIONS Report for EPPM databases.
Version 4.16 (September 2017)
IMPROVED VIEW FILE/SAVE FUNCTIONALITY
BASELINE: Don't close the View Window until report is generated.
UPDATE: Don't close the View Window until report is generated.
DASHBOARD: Don't close the View Window until report is generated.
LOGGER: Don't close the View Window until report is generated.
LONGPATH: Don't close the View Window until report is generated.
BASELINE: Load report name into View Window File / Save dialog box.
UPDATE: Load report name into View Window File / Save dialog box.
DASHBOARD: Load report name into View Window File / Save dialog box.
LOGGER: Load report name into View Window File / Save dialog box.
LONGPATH: Load report name into View Window File / Save dialog box.
Version 4.15 (August 2017)
IMPROVED LONGEST PATH SOFTWARE
LONGPATH: Increased storage to better accommodate very large schedules.
LONGPATH: Improved in-progress reporting for very large schedules.
Version 4.14 (May 2017)
TWO NEW BASELINE CHECKER REPORTS
ALL: Upgraded handling of Windows forced closing of program.
BASELINE: Added MIS-TYPED START MILESTONES (NO SUCCESSORS) Report.
BASELINE: Added MIS-TYPED FINISH MILESTONES (NO PREDECESSORS) Report.
BASELINE: Added Calendar Workhour Mis-Matches Report.
Version 4.13 (April 2017)
FIX LONGEST PATH NOT WORKING THE SECOND TIME ON THE SAME SCHEDULE.
LONGPATH: Update Longest Path Value and Logical Sequence Number processes to match records already using old protocols.
Version 4.12 (March 2017)
UPDATE TASK TAGS AND LONGEST PATH UDF HANDLING
BASELINE: Update Task Tags to meet new P6 UDF protocols.
UPDATE: Update Task Tags to meet new P6 UDF protocols.
LONGPATH: Update Longest Path Value and Logical Sequence Number to fit new P6 UDF protocols.
LONGPATH: Exit early if calendar not found in the XER file.
Version 4.11 (February 2017)
ADDED OPTION TO ONLY DISPLAY ACTIVE PROJECTS
ALL: Added option to only display active projects.
LONGPATH: Fixed typos in diagnostic report.
UPDATE: Updated Exclude Reports screen to be easier to use.
UPDATE: Added POBS Check to Excluded Reports list.
Version 4.10 (October 2016)
SPEED UP UPDATE CHECKER PROCESSING ON LARGE INSTALLATIONS
UPDATE: Internal adjustment to accommodate very large data installations.
ALL: More error checking added to ensure that the report directory exists.
Version 4.09 (September 2016)
ADDED SUPPORT FOR RAM DISK TO SPEED UP PROCESSING
ALL: Added screen refresh to capture newly added schedules.
BASELINE: Cleaned-up Smart Copy accuracy.
UPDATE: Cleaned-up Smart Copy accuracy.
UPDATE: Cleaned-up Relationship Reports column header.
BASELINE: Added RAM Disk option for working files to speed up processing.
UPDATE: Added RAM Disk option for working files to speed up processing.
LONGPATH: Added RAM Disk option for working files to speed up processing.
ALL: Updated the Splash Screen.
UPDATE: Added check for use of P6 function, Update Progress in the NEW ACTUAL DATES Report.
Version 4.08 (July 2016)
ADDED AND UPDATED REPORTS
BASELINE: Added the 'DELETED' Activity Report.
UPDATE: Modified the ACTIVE ACTIVITIES WITHOUT FLOAT Report to flag Physical Percent Complete activities.
Version 4.07 (June 2016)
FIXED LONGEST PATH NOT WORKING ON VERY LARGE SCHEDULES
UPDATE: Fixed Steps reporting on the same step being both added and deleted.
LONGPATH: Fixed error where all LP Values are 0 for very large schedules.
Version 4.06 (February 2016)
IMPROVED PURGE POBS
PURGE: Improved program to work better on corrupted XER files.
UPDATE: Fixed over-reporting in the DANGLING ACTIVITIES WITH A SINGLE SS OR FF PREDECESSOR Report.
Version 4.05 (December 2015)
ADJUST UPDATE CHECKER FOR INTERNATION DATE SETTINGS
UPDATE: Fixed error in Data Date for international installations that print day before month number in dates.
Version 4.04 (November 2015)
IMPROVED LONGEST PATH SOFTWARE
LONGPATH: Corrected problem reading new format of P6 calendar string.
ALL: Bullet-proofed Directory Settings screen when blank is entered.
Version 4.03 (September 2015)
ADDED WINDOWS 10 COMPATIBILITY
LOGIC: Fixed Error 9 when creating Resource Links.
ALL: Added Windows 10 compatibility.
Version 4.02 (July 2015)
ADDED ABILITY TO LOAD SCHEDULES ON LARGE SERVER INSTALLATOINS FASTER
BASELINE: Added option to not save calendars to a file.
UPDATE: Added option to not save calendars to a file.
BASELINE: Added command line parameters to automatically limit OBS for quicker schedule loading.
UPDATE: Added command line parameters to automatically limit OBS for quicker schedule loading.
LOGGER: Added command line parameters to automatically limit OBS for quicker schedule loading.
LONGPATH: Added command line parameters to automatically limit OBS for quicker schedule loading.
REPORT: Added command line parameters to automatically limit OBS for quicker schedule loading.
Version 4.01 (July 2015)
POBS TABLE CHECK TO BASELINE/UPDATE CHECKER
BASELINE: Limited Suspicious Remaining Duration Report to activities with Physical Percent Complete.
DASHBOARD: Added Actual Dates with Incorrect Times Report.
BASELINE: Added POBS Table Check.
UPDATE: Added POBS Table Check.
Version 4.00 (June 2015)
ADDED TWO NEW PROGRAMS TO SAe
STEPS: Removed Delete Steps from the SAe module list.
REPORT: Added Report Writer module to the list of programs.
POBS: Added Purge POBS to the list of programs.
Version 3.42 (June 2015)
MINOR FUNCTIONALITY IMPROVEMENTS
UPDATE: Improved summary total message in LONGEST PATH LISTING Report.
UPDATE: Minor error checking improvements when opening the report file.
BASELINE: Added Help Button to Interproject Relationships Clean-Up request.
STEPS: Resized programming to accommodate very large files.
ALL: Improved functionality of Directory Picker.
Version 3.41 (April 2015)
IMPROVED EXISTING 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS REPORT
UPDATE: Added stricter control over report date formatting.
UPDATE: Added stricter control over output report naming.
UPDATE: Added more thorough error reporting in report creation process.
BASELINE: Improved formatting of 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report.
BASELINE: Further screen positioning error checks.
ALL: New compile of software.
Version 3.40 (March 2015)
NEW SUSPEND AND RESUME REPORTS
UPDATE: Added check for missing Resume Date when Suspend Date added in SUSPEND DATE STATUS CHANGE Report.
UPDATE: Fixed failure to skip sections under unusual conditions.
UPDATE: Changed SUSPENDED ACTIVITY LISTING to ACTIVE SUSPENDED ACTIVITIES Report
BASELINE: Added ACTIVE SUSPENDED ACTIVITIES Report.
Version 3.39 (March 2015)
COMPATIBLE WITH WINDOWS 8.1 TOUCHSCREEN
UPDATE: Removed check for Resume date in the future and added notes.
BASELINE: Restricted % Complete status checks to Physical % Complete only due to database change.
ALL: Updated Open Screen to work under touchscreen Windows 8.1
BASELINE: Added FINISH MILESTONES WITH MISMATCHED PREDECESSORS Report.
Version 3.38 (December 2014)
IMPROVED 3 UPDATE CHECKER REPORTS
UPDATE: Fixed overreporting in NEW ACTUAL DATES WITH INCORRECT TIMES Report
UPDATE: Added flag to ACTIVITIES WITH MODIFIED ACTUAL START DATES Report when just times are different.
UPDATE: Added flag to ACTIVITIES WITH MODIFIED ACTUAL FINISH DATES Report when just times are different.
Version 3.37 (September 2014)
ADDED 5 NEW REPORTS
BASELINE: Allows histograms to be converted into spreadsheets.
BASELINE: Added ACTUAL DATES WITH INCORRECT TIMES Report.
BASELINE: Added IMPROPER START TIMES FOR CONSTRAINTS Report.
BASELINE: Added IMPROPER FINISH TIMES FOR CONSTRAINTS Report.
BASELINE: Added IMPROPER FINISH TIMES FOR EXPECTED FINISH CONSTRAINTS Report.
UPDATE: Fixed formatting of ACTIVE ACTIVITIES WITHOUT FLOAT Report.
UPDATE: Added ACTIVITIES WITH ORIGINAL DURATION LESS THEN REMAINING DURATION Report.
Version 3.36 (July 2014)
IMPROVED OPENING PROGRAM DISPLAY ACCURACY
ALL: Corrected display of Baseline Names and Data Dates on Main Screen.
UPDATE: Made more resilient to ` character in Activity ID under MS SQL database.
BASELINE: Fixed where changing Suspicious Duration Length changed Report Width.
Version 3.35 (June 2014)
PROGRAMS CAN BE OPENED WITH THE EPS TREE COLLAPSED
UPDATE: Improved calendar checks for Oracle databases.
BASELINE: Caution message in FRACTION OF A DAY DURATIONS Report removed as we now use calendar setting.
Clear SAe Setting: Now also resets ADMUSER ID.
ALL: Programs can be open with the EPS tree fully closed instead of open.
Version 3.34 (May 2014)
AUTOMATICALLY INSTALL SAe CORRECTLY FOR 64-BIT COMPUTERS
ALL: Improved Save as Word document to format font and size.
CALENDAR Read XER file name correctly when extension is in lower case.
ALL: Made parts of the login screen re-sizeable.
All: Automatically install in C:\Schedule Analyzer Enterprise\ directory.
Version 3.33 (March 2014)
ADDED FIXED DEFAULTS FOR LONG TASK DURATIONS REPORT
LOGGER: Picked-up missing description change report activities.
ALL: Added automatic login parameter
BASELINE: Corrected label and default setting in Long Task Duration and Suspicious Durations Reports.
CALENDAR: Added audit information to List Current Calendar Report.
Version 3.32 (March 2014)
FIXED WINDOWS UAC ISSUE WITH UPDATE CHECKER
UPDATE: Renamed program and fixed Windows UAC triggering issue.
Version 3.31 (February 2014)
FIXED 3.30 INTRODECED TESTING STUB
MENU: Removed testing stub that interferred with reading the initialization parameters.
ALL: Fixed ability to set print page orientation
ALL: Better placed progress indicator in View Window.
Version 3.30 (February 2014)
ADDED MISSING SCREEN FIX AND OVERRIDE
ALL: Added Pause/Break 'SAe Window Missing' fix.
ALL: Added QC check for saving Normal Window screen position.
MENU: Added ability to pass-on Citrix INI user override location to selected program.
Version 3.29 (February 2014)
ADDED DUPLICATE ACTIVITY ID REPORT
ALL: Solved Oracle XE 11g database logon, Provider cannot be found error.
BASELINE: Added the DUPLICATE ACTIVITY IDs Report.
Version 3.28 (December 2013)
ADDED GENERATE 'PART 2' REPORT WHEN THE REPORT TOO LONG TO DISPLAY
ALL: Added Longer Activity Titles video to View Help.
BASELINE: Added automatic generation of multi-part reports when they overflow the size limits.
UPDATE: Added automatic generation of multi-part reports when they overflow the size limits.
Version 3.27 (November 2013)
ADDED TWO NEW REPORTS TO UPDATE CHECKER
ALL: Improved Oracle SQL parsing of dates.
UPDATE: Added the ACTIVITIES THAT COULD HAVE STARTED THIS PERIOD Report.
UPDATE: Added POSSIBLE ACTIVITY MISMATCHES DUE TO ID MODIFICATION Report.
Version 3.26 (October 2013)
IMPROVED LOOK OF LOGIN SCREEN
ALL: Modified login screen (moved Logon Button to the top) to allow Hide Settings to work better.
BASELINE: Further bullet-proofed bad file name error when creating a report.
BASELINE: Stopped ACTIVITY DISTRIBUTION HISTOGRAM from displaying zero counts at the end of the project.
BASELINE: Prevented deleted but not removed records in the database from appearing in any report.
Version 3.25 (September 2013)
ADDED ACTIVITY STEPS LISTING
ALL: Limit appended Task Tag fields to 255 (P6 limit.)
BASELINE: Fixed Task Tags and Active Reports in reports that use "*" to indicate a blank.
UPDATE: Added check for no Data Date established in schedule.
BASELINE: Added existing Activity Steps Overview report to the manual.
BASELINE: Added Activity Steps Listing.
Version 3.24 (July 2013)
OVERVIEW: IMPROVED TASK TAG ERROR CHECKING.
BASELINE: Fixed over-reporting on Dangling Activities in DCMA Checks.
ALL: Improved spreadsheet creation error checking.
BASELINE: Added /LOGTAGS command line parameter to test Task Tags.
BASELINE: Fixed overreporting of ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report when max report lenght is set low.
Version 3.23 (June 2013)
OVERVIEW: IMPROVED REPORT TO SPREADSHEET CONVERSION PROCESS.
UPDATE: Improved formatting on MODIFIED CONSTRAINTS Report
ALL: Prevented Error 5 on Smart Tags feature when table is improperly formatted.
UPDATE: Fixed Error on Report 140 during DCMA BEI analysis.
ALL: Re-activated Print Button on Print Settings screen.
UPDATE: Added Longest Path Activity indicator to Deleted Relationships Reports.
ALL: Adjusted Spreadsheet-maker to work with columns that overrun their space (like MULTIPLE RELATIONSHIPS Report.)
Version 3.22 (May 2013)
OVERVIEW: IMPROVED LAG DURATION CALCULATION PROCESS.
ALL: Fixed Free RAM Memory reading on 64-bit computers.
BASELINE: Added relationship calendar rule to converting lag durations.
ALL: Improved performance and accurcy on large servers with poor deleted records collection.
BASELINE: Improved SQL date handling on Oracle systems.
UPDATE: Repared bad float reported in PLANNED ACTIVITIES Reports
Version 3.21 (April 2013)
OVERVIEW: INCORPORATED NEW P6v8.3 DISCUSSION TAB REVIEW.
BASELINE: Added COMPLETE ACTIVITY DISCUSSIONS Report.
UPDATE: Added ADDED ACTIVITY DISCUSSIONS Report.
Version 3.20 (March 2013)
OVERVIEW: REPAIRED TASK TAGS FUNCTION.
ALL: Fixed Task Tags Setup feature.
Version 3.19 (February 2013)
OVERVIEW: UPDATED ALL SOFTWARE TO WORK WITH WINDOWS 8 COMPUTERS.
ALL: Windows 8 system file upgrade for compatibility.
UPDATE: Improved selectivity of ADDED RELATIONSHIPS (ACTIVITIES EXISTED) Report.
Version 3.18 (December 2012)
OVERVIEW: FIXED BASLINE CHECK REPORT.
BASELINE: Fixed ACTIVITIES WITH DURATIONS GREATER THEN X Report.
ALL: Fixed program not returning after Diagnostics Window is closed.
ALL: Changed White text on Cyan background to black words for better visability.
UPDATE: Fixed blank table name in View / Spreadsheet function.
Version 3.17 (October 2012)
OVERVIEW: IMPROVED CALENDAR HOLIDAYS LISTING.
BASELINE: Improved calendar holidays listing format.
ALL: Overcome User not allowed to write to their own Local Applications Data folder.
UPDATE: Added Target Schedule Total Float to ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS Report.
BASELINE: Corrected Near-Critical Activity percentage count.
BASELINE: Prevented error message when no secure resource codes exist.
Version 3.16 (September 2012)
OVERVIEW: IMPROVED COST REPORT SECTION.
UPDATE: Modified the ACTIVITY RESOURCE UNITS/TIME PERIOD CHANGE Report to signal when very small values exist.
UPDATE: Prevented over-reporting of resource discrepancies in DELETED/ADDED TASK RESOURCE BUDGETS Reports.
UPDATE: Improved the format for resource IDs.
UPDATE: Separated out the INCREASING REMAINING RESOURCES Report to one for COSTS and one for QUANTITIES.
ALL: Corrected use of separator character used in complex names.
UPDATE: Automatically adjust for incorrectly formatted lower-case Activity ID codes.
BASELINE: Added Right-Click Main Screen Capture.
ALL: Added Screen Capture Log feature.
Version 3.15 (August 2012)
OVERVIEW: ADDED MILESTONE VARIANCE REPORT.
BASELINE: Added function to clean-up bad, Inter-Baseline relationships.
UPDATE: Added the MILESTONE VARIANCE Report.
BASELINE: Added Escape for SUCCESSORS TO SUBSTANTIAL COMPLETION Report.
Version 3.14 (August 2012)
OVERVIEW: MODIFIED BASELINE CHECKER TO BETTER REPORT ON INTER-PROJECT RELATIONSHIPS.
UPDATE: Added float to the ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS Report.
UPDATE: Fixed offest page header error in printed reports if Diagnostics are appended to report.
UPDATE: Fixed over-reporting in the NEW ACTUAL DATES WITH INCORRECT TIMES Report.
UPDATE: Blanked-out Target float if activity was added in NEW PERCENT COMPLETE THIS PERIOD Report.
BASELINE: Prevented ODD RELATIONSHIP Report from listing relationships between schedules not present.
BASELINE: Corrected the MERGE BIAS RISK HISTOGRAM Report.
BASELINE: Fixed error in lag values in ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS Report.
BASELINE: Redesigned INTER-PROJECT RELATIONSHIPS Report to report on Baseline Schedule connections.
ALL: Active Reports modification to accomodate P6 using languages other than English.
Version 3.13 (July 2012)
OVERVIEW: ADDED ABILITY TO AUTOMATICALLY APPEND THE DIAGNOSTICS REPORT TO THE ANALYSIS.
BASELINE: Allow optional append Diagnostics Report to Baseline Checker Report.
UPDATE: Allow optional append Diagnostics Report to Baseline Checker Report.
UPDATE: Correct Data Date if date is less than Schedule Planned Start Date
UPDATE: Updated to comply with PASEG Version 2 CEI definitions.
LOGGER: Allowed user to change font size in Log Memos feature.
LOGGER: Revised completion process in clear logged memos function.
Version 3.12 (July 2012)
OVERVIEW: IMPROVED 3 REPORTS IN UPDATE CHECKER.
UPDATE: Included added activities in the NEW ACTUAL DATES Reports.
UPDATE: Included added activities in the NEW PERCENT COMPLETES THIS PERIOD Reports.
UPDATE: Bullet-proofed Building Calendars when thousands of hollidays are added.
Version 3.11 (June 2012)
OVERVIEW: ADDED BASELINE CHECKER RESOURCE CODE REPORTS.
ALL: Improvements in Login Screen usability and error reporting.
UPDATE: Added interactive Table Of Contents to the report.
UPDATE: Fixed blank screen condition after login due to a system file issue.
BASELINE: Added RESOURCE CODES Report.
BASELINE: Added SECURE RESOURCE CODES Report.
BASELINE: Added Secure User-Defined Fields check.
MENU: Added ability to reset the Oracle XE database if locked.
UPDATE: Fixed Deleted & Added activity over-reporting caused by Exel import.
Version 3.10 (June 2012)
OVERVIEW: ADDED NAVFAC STANDARDS CHECK OPTION.
BASELINE: Added NAVFAC Standards Check.
BASELINE: Added PROJECT CODES IN USE Report.
BASELINE: Added SECURE PROJECT CODES Report.
BASELINE: Made NAVFAC Standards Check interactive if failure shown.
BASELINE: Added interactive Table Of Contents to the report.
Version 3.09 (May 2012)
OVERVIEW: ADDED SECURE ACTIVITY CODES REPORT.
UPDATE: Fixed over-reporting in ACTIVE ACTIVITIES WITH ZERO PERCENT COMPLETE Report.
BASELINE: Added the SECURE ACTIVITY CODES IN USE Report.
UPDATE: Fixed Unable to perform Critical Review by Codes error.
UPDATE: Prevented Invalid procedure call or argument error in Report 77 error.
Version 3.08 (April 2012)
OVERVIEW: ADDED SHORT FORMAT FEATURE TO SCHEDULE LOGGER MEMOS.
LOGGER: Added Log Memos short format option.
LOGGER: Improved Longest Path Listing presentation.
UPDATE: Improved resource reports.
LONGPATH: Added ability to skip recalculating the CPM and use existing dates.
Version 3.07 (March 2012)
OVERVIEW: ADDED ESCAPE FEATURE FOR EARLY TERMINATION OF LONG REPORTS.
UPDATE: Fixed Error 5 in ADDED NOTES Report.
UPDATE: Updated the LONGEST PATH LISTING Report.
DASHBOARD: Fixed reporting on Inter-Project Relationships Report.
BASELINE: Various process speed enhancements.
BASELINE: Added [Esc] Escape feature during long reports.
UPDATE: Added [Esc] Escape feature during long reports.
CALENDAR: Allowed for multiple lines to be selected.
LONGPATH: Fixed occasional error in reading the Base Calendar.
UPDATE: Added the Calender Comparison Report.
LOGGER: Fixed Log Reports failure to find reports to log.
Version 3.06 (February 2012)
OVERVIEW: ADDED MERGE BIAS REPORT AND UDF SECTION (11 REPORTS)
UPDATE: Added option to not report on Longest Path Value UDF changes.
BASELINE: Added NEAR-CRITICAL MERGE BIAS ACTIVITIES Report.
BASELINE: Added MERGE BIAS RISK Histogram.
BASELINE: Added UDF Summary Report.
BASELINE: Added Activities UDF report.
BASELINE: Added Activity Resource Assignments UDF report.
BASELINE: Added Activity Steps UDF report.
BASELINE: Added Issues UDF report.
BASELINE: Added Project Expenses UDF report.
BASELINE: Added Projects UDF report.
BASELINE: Added Resources UDF report.
BASELINE: Added Risks UDF report.
BASELINE: Added WBS UDF report.
BASELINE: Added Work Products & Documents UDF report.
Version 3.05 (January 2012)
OVERVIEW: IMPROVED ORACLE CONNECTIVITY ERROR REPORTING
ALL: Improved logon error explanations for Oracle Databases.
ALL: Standardized internal Check Baselines coding.
MENU: Prevented one-time Error 5 when launching programs on 64-Bit Windows 7 computers.
Version 3.04 (November 2011)
OVERVIEW: FINAL ORACLE PROJECT DISPLAY FIX
BASELINE: Fixed overflow formatting error in ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report.
BASELINE: Fixed minor formatting error in BOGUS RELATIONSHIP RECORDS Report.
ALL: Fixed incorrect project name being displayed 1% of the time for Oracle databases.
ALL: Prevented Cancel Error when adjusting jump parameter.
ALL: Changed the default Jump Interval to 400.
Version 3.03 (October 2011)
OVERVIEW: IMPROVED ORACLE INTERFACE
ALL: Added option of which short project name field to use.
MENU: Added Screen Font control.
ALL: Fixed saving the current screen font.
MENU: Added Oracle password help.
Version 3.02 (October 2011)
OVERVIEW: LOGIC LEAGUE WORKS WITH P6 R8.1
UPDATE: Fixed internal problem with relationships and 20 character Activity IDs.
UPDATE: Fixed ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report over-reporting with long Activity IDs,
UPDATE: Improved formatting of CRITICAL ACTIVITY COUNT BY ACTIVITY CODE Report.
LOGIC: Updated code to comply with P6 R8.1
Version 3.01 (September 2011)
OVERVIEW: IMPROVED SCHEDULE LOGGER LOG-TO-MEMOS FEATURE
BASELINE: Added Scheduling Notice to analysis.
UPDATE: Added Scheduling Notice to analysis.
LOGGER: Added Relationships to Logger Memos.
Logger: Cleaned-up some of the Logger Memo messages.
ALL: New development platform installed.
UPDATE: Fixed Error #3265 in Added Project Issues Report.
BASELINE: Improved formatting in the INDEX TO ACTIVITY NOTES BY TOPIC Report.
UPDATE: Fixed over-reporting in ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
UPDATE: Corrected Error 13 in DCMA Check when Target is not the baseline schedule.
Version 3.00 (August 2011)
OVERVIEW: ADDED MENU PROGRAM AND REPORT BACKUP.
MENU: Added Menu Program with Backup and new video.
RELATED: Removed Related Schedules module.
LOGGER: Comply with administrative write permissions.
CALENDAR: Correctly read Version 8 Database Version.
BASELINE: Fixed Report Help
CALENDAR: Added option for suppression of raw holiday information.
CALENDAR: Added better error trapping when Oracle backup file does not contain the desired calendar.
Version 2.88 (August 2011)
OVERVIEW: ADDED PASEG SCHEDULE EXECUTION METRIC CHECKS.
UPDATE: Added Planning & Scheduling Excellence Guide (PASEG) Schedule Execution Metrics,
UPDATE: 1. Critical Path Length Index
UPDATE: 2. Schedule Performance Index
UPDATE: 3. Baseline Execution Index
UPDATE: 4. Current Execution Index
ALL: Added Version and Serial Number to Login Screen.
UPDATE: Fixed error when you cancel twice from Oracle export file definition.
Version 2.87 (August 2011)
OVERVIEW: ADDED PLANNED DATES TO UPDATE CHECKER.
BASELINE: Added check for default duration not equal to calendar conversion factor in ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report.
UPDATE: Added Planned Dates to the database.
UPDATE: Added PLANNED DATES NOT EQUAL TO EARLY DATES Report.
DASHBOARD: Added PLANNED DATES NOT EQUAL TO EARLY DATES Report.
Version 2.86 (July 2011)
OVERVIEW: UPDATED DATE CALCULATOR.
DATECALC: Fixed weekday calculation.
DATECALC: Bullet-proofed date entry portion.
DATECALC: Upgraded Help facilities.
DATECALC: Added ability to select which days were the weekend.
DATECALC: Added day name to Ticker Tape.
DATECALC: Added ability to read P6 XER and XML File Holidays.
Version 2.85 (July 2011)
OVERVIEW: ADDED FUNCTION TO LOG REPORTS TO ACTIVITY MEMOS.
LOGGER: Added Log Memos function.
ALL: Bullet-proofed SAe setting for whether we should ask for XER file.
Version 2.84 (June 2011)
OVERVIEW: NEW LOGIC REPORT FOR BASELINE CHECKER.
BASELINE: Corrected Diagnostic listing for activities without a start relationship (report OK).
DASHBOARD: Compiler issue in the middle of June 2011
BASELINE: Added ACTIVITIES ON REVERSE LOGICAL PATH Report.
DASHBOARD: Added ACTIVITIES ON REVERSE LOGICAL PATH Report.
Version 2.83 (May 2011)
OVERVIEW: P6 VERSION 8 SUPPORTED.
ALL: Display all schedules in half of the original time.
ALL: Added P6 Release 8 (Oracle G11) support.
ALL: Fixed SQL errors caused by not knowing V8 version number due to database reformatting.
BASELINE: Added Issue Notes for Oracle installations.
BASELINE: Fixed null reporting on User Fields and Rate Types in the Administrative Checks.
BASELINE: Fixed DELECTED/ADDED/MODIFIED USER-DEFINED ACTIVITY RESOURCE DATA Reports.
ALL: Fixed inability to save some program settings.
Version 2.82 (May 2011)
OVERVIEW: ADDED TWO NEW REPORTS.
UPDATE: Added the LONGEST PATH LISTING Report.
DASHBOARD: Added the LONGEST PATH LISTING Report.
LONGPATH: Fixed Oracle Database reporting wrong type of CPM logic rule.
BASELINE: Added the ACTIVITY/RESOURCE CALENDAR MISMATCHES Report.
DASHBOARD: Added the ACTIVITY/RESOURCE CALENDAR MISMATCHES Report.
BASELINE: Fixed the opt-out function setting for using Oracle XER files.
Version 2.81 (April 2011)
OVERVIEW: ADDED MULTI-SCHEDULE LONGEST PATH VALUE ANALYSIS.
STEPS: Improved functionality.
BASELINE: Added a warning about using assigned Base Calendars.
BASELINE: System communications quality check.
BASELINE: Require both predecessor and successor to be in the selected projects for NON-OVERLAPPING LAGS Report.
BASELINE: Perform WBS checks if no activity codes exist to check.
BASELINE: Added the LONG ACTIVITY DESCRIPTIONS Report.
DASHBOARD: Added the LONG ACTIVITY DESCRIPTIONS Report.
BASELINE: Added a check to see if the project Must Finish By date is set to midnight (the default) instead of at the end of the day.
LONGPATH: Converted to allow multi-schedule processing.
Version 2.80 (March 2011)
OVERVIEW: ADDED PROJECT BANDING TO MULTI-PROJECT REPORTS.
BASELINE Added Project Banding to all reports for multi-project analysis.
UPDATE Added Project Banding to all reports for multi-project analysis.
BASELINE: Added check to see if Data Date is later than today's date.
UPDATE: Added check to see if Data Date is later than today's date.
ALL: Update Splash Screen.
BASELINE: Changed report horizontal border to a continuous line.
UPDATE: Changed report horizontal border to a continuous line.
LOGGER: Able to recognize a continuous line as a report horizontal border.
DASHBOARD: Able to recognize a continuous line as a report horizontal border.
Version 2.79 (February 2011)
OVERVIEW: Greatly enhanced the BOGUS RELATIONSHIP RECORDS Report.
BASELINE: Improved accuracy of USER-DEFINED ACTIVITY STEP FIELDS IN USE Report.
BASELINE: Improved BOGUS RELATIONSHIP RECORDS Report.
Version 2.78 (January 2011)
OVERVIEW: MINOR FORMATTING IMPROVEMENTS.
BASELINE: Improved COMPLETE PROJECT NOTES Report formatting when maximum lines is reached.
BASELINE: Fixed blank inter-project relationship activity IDs caused by referencing outside schedules.
BASELINE: Combined Successor & Predecess Inter-Project Relationships into one report.
UPDATE: Made 'opt-out' of Oracle XER selection process more smooth.
Version 2.77 (January 2011)
OVERVIEW: UPDATED DCMA 14-POINT ASSESSMENT CHECKS.
BASELINE: Updated DCMA 14-Point check for the 21NOV09 protocols.
UPDATE: Updated DCMA 14-Point check for the 21NOV09 protocols.
ALL: Added Trail Version.
Version 2.76 (December 2010)
OVERVIEW: IMPROVED DATE CALC ACCURACY.
DATECALC: Fixed working days occasionally off if less than 1 week was specified.
UPDATE: Made ACTIVITIES WITH DIMINISHING PROGRESS THIS PERIOD Report more sensitive to reporting.
BASELINE: Fixed Original Duration column in Topic Checks.
Version 2.75 (November 2010)
OVERVIEW: ADDED XML OPTION FOR ORACLE HOLIDAY REPORTING.
LOGIC: Updated Open Schedule Screen (incorrect project names were sometimes displayed.)
BASELINE: Added XML option for Oracle database calendar holidays.
UPDATE: Added XML option for Oracle database calendar holidays.
CALENDAR: Added XML option for Oracle database calendar holidays.
LONGPATH: Added XML option for Oracle database calendar holidays.
STEPS: Added XML option.
BASELINE: Improved HTML translation in Notes.
UPDATE: Improved HTML translation in Notes.
Version 2.74 (November 2010)
OVERVIEW: ADDED 3 NEW BASELINE CHECKER REPORTS.
UPDATE: Added Target Finish Date to ACTIVITIES THAT COULD HAVE FINISHED BUT DID NOT Report.
UPDATE: Updated Report Help index.
BASELINE: Added ACTIVITIES WITHOUT RESOURCES ASSIGNED Report.
BASELINE: Added SUMMARY ACTIVITIES WITH ASSIGNED RESOURCES Report.
BASELINE: Added MILSTONES WITH ASSIGNED RESOURCES Report.
DASHBOARD: Added ACTIVITIES WITHOUT RESOURCES ASSIGNED Report.
DASHBOARD: Added SUMMARY ACTIVITIES WITH ASSIGNED RESOURCES Report.
DASHBOARD: Added MILSTONES WITH ASSIGNED RESOURCES Report.
ALL: Improve handling of MS Oracle data connection.
Version 2.73 (October 2010)
OVERVIEW: FIXED BLANK OPENING SCREEN.
UPDATE: Fixed blank opening screen.
Version 2.72 (September 2010)
OVERVIEW: FIXED CALENDAR PROBLEMS WITH ORACLE DATABASE.
BASELINE: Fixed Calendar problems using Oracle Database.
BASELINE: Fixed CPM settings problems using Oracle Database.
BASELINE: Fixed Notebook log problems using Oracle Database.
UPDATE: Fixed RELATIONSHIP ADDED WHEN ACTIVITY ADDED Report over-reporting.
LONGPATH: Fixed CPM computational error involving Start-to-start relationships.
LONGPATH: Fixed operational problem using Oracle Database.
UPDATE: Improved External Constraint Date monitoring.
UPDATE: Fixed Calendar problems using Oracle Database.
UPDATE: Fixed CPM settings problems using Oracle Database.
UPDATE: Fixed Notebook log problems using Oracle Database.
UPDATE: Improved Notebook presentation.
CALENDAR: Fixed Calendar problems using Oracle Database.
Version 2.71 (September 2010)
OVERVIEW: ADDED RESPONSIBILITY REPORT TO BASELINE CHECKER.
UPDATE Fine-tuned ACTIVE ACTIVITIES WITH ZERO PERCENT COMPLETE Report for near-zero % completes.
BASELINE: Further bullet-proofed NEGATIVE LAGS USED Report.
BASELINE: Added ability to select an activity code used for Responsibility.
BASELINE: Added RELATIONSHIPS WHERE RESPONSIBILITY CHANGES Report.
UPDATE: Added relationships with NULL lag values to the internal check database.
UPDATE: Modified the MODIFIED LAGS Report to report on NULL lag values.
Version 2.70 (August 2010)
OVERVIEW: ADDED SORT FEATURE TO LONGEST PATH SUBSTANTIAL COMPLETION ACTIVITY.
ALL: Updated login to better remember non-local server names.
LONGPATH: Added sort by column to Substantial Completion selection screen.
Version 2.69 (August 2010)
OVERVIEW: ADDED UPDATE CHECKER CRITICAL ACTIVITIES BY AREA CODE REPORT
CALENDAR: Reversed the Form: and To: in Compare Saved.
UPDATE: Minor Percent Complete reporting modifications.
UPDATE: Prevent processing error while reporting on Activity Notes in an Oracle database.
UPDATE: Added the CRITICAL ACTIVITY COUNT BY ACTIVITY CODE Report
UPDATE: Updated Report Help to point to correct passages in the Help file.
Version 2.68 (14July 2010)
OVERVIEW: REPAIRED UPDATE CHECKER BLANK SCREEN
UPDATE: Fixed internal error causing only a blank screen to show.
Version 2.67 (09July 2010)
OVERVIEW: ADDED EXTERNAL CONSTRAINTS CHECKS
LOGGER: Minor enhancements in program user interface.
UPDATE: Added ability to ignore minor calendar name changes (just different number at the end.)
ALL: Added Save as MS Word or Text file to the View Window.
BASELINE: Improved Notebook HTML translation.
BASELINE: Moved Agency Checks to the end of the analysis.
UPDATE: Moved Agency Checks to the end of the analysis.
UPDATE: Improved performance of Project WBS User-Defined field checks.
Version 2.66 (June 2010)
OVERVIEW: ADDED EXTERNAL CONSTRAINTS CHECKS
BASELINE: Improved formatting of BASELINE SCHEDULE CONSTRAINTS Report.
BASELINE: Added EXTERNAL CONSTRAINTS Report.
DASHBOARD: Added EXTERNAL CONSTRAINTS Report.
UPDATE: Added External Early Start Date to the database.
UPDATE: Added External Late Finish Date to the database.
UPDATE: Added External Date Constraints to Deleted Constraints Reports.
UPDATE: Added External Date Constraints to Added Constraints Reports.
UPDATE: Removed milestones and WBS activities from ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
BASELINE: Removed milestones from ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Removed milestones from ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
LOGON: Updated Help video.
BASELINE: Updated Help video.
UPDATE: Updated Help video.
Version 2.65 (June 2010)
OVERVIEW: UPGRADE TASK TAGS AND ACTIVE REPORTS. ADDED SAVE AS SPREADSHEET TO VIEW REPORTS
UPDATE: Removed Float column from AS-BUILT ACTIVITIES THAT HAVE BEEN DELETED SINCE LAST UPDATE Report.
Update: Fixed Error 5 issue in Notebooks section when report width was shorter than standard size.
BASELINE: Added Save to Spreadsheet in the Report View Window.
UPDATE: Added Save to Spreadsheet in the Report View Window.
DASHBOARD: Added Save to Spreadsheet in the Report View Window.
BASELINE: Improved Task Tag responsiveness.
UPDATE: Improved Task Tag responsiveness.
DASHBOARD: Improved Task Tag responsiveness.
BASELINE: Added ability to append Task Tags as opposed to just overwriting them.
UPDATE: Added ability to append Task Tags as opposed to just overwriting them.
DASHBOARD: Added ability to append Task Tags as opposed to just overwriting them.
BASELINE: Extensive timing improvements made for Active Reports.
UPDATE: Extensive timing improvements made for Active Reports.
DASHBOARD: Extensive timing improvements made for Active Reports.
Version 2.64 (May 2010)
OVERVIEW: FIXED ERROR CREATED IN VERSION 2.63 (ALL CUSTOMERS UPDATED.)
BASELINE: Fixed Run time error 13: Type Mismatch in Run Options screen.
UPDATE: Fixed Run time error 13: Type Mismatch in Run Options screen.
UPDATE: Improved handling of Activity Memo report for Oracle systems.
UPDATE: Improved handling of Activity Issues report for Oracle systems.
UPDATE: Fixed Unable to select Update Schedule after selecting an empty WBS.
Version 2.63 (May 2010)
OVERVIEW: OLDER P6 VERSIONS HOURS/DAY FACTOR ACCOMMODATED.
BASELINE: Bullet-proofed report start-up further.
UPDATE: Bullet-proofed report start-up further.
ALL: Added ability to turn off sound queues in Video Setup.
BASELINE: Added back in Hours/Day factor confirmation from Pre-Version 7 P6 systems.
UPDATE: Added back in Hours/Day factor confirmation from Pre-Version 7 P6 systems.
ALL: Task Tags now work if the Activity ID is numeric.
LONGPATH: Added ability to change Longest Path Value column label in P6.
LONGPATH: Update database updating routines to match P6v7 requirements.
Version 2.62 (April 2010)
OVERVIEW: MORE ORACLE DATABSE ACCOMODATION IMPROVEMETNS.
UPDATE: Added Oracle BLOB check in CPM Rules Check section.
BASELINE: Fixed Activity Integrity Checks #32, 33, & 39 for Oracle SQL date issue.
BASELINE: Fixed Oracle SQL MoveFirst problem (causing blank reports.)
UPDATE: Fixed Oracle SQL MoveFirst problem (causing blank reports.)
DASHBOARD: Added Save as Spreadsheet function.
BASELINE: Improved formatting of float values with decimals.
Version 2.61 (March 2010)
OVERVIEW: NEW BASELINE CHECKER REPORT AND UPGRADED DASHBOARD.
DASHBOARD: Major update to match wide reports.
DASHBOARD: Major error-proofing if report is missing sections.
BASELINE: Increased maximum Activity Title Length from 60 to 120.
UPDATE: Increased maximum Activity Title Length from 60 to 120.
BASELINE: Added fractional lag check to the ODD LAGS OR LEADS Report.
BASELINE: Added NEGATIVE LAGS USED Report.
DASHBOARD: Added NEGATIVE LAGS USED Report.
Version 2.60 (March 2010)
OVERVIEW: NEW UPDATE CHECKER REPORT.
UPDATE: Added ACTIVITIES THAT COULD HAVE FINISHED Report
DASHBOARD: Added ACTIVITIES THAT COULD HAVE FINISHED Report
DASHBOARD: Minor report enhancements.
ALL: Update Splash Screen
ALL: Updated the Instashield software loaded settings.
Version 2.59 (March 2010)
OVERVIEW: UPGRADED DASHBOARD HANDLING.
BASELINE: Keep Baseline Checker running while Dashboard is working.
UPDATE: Keep Update Checker running while Dashboard is working.
Version 2.58 (February 2010)
OVERVIEW: UPGRADED DATE CALCULATOR.
ALL: Added Smart Copy Help Video.
UPDATE: Improved accuracy with ACTIVITIES WITH MODIFIED DURATION TYPES Report.
DATECALC: Multiple improvements to functionality.
Version 2.57 (February 2010)
OVERVIEW: CORRECTED FOR BLANK SCREEN AFTER LOGIN.
ALL: Corrected software production error introduced in Version 2.54.
Version 2.56 (November 2009)
OVERVIEW: IMPROVED REPORTS.
BASELINE: Added FS successor relationship to DANGLING ACTIVITIES WITH A SINGLE SS OR FF PREDECESSOR Report
BASELINE: Converted FRACTION OF A DAY DURATIONS Report to use P6v7 calendars.
Version 2.55 (January 2010)
OVERVIEW: IMPROVED REPORTS.
DASHBOARD: Changed File / Save process from an "Open" button to a "Save" button.
BASELINE: Converted Activity Duration Histogram to use P6v7 calendars.
BASELINE: Converted One-day Activity durations report to use P6v7 calendars
Version 2.54 (December 2009)
OVERVIEW: IMPROVED GENERAL LOGIN HANDLING.
ALL: Internal error checking change for higher reliability.
All: Improved explanation for database connect failure due to incorrect settings.
ALL: Returned log-in error checking back to early set-up.
Version 2.52 (November 2009)
OVERVIEW: ALLOWED FOR RESET OF WINDOWS POSITIONING TO DEFALT LOCATIONS.
ALL: Added a Program Windows reset function.
Version 2.52 (November 2009)
OVERVIEW: IMPROVED ORACLE LOGIN.
ALL: Improved logon for Oracle installations.
BASELINE: Rounded all Total Floats as appropriate to nearest whole value for cleaner display.
BASELINE: Improved Constraints Section formatting & added activity status to complete constraint listing.
Version 2.51 (October2009)
OVERVIEW: RESTORED ACTIVE REPORTS FEATURE FOR P6v7.
ALL: Fixed Active Reports failure due to a P6, Version 7 change.
Version 2.50 (October 2009)
OVERVIEW: COMPLETED REVISION OF DURATIONS BASED UPON P6v7 CALENDAR FACTORS.
BASELINE: Added maximum list length to ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
BASELINE: Completed conversion of durations based upon P6v7 activity calendar conversion factors.
UPDATE: Improved Critical Summary report.
UPDATE: Prevented Error 6: Overflow on Report 146.
UPDATE: Completed conversion of durations based upon P6v7 activity calendar conversion factors.
Version 2.49 (September 2009)
OVERVIEW: UPGRADED TO MEET WINDOWS 7 REQUIREMENTS.
ALL: Updated internal screen controls for Windows 7 compatibility.
UPDATE: Sped-up building of resource database.
LONG PATH: Internal memory adjustment to support larger schedules.
Version 2.48 (September 2009)
OVERVIEW: UPGRADED TO MEET P6 v7 CHANGES TO THE DATABASE.
BASELINE: Updated User-Defined Fields checks to work with P6 v7 (new database change.)
UPDATE: Updated User-Defined Fields checks to work with P6 v7 (new database change.)
BASELINE: Updated UNUSUAL NUMBER OF MOBILIZATION ACTIVITIES FOUND Report.
BASELINE: Improved formatting of calendar holidays when multiple periods in a day were present.
CALENDAR: Added P6 v7 calendar hour conversion factors.
UPDATE: Modified Daily/Hourly Schedule Review programmability
BASELINE: Added Hour Conversion Factors to Calendar Summaries.
UPDATE: Sped-up and corrected bad SQL reads from Activity Cost Database.
Version 2.47 (September 2009)
OVERVIEW: ALLOWED FOR WIDER REPORTS AND LONGER ACTIVITY TITLES TO BE PRINTED.
BASELINE: Added ability to change the width of all reports, changing the amount of activity title displayed.
BASELINE: Quality checked the formatting of all reports.
BASELINE: Restored calendar checks.
BASELINE: Added Invalid Forecast Dates Report to DCMA 14-Point Checks Section.
UPDATE: Added ability to change the width of all reports, changing the amount of activity title displayed.
UPDATE: Added Invalid Forecast Dates Report to DCMA 14-Point Checks Section.
UPDATE: Moved numeric IDs to the right in reports.
DASHBORD: Added DCMA 14-point Checks Section.
Version 2.46 (September 2009)
OVERVIEW: ADDED DCMA 14-POINT CHECK TO UPDATE CHECKER.
ALL: Modified Project Open Screen to sort Projects by EPS like P6 does.
UPDATE: Added DCMA 14-Point Assessment Checks section.
UPDATE: Modified internal procedures for calculating Maximum ID Length.
BASELINE: Fixed "User Requested Halt" error in calendar section when schedule had a "?" in the name.
Version 2.45 (August 2009)
OVERVIEW: ADDED SCHEDULE MATCH WHEN MULTIPLE SCHEDULES ARE SELECTED TO UPDATE CHECKER.
UPDATE: Spead-up ORPHANED ACTIVITIES Report.
UPDATE: Spead-up RELATIONSHIP ADDED WHEN ACTIVITY ADDED Report.
UPDATE: Improved accuracy in ADDED INVALID RELATIONSHIPS (DUE TO STATUS) Report.
UPDATE: Added schedule match capability when comparing groups of schedules at a time and improved accuracy.
UPDATE: Fixed missing target relationships issue.
BASELINE: Fixed listing of Primary Resource name in PRIMARY RESOURCE SUMMARY Report.
BASELINE: Fixed relationship type in INTER-PROJECT PREDECESSORS and SUCCESSORS Reports.
DASHBOARD: Fixed Added As-Built Activity Reporting.
Version 2.44 (August 2009)
OVERVIEW: UPGRADED UPDATE CHECKER'S ABILITY TO REVIEW MULTIPLE SCHEDULES.
UPDATE: Sped-up ORPHANED ACTIVITIES Report.
UPDATE: Sped-up RELATIONSHIP ADDED WHEN ACTIVITY ADDED Report.
UPDATE: Improved accuracy in ADDED INVALID RELATIONSHIPS (DUE TO STATUS) Report.
UPDATE: Added schedule match capability when comparing groups of schedules at a time and improved accuracy.
UPDATE: Fixed missing target relationships issue.
BASELINE: Fixed listing of Primary Resource name in PRIMARY RESOURCE SUMMARY Report.
BASELINE: Fixed relationship type in INTER-PROJECT PREDECESSORS and SUCCESSORS Reports.
DASHBOARD: Fixed Added As-Built Activity Reporting.
Version 2.44 (August 2009)
OVERVIEW: ADDED BASELINE CHECKER DCMA 14-POINT METRICS CHECK.
BASELINE: Added DCMA 14-Point Check.
BASELINE: Fixed the saving "Time Units are Organized by" setting.
BASELINE: Internal programming architecture changes for robustness.
UPDATE: Internal programming architecture changes for robustness.
Version 2.43 (August 2009)
OVERVIEW: UPDATE SOFTWARE INSTALLATION FOR WINDOWS 7.
ALL: Upgraded software loading system to be compatible with Windows 7.
Version 2.42 (July 2009)
OVERVIEW: FIXED A BASELINE CHECKER REPORT.
LONGEST PATH: We no longer try to reclaim 'unused fields' because they may be used but the title was not changed.
BASELINE: Fixed the ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS (NOT SS & FF PAIRS) Report.
Version 2.41 (June 2009)
OVERVIEW: ENHANCED SCHEDULE SELECTION PAGE.
ALL: Added combination box for login Server Name for multiple servers.
ALL: Update schedule selection screen for style and Windows 7.
LOGIC LEAGUE: Fixed Filter to remember past additions.
LOGIC LEAGUE: Fixed User Codes to remember past additions.
Version 2.40 (June 2009)
OVERVIEW: IMPROVED ACTIVITY MEMO COMPARISONS.
UPDATE: Allowed for super-large activity memos.
Version 2.39 (May 2009)
OVERVIEW: CREATED SEPERATE CALENDAR REVIWEING MODULE.
CALENDAR: Moved calendar viewing function from Baseline & Update Checker into separate utility.
ALL: Fixed "Show Baselines" function.
Version 2.38 (May 2009)
OVERVIEW: IMPROVED ACTIVITY DESCRIPTION CHANGE DETECTION.
UPDATE: Improved accuracy of detection of activity description changes.
BASELINE: Calendar Report improvements.
ALL: Opening screen inactive while building list.
Version 2.37 (April 2009)
OVERVIEW: ADDED A NEW UPDATE CHECKER REPORT.
UPDATE: Added NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED Report.
UPDATE: Error proofing for Run Time Error 28, out of stack space in ADDED AS-BUILT ACTIVITIES Report.
Version 2.36 (March 2009)
OVERVIEW: IMPROVED UPDATE CHECKER CONSTRAINTS SECTION.
UPDATE: Fixed skipping of Constraints Section when Activity Code Section was skipped.
UPDATE: Improved deleted constraints accuracy in odd situations.
UPDATE: Improved added constraints accuracy in odd situations.
BASELINE: Improved corrupted secondary constraints check.
Version 2.35 (February 2009)
OVERVIEW: IMPROVED OPEN SCHEDULE PAGE.
ALL: Display all projects in alphabetical order.
LONGPATH: Fixed CPM calculation error with completed activity with large positive lag.
LONGPATH: Fixed 1-hour error on initial activity CPM dates.
Version 2.34 (January 2009)
OVERVIEW: IMPROVED LONGEST PATH CPM ACCURACY.
BASELINE: Adjusted ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report to work with days as well as just hours.
LONGPATH: Caught rounding error in CPM calculations that could make LPV one hour too low.
LONGPATH: Allowed for all lag calendar settings to be used.
LONGPATH: Option to save generated calendars added.
LONGPATH: Option to save CPM calculations added.
LONGPATH: Re-write of calendar generation for speed and accuracy.
LONGPATH: Re-write of CPM forward pass for speed and accuracy.
UPDATE: Prevented reporting on completed activities in NEWLY ORPHANED ACTIVITIES Report.
UPDATE: Improved formatting of percent complete on reports.
Version 2.33 (December 2008)
OVERVIEW: IMPROVED CALENDAR REPORTS.
BASELINE: Improved the accuracy of Calendar Reports.
UPDATE: Improved the accuracy of Calendar Reports.
UPDATE: Fixed formatting of Memo Checks when memo was blank.
Version 2.32 (December 2008)
OVERVIEW: IMPROVED ERROR CHECKING FOR ACTIVITY PERCENT COMPLETE.
BASELINE: Prevented negative %-complete when RD > OD in ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Prevented negative %-complete when RD > OD in ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Corrected occasional formatting errors with NEW PERCENT COMPLETE THIS PERIOD Report.
UPDATE: Prevented negative %-complete in NEW PERCENT COMPLETE THIS PERIOD Report.
Version 2.31 (December 2008)
OVERVIEW: MAJOR INTERNAL MODIFICATION TO UPDATE CHECKER.
UPDATE: Fixed activity SQL ORDER error.
UPDATE: Fixed other causes for activity out of order issues.
UPDATE: Fixed activity steps SQL ORDER error.
UPDATE: Fixed activity codes SQL ORDER error.
UPDATE: Fixed activity constraints SQL ORDER error.
UPDATE: Fixed activity costs SQL ORDER error.
UPDATE: Fixed activity resources SQL ORDER error.
UPDATE: Improved ADDED RELATIONSHIPS Report.
UPDATE: Fixed internal Overflow Error while building Resource database.
UPDATE: Prevent SQL connection error while building resource database.
UPDATE: Sped-up Building Resource Database routine.
ALL: Positive program end when File / Cancel is selected in View.
Version 2.30 (November 2008)
OVERVIEW: IMPROVED TWO BASELINE RELATIONSHIP REPORTS.
BASELINE: Removed redundant rows in ACTIVITIES WITHOUT FINISH RELATIONSHIP Report.
BASELINE: Improved accuracy in SUBMITTALS WIHTOUT FINISH RELATIONSIPS Report.
Version 2.29 (November 2008)
OVERVIEW: MAINLY SCHEDULE OPEN DISPLAY ENHANCEMENTS.
UPDATE: Fixed same activity being reported as both Added & Deleted due to SQL ORDER error.
UPDATE: Fixed non-reporting on Costs when no Cost Accounts are defined but costs exist.
UPDATE: Removed the calendar compare section, because they overwrite each other.
ALL: Fixed cases where project name was incorrect (mainly an Oracle issue.)
ALL: Reorder the schedules in the list before WBS categories to match P6's orientation.
Version 2.28 (November 2008)
OVERVIEW: PREVENT ENDLESS LOOP WHILE SAVING REPORT
BASELINE: Fix endless loop while Checking Mobilization relationships.
UPDATE: Fix endless loop when opening the report.
Version 2.27 (November 2008)
OVERVIEW: IMPROVED ORACLE CONNECTION
ALL: Fixed Oracle Login-in glitch.
BASELINE: Corrected Duration Type Summary results.
ALL: Improved database server connectivity in slow environments.
Version 2.26 (September 2008)
OVERVIEW: ACTIVE REPORTS IMPROVED AND WSB SUMMARY TYPE ADDED
ALL: Improved Active Reports response to P6.
BASELINE: Included WBS Summary activities.
BASELINE: Excluded WBS Summary activities from missing predecessors and missing successors reports.
BASELINE: Excluded activities without successors from ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
UPDATE: Prevented Error 5 in Notebook Reports.
UPDATE: Added WBS activity type to reports.
Version 2.25 (September 2008)
OVERVIEW: MINOR FIXES AND IMPROVED RELIABILITY UPDATES
LONGPATH: Fixed calendar for working days on Saturday issue.
BASELINE: Fixed 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report.
BASELINE: Re-wrote ACTIVITIES WITHOUT PREDECESSORS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITHOUT SUCCESSORS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report to prevent Data Server Time-outs.
Version 2.24 (August 2008)
OVERVIEW: IMPROVED CITRIX INSTALLATION PERFORMANCE
BASELINE: Fixed occasional formatting problem with ALL OTHER LAGS OR LEADS USED Report.
ALL: Added command line parameter to override initialization file location.
Version 2.23 (August 2008)
OVERVIEW: IMPROVED VIEW PERFORMANCE WITH VERY LARGE SCHEDULES
ALL: Prevented View Screen from freezing-up with a very large report.
UPDATE: Fixed Error 9 on Day of the Week Reports.
Version 2.22 (August 2008)
OVERVIEW: ADDED UPDATE CHECKER REPORTS LABELING ACTUAL DATES WITH THEIR DAY OF THE WEEK
Baseline: Fixed Data Date and Project Name display in the header of the report.
UPDATE: Fixed Project Name in report header.
UPDATE: Added the NEW ACTUAL START DATE SORTED BY WORKDAY Report.
UPDATE: Added the NEW ACTUAL FINISH DATE SORTED BY WORKDAY Report.
Version 2.21 (August 2008)
OVERVIEW: MINOR ERROR CORRECTIONS
UPDATE: Fixed Activity Issue "maximum number listed" error.
BASELINE: Fix error in NON-OVERLAPPING LAGS Report.
Version 2.20 (August 2008)
OVERVIEW: CORRECTED OVER-REPORTING OF MILESTONE ACTIVITIES IN UPDATE CHECKER
Update: Corrected MISSING ACTUAL START DATES Report for milestones.
Update: Corrected NEW ACTUAL DATES EARLIER THAN TARGET DATE Report for milestones.
Update: Corrected NEW ACTUAL DATES LATER THAN UPDATE DATE Report for milestones.
Update: Corrected MISSING ACTUAL START DATES Report for milestones.
Update: Corrected NEW ACTUAL DATES EARLIER THAN TARGET DATE Report for milestones.
Update: Corrected NEW ACTUAL DATES LATER THAN UPDATE DATE Report for milestones.
BASELINE: Added a note warning about using Global Calendars.
Version 2.19 (July 2008)
OVERVIEW: ADDED MORE SUPPORT FOR LARGE NOTEBOOK LIBRARIES
UPDATE: Added more status reporting for Notebook checks.
UPDATE: Corrected NEW ACTUAL DATES WITH INCORRECT TIMES Report to properly account for milestone activities.
Version 2.18 (July 2008)
OVERVIEW: MINOR REPORT UPDATES AND BETTER ACTIVE REPORTS FUNCTIONALITY
ALL: Improved Active Reports response to P6 screen conditions.
BASELINE: Fixed the ACTIVITIES WITH TOO MUCH FLOAT Report.
UPDATE: Corrected float in CHANGE IN FLOAT GREATER THAN THE NUMBER OF DAYS IN THE UPDATE PERIOD Report.
Version 2.17 (July 2008)
OVERVIEW: FINAL CORRECTION FOR UPDATE CHECKER DEALING WITH NUMERIC ACTIVITY IDs
ALL: Added multiple database logon capability.
UPDATE: Final Numeric Activity ID adjustment. Version 2.16 is incorrect and should not be used.
UPDATE: Fixed a minor Calendar Report formatting error.
Version 2.16 (July 2008)
OVERVIEW: TEST PATCH FOR UPDATE CHECKER DEALING WITH NUMERIC ACTIVITY IDs
UPDATE: Attempt to correct for over-reporting in schedules with numeric Activity IDs.
Version 2.15 (July 2008)
OVERVIEW: ADDED NEW UPDATE CHECKER REPORT.
UPDATE: Added NEW ACTUAL DATES WITH INCORRECT TIMES Report.
DASHBOARD: Added NEW ACTUAL DATES WITH INCORRECT TIMES Report.
UPDATE: Updated Exclude Reports Section.
Version 2.14 (July 2008)
OVERVIEW: MINOR INTERNAL IMPROVEMENTS.
LOGIC: Changed SQL calls to comply with Oracle requirements.
UPDATE: Fixed Calendar Report.
Version 2.13 (June 2008)
OVERVIEW: ADDED SUMMARY OVERVIEW.
BASELINE: Added Summary overview section to the report.
Version 2.12 (May 2008)
OVERVIEW:ERROR-PROOFED CPM CHECK.
BASELINE: Caught incorrect reporting of CPM settings if CPM in the schedule had never been computed.
UPDATE: Caught incorrect reporting of CPM settings if CPM in the schedule had never been computed.
Version 2.11 (May 2008)
OVERVIEW: SPEED-UP UPDATE CHECKER PROCESSING.
UPDATE: Dramatically sped-up relationship database building and prevented data server thrashing.
Version 2.10 (May 2008)
OVERVIEW: FIXED UNCOMMON ERROR IN UPDATE CHECKER.
UPDATE: Fixed endless loop opening report if project name is odd and report run more than once.
Version 2.09 (April 2008)
OVERVIEW: SELECT SCHEDULES FASTER BY LIMITING SCHEDULES SHOWN.
LONGPATH: Sped-up Pre-Slack preparation section.
ALL: Limit the number of schedules displayed by selecting their OBS.
Version 2.08 (April 2008)
OVERVIEW: ADJUSTED TWO UPDATE CHECKER REPORTS.
UPDATE: Fixed ACTIVITIES WITH MODIFIED DURATION TYPES Report.
UPDATE: Fixed ACTIVITIES WITH MODIFIED PERCENT COMPLETE TYPES Report.
Version 2.07 (March 2008)
OVERVIEW: IMPROVED ERROR CHECKING IN LONGEST PATH.
LONGPATH: Added the program to the run menu (previously loaded but not visible.)
LONGPATH: Fixed condition where Longest Path Sequence Number = 32000 (Completed activities without dates.)
UPDATE: Fixed Error 3001 in Comparing Issue Notes section.
Version 2.06 (March 2008)
OVERVIEW: ALLOWED BASELINE CHECKER TO DEAL WITH POORLY-MADE MEGA-SCHEDULES.
BASELINE: Added limit to stop checking (as opposes to just stop reporting.)
Version 2.05 (February 2008)
OVERVIEW: COMPLETION OF DISPLAYING PROJECTS SPEEDUP.
LOGIC: Greatly speed-up start of Open Project screen.
MASTER: Greatly speed-up start of Open Project screen.
LOGIC: Greatly speed-up re-painting of Open Project screen with baseline schedules.
MASTER: Greatly speed-up re-painting of Open Project screen.
DASHBORD: Allowed user to change screen font and size.
Version 2.04 (February 2008)
OVERVIEW: BEGINNING OF SIGNIFIANTLY FASTER AT DISPLAYING PROJECTS.
BASELINE: Greatly speed-up start of Open Project screen.
LOGGER: Greatly speed-up start of Open Project screen.
LONGPATH: Greatly speed-up start of Open Project screen.
RELATED: Greatly speed-up start of Open Project screen.
UPDATE: Greatly speed-up start of Open Project screen.
BASELINE: Greatly speed-up re-painting of Open Project screen with baseline schedules.
LOGGER: Greatly speed-up re-painting of Open Project screen with baseline schedules.
LONGPATH: Greatly speed-up re-painting of Open Project screen with baseline schedules.
RELATED: Greatly speed-up re-painting of Open Project screen with baseline schedules.
UPDATE: Greatly speed-up re-painting of Open Project screen with baseline schedules.
Version 2.03 (February 2008)
OVERVIEW: DUPLICATED P6 OPEN PROJECT SCREEN.
BASELINE: Improved look of Open Project screen with color-coded hierarchy.
LOGGER: Improved look of Open Project screen with color-coded hierarchy.
LONGPATH: Improved look of Open Project screen with color-coded hierarchy.
RELATED: Improved look of Open Project screen with color-coded hierarchy.
UPDATE: Improved look of Open Project screen with color-coded hierarchy.
Version 2.02 (February 2008)
OVERVIEW: IMPROVED RELATED SCHEDULES PROGRAM.
DASHBOARD: More error-proofing on file open.
RELATED: Added Relationships and Lags to report.
RELATION: Prevented Run Time Error 3265.
BASELINE: Numerous spelling corrections.
UPDATE: Numerous spelling corrections.
Version 2.01 (January 2008)
OVERVIEW: MINOR CHANGES.
ALL: Prevented ORA-00911 error for Oracle installations.
LOGIC: Fixed video presentation.
ALL: More error protection from Internal Error 75 on login.
Version 2.00 (January 2008)
OVERVIEW: MOVED LOGIC LEAGUE TO THE SAe PACKAGE.
LOGIC: Added Logic League to Schedule Analyzer. Also made extensive user enhancements.
UPDATE: Added Average Float calculation.
UPDATE: Added ability to limit the number of lines in the ODD TOTAL FLOAT Report.
Version 1.62 (May 2007)
OVERVIEW: LAST VERSION 1 UPGRADE. FIXED TWO OPERATING ERRORS.
RELATED: Added relationship type and lag to report lines
Relation: Prevented Run Time Error 3265.
UPDATE: Prevented un-ending loop opening report with an unusual file name.
Version 1.61 (February 2007)
OVERVIEW: FIXED OPERATING ERRORS.
ALL: Fixed Oracle error number ORA-00911.
DASHBOARD: More error-proofing on file open.
ALL: Fixed program folder automatically opening on computer startup.
Version 1.60 (December 2007)
OVERVIEW: ADDED ISSUES AND ATTACHED DOCUMENTS SECTION FOR A TOTAL OF 13 NEW REPORTS.
BASELINE: Changed internal Memo collection to meet Oracle database restrictions.
UPDATE: Changed internal Memo collection to meet Oracle database restrictions.
BASELINE: Added EXPANDED REFERENCED DOCUMENT TYPE LAYOUT Report.
BASELINE: Added ATTACHED ACTIVITY DOCUMENTS Report.
BASELINE: Added: PROJECT DOCUMENT FILE Report.
DASHBOARD: Added ATTACHED ACTIVITY DOCUMENTS Report.
DASHBOARD: Added: PROJECT DOCUMENT FILE Report.
BASELINE: Improved COMPLETE PROJECT NOTES Report by removing HTML Tags
UPDATE: Added DELETED PROJECT DOCUMENTS Report.
UPDATE: Added ADDED PROJECT DOCUMENTS Report.
UPDATE: Added CHANGED PROJECT DOCUMENTS Report.
UPDATE: Added CHANGED PROJECT DOCUMENT LOCATION Report.
DASHBOARD: Added DELETED PROJECT DOCUMENTS Report.
DASHBOARD: Added ADDED PROJECT DOCUMENTS Report.
DASHBOARD: Added CHANGED PROJECT DOCUMENTS Report.
DASHBOARD: Added CHANGED PROJECT DOCUMENT LOCATION Report.
BASELINE: Added PROJECT ISSUES Report.
BASELINE: Added ACTIVITY ISSUES Report.
DASHBOARD: Added PROJECT ISSUES Report.
DASHBOARD: Added ACTIVITY ISSUES Report.
UPDATE: Added DELETED PROJECT ISSUES Report.
UPDATE: Added ADDED PROJECT ISSUES Report.
UPDATE: Added MODIFIED PROJECT ISSUE DATA Report.
UPDATE: Added MODIFIED PROJECT ISSUE NOTES Report.
DASHBOARD: Added DELETED PROJECT ISSUES Report.
DASHBOARD: Added ADDED PROJECT ISSUES Report.
DASHBOARD: Added MODIFIED PROJECT ISSUE DATA Report.
DASHBOARD: Added MODIFIED PROJECT ISSUE NOTES Report.
Version 1.59 (November 2007)
ALL: Fixed Line Edit: Cancel Button function while viewing reports.
ALL: Added View/ Copy Activity ID and Copy Full Activity description to menu.
ALL: Added Task Tag Help video.
ALL: Added Copy Activity Help video.
DASHBOARD: Improved INI Lower and Upper setting procedure.
DASHBOARD: Fixed ability to manually update Lower and Upper settings.
DASHBOARD: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
DASHBOARD: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
DASHBOARD: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
DASHBOARD: Added UDF Costs Reports.
DASHBOARD: Added UDF WBS Reports.
DASHBOARD: Added UDF ISSUES Reports.
DASHBOARD: Added UDF RISKS Reports.
DASHBOARD: Added UDF DOCUMENTS Reports.
LOGGER: Skip reports tagged to not contain Activity IDs (internal reliability enhancement.)
ALL: Don't run Active Reports routine if report is not based on Activity ID.
Version 1.58 (November 2007)
BASELINE: Added Saved Calendar creation to baseline check as well as with update check.
BASELINE: Added Calendar Reports function.
RELATED: Fixed No Column 6 error.
Version 1.57 (October 2007)
UPDATE: Added User-Defined Field (UDF) Costs Reports.
UPDATE: Added UDF WBS Reports.
UPDATE: Added UDF ISSUES Reports.
UPDATE: Added UDF RISKS Reports.
UPDATE: Added UDF DOCUMENTS Reports.
Version 1.56 (October 2007)
ALL: Modified Active Reports to not automatically slide to the left-most column.
ALL: Improved View screen printing procedures.
UPDATE: Added Calendar Reports and Compare Calendars functions.
UPDATE: Changed date in Saved Calendar title from data date to the date that the file was saved.
Version 1.55 (September 2007)
UPDATE: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
UPDATE: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
BASELINE: Cleaned-up formatting of hourly holidays.
BASELINE: Speed-up the FINISH-TO-START LAGS USED Report.
BASELINE: Speed-up the NON-OVERLAPPING LAGS USED Report.
BASELINE: Speed-up the ODD LAGS OR LEADS USED Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT PREDECESSORS Report.
BASELINE: Speed-up the ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT SUCCESSORS Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
BASELINE: Prevented hang in FRACTIONAL DAYS Report if database problems exist.
BASELINE: Prevented hang in ODD LAGS OR LEADS Report if database problems exist.
ALL: No longer automatically install MDAC on installation.
Version 1.54 (September 2007)
ALL: Speed improvements in displaying schedule listing.
ALL: Corrected default report directory.
ALL: Allowed manual review and adjustment of user directories.
Version 1.53 (August 2007)
ALL: Modified file locations to comply with Vista security requirements.
Version 1.52 (July 2007)
BASELINE: Greatly Speed-up execution of ACTIVITIES WITHOUT FINISH SUCCESSORS Report.
BASELINE: Added maximum line count to ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
ALL: Allowed for Database Administrator to prevent writing to the P6 database.
BASELINE: Added Task Tags.
UPDATE: Added Task Tags.
Version 1.51 (July 2007)
LOGGER: Added Schedule Logger to the Schedule Analyzer suite.
ALL: Modified the default sever machine name and database to match new installs for P5.
ALL: Added Contractor to the list of login connections and removed the Version 3 Interbase option.
Version 1.50 (June 2007)
ALL: Changed over to use an external video player for Vista compatibility.
Version 1.49 (June 2007)
DATECALC: Added Ticker Tape, Save as Spreadsheet, and Print Functions.
DATECALC: Prevented Error 5 on loading Holidays.
BASELINE: Added Select Report function in View Report menu.
DASHBOARD: Added Select Report function in View Report menu.
UPDATE: Added Select Report function in View Report menu.
BASELINE: Redesigned and standardized View window with menus instead of buttons.
DASHBOARD: Redesigned and standardized View window with menus instead of buttons.
UPDATE: Redesigned and standardized View window with menus instead of buttons.
ALL: Improved saving video player settings.
Version 1.48 (June 2007)
ALL: Smart Copy now lists the title information in the second column and not the last.
ALL: Modified Smart Copy to put activity title in the second column.
UPDATE: Improved User-Defined Field check accuracy.
ALL: Modernized Help/About in support of HTML help conversion.
ALL: Converted over to HTML Help to support Vista installations.
MASTER: Added Help file.
BASELINE: Added maximum line limit to ACTIVITIES WITH TASK/DURATION TYPE MISMATCHES Report.
BASELINE: Corrected listing for "O-DUR" column in ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report.
BASELINE: Added maximum line limit to TOPIC Check Reports.
BASELINE: Corrected misprint of activity ID in ACTIVITIES WITH TOO MUCH FLOAT Report.
BASELINE: Corrected misprint of predecessor activity ID in 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report.
BASELINE: Corrected summary line in 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report
UPDATE: Reformat calendar report to fit the page better.
UPDATE: Additional Activity ID formatting to improve accuracy in over-detection of changes.
UPDATE: Improved Calendar Changes accuracy.
UPDATE: Improved UDF Task Reports accuracy with unusual task/UDF combinations.
DASHBOARD: Improved reporting when reports sections were skipped.
DASHBOARD: Improved error handling on displaying extremely large reports.
Version 1.47 (May 2007)
BASELINE: Formatted numeric Activity IDs correctly in Critical Path Summary Review.
BASELINE: Added more status indications while in-progress.
Version 1.46 (April 2007)
LONGPATH: Computation routines speeded-up.
LONGPATH: Calendar limits better handled and reported on.
Version 1.45 (March 2007)
LONGPATH: Added check for lag calendar and CPM calculation rule settings.
LONGPATH: Re-wrote CPM computation section.
ALL: Allowed multiple video players to be used.
ALL: Upgraded installer corrects for Vista loading problems.
Version 1.44 (March 2007)
UPDATE: Corrected problems when comparing numeric activity IDs.
Version 1.43 (March 2007)
UPDATE: Improved calendar precondition & pairing.
UPDATE: Improved User Defined Field Check for Project Records.
UPDATE: Added Cost User Defined Field checks.
Version 1.42 (February 2007)
ALL: Listed WBS in alphabetical sub-order
LONGPATH: Fixed unusual program hang during "Computing CPM."
ALL: Ensured 'clean end' to all background processes.
Version 1.41 (February 2007)
ALL: Database Version awareness increased from Version 9 to 99.
ALL: Added Project Last Updated to project select screen.
UPDATE: Fixed Percent Complete when Percent Complete Type is By Duration.
Version 1.40 (February 2007)
BASELINE: Added View print information help.
UPDATE: Added View print information help.
DASHBOARD: Added View print information help.
LONGPATH: Greatly Speed-up CPM/Slack/LPV calculation routines.
LONGPATH: Fixed time reported in Diagnostic Window.
Version 1.39 (January 2007)
BASELINE: Fixed error in relationship LOE check.
BASELINE: Fixed formatting problem in corrupt relationship check.
BASELINE: Fixed formatting problem in Baseline Schedules when activity id was very short.
UPDATE: Fixed formatting problem in Baseline Schedules when activity id was very short.
BASELINE: Fixed blank duplicate description report when too many exist to print all of them.
DASHBOARD: Made Video Help more prominent.
DASHBOARD: Added report name to title bar of program.
BASELINE: Improved Active Reports handling with P5.
UPDATE: Improved Active Reports handling with P5.
DASHBOARD: Improved Active Reports handling with P5.
Version 1.38 (November 2006)
UPDATE: Fixed reporting error with numeric Activity IDs.
BASELINE: Improved formatting of numeric Activity IDs.
BASELINE: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
DASHBOARD: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Reversed Predecessor & Successors in some reports.
Version 1.37 (October 2006)
BASELINE: fixed ACTIVITIES WITH TOO MUCH FLOAT Report.
ALL: Cosmetic update of Version Label in View Screen.
UPDATE: Fixed Error 1001 on main screen.
UPDATE: Improved User Interface on Main Screen.
UPATE: Updated help video to explain new user interface.
Version 1.36 (October 2006)
BASELINE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
BASELINE: Added ACTIVITIES WITH TOO MUCH FLOAT Report.
BASELINE: Fixed V 1.33 formatting error when numeric IDs are used.
UPDATE: Fixed V 1.33 formatting error when numeric IDs are used.
Version 1.35 (September 2006)
BASELINE: Added Immediate Report Help.
UPDATE: Added Immediate Report Help.
ALL: Added Copy Help video.
ALL: Added Report Help video.
ALL: Added Smart Copy to View menu.
Version 1.34 (September 2006)
ALL: Prevent exit (error) before schedules are done being displayed.
ALL: Allowed for early escape before all schedules are loaded.
Version 1.33 (August 2006)
UPDATE: Fixed PLANNED ACTIVITIES THAT HAVE BEEN DELETED SINCE LAST UPDATE report.
UPDATE: Fixed PLANNED ACTIVITIES THAT HAVE BEEN ADDED SINCE LAST UPDATE report.
UPDATE: Improved ADDED ACTIVITIES WITH FRACTIONAL DURATIONS report
UPDATE: Improved FRACTIONAL DURATION CHANGE report.
UPDATE: Improved Cancel from printing recovery.
UPDATE: Automatically resize reports for optimum amount of space.
BASELINE: Automatically resize reports for optimum amount of space.
BASELINE: Fixed formatting error in ACTIVITIES WITH TASK/DURATION MISMATCHES report.
BASELINE: Fixed ACTIVITY DISTRIBUTION HISTOGRAM report when unrealistically early project finish used.
BASELINE: Added schedule designation to every activity in multi-schedule analyses.
UPDATE: Added schedule designation to every activity in multi-schedule analyses.
Version 1.32 (July 2006)
BASELINE: More responsiveness added to Administrative Section.
MASTER: Modified program for Oracle compatibility
Version 1.31 (June 2006)
UPDATE: Allow multiple schedules to be analyzed at the same time.
UPDATE: Recorded new Help Video to explain new functioning.
UPDATE: Improved formatting of holidays with hours in the Calendar Section.
BASELINE: Improved formatting of holidays with hours in the Calendar Section.
UPDATE: Improved accuracy NEW ACTUAL DATES LATER THAN UPDATE DATE report.
UPDATE: Fixed Added/Deleted Task Resource Budgets reports.
UPDATE: Added Finished Run Help message.
BASELINE: Added Finished Run Help message.
ALL: Through review and rewriting of all controls 'bubble help.'
ALL: New login help video.
BASELINE: New help video.
Version 1.30 (May 2006)
ALL: Fixed edit function in on-line reports.
ALL: Improved Tool-Tip Messages & Button Placement.
LONGPATH: Fixed Option Screen Help Button.
Version 1.29 (May 2006)
DASHBOARD: Added new program to Schedule Analyzer.
BASELINE: Added Dashboard access.
UPDATE: Added Dashboard access.
MASTER: Fixed Error 400 problem.
MASTER: Fixed Help File problem.
Version 1.28 (May 2006)
ALL: Versions 1.25 - 1.27 were flawed due to incorrect Windows registration. Fixed.
Version 1.27 (March 2006)
BASELINE: Re-written for speed improvements.
BASELINE: Broke-out slow system checks from other administrative checks.
UPDATE: Improved processing speed when looking up expanded descriptions.
Version 1.26 (March 2006)
UPDATE: Better error recovery; resume working at next report.
UPDATE: Improved headers on printed reports.
BASELINE: Allow multiple schedules to be analyzed at the same time.
BASELINE: Improved headers on printed reports.
BASELINE: Administrative Preference check improvements.
BASELINE: Calendar check improvements.
Version 1.25 (March 2006)
ALL: Improved error handling with first-time User Logins.
ALL: Upgraded internal display controls to V5.
BASELINE: Fixed "CLICK ON ANY FILE IN THE DIRECTORY FOR USER FILES" repeating error.
LONGPATH: Prevent hang on close.
MASTER: Prevent hang on close.
UPDATE: Added ability to suppress any report in the series.
UPDATE: Fixed "CLICK ON ANY FILE IN THE DIRECTORY FOR USER FILES" repeating error.
UPDATE: Added Suspend/Resume Dates to the database.
UPDATE: Added 8 new Suspend/Resume date checks.
UPDATE: Fixed ACTIVE ACTIVITIES WITH NO PROGRESS Report.
UPDATE: Better error recovery; resume working at next report.
UPDATE: Improved headers on printed reports.
Version 1.24 (March 2006)
BASELINE: Made "ACTUAL FINISH IS BEFORE PROJECT START DATE" report more accurate.
BASELINE: Better recovery from canceled print.
BASELINE: Brought Personalize User Settings to main menu.
BASELINE: Improve identification of reports directory error recovery.
UPDATE: Improve identification of reports directory error recovery.
Version 1.23 (February 2006)
BASELINE: Improved speed and completness of Database Integrety Checks
Version 1.22 (January 2006)
UPDATE: Eliminated Automation Error.
UPDATE: Eliminated Unable to load SQL Server OLEDB DLL error.
UPDATE: Improved processing speed on projects with deep hierarchies.
UPDATE: Fixed Units printout on ACTIVITY RESOURCE UNITS/TIMEPERIOD Report.
BASELINE: Eliminated Automation Error.
BASELINE: Eliminated Unable to load SQL Server OLEDB DLL error.
BASELINE: Improved processing speed on projects with deep hierarchies.
Version 1.21 (December 2005)
BASELINE: fixed printing error in NON-OVERLAPPING LAGS USED report.
BASELINE: Multiple status-reporting enhancements.
BASELINE: Multiple report formatting improvements.
BASELINE: Multiple speed improvements when database has bad data.
Version 1.20 (November 2005)
BASELINE: Cleaned-up Database Integrity Check when no errors are present.
BASELINE: Added Activity Duration Type summary.
UPDATE: DELETED & RE-ADDED ACTIVITY Report added.
Version 1.19 (October 2005)
UPDATE: Added INVALID ADDED RELATIONSHIP (DUE TO STATUS) Report.
Version 1.18 (August 2005)
STEPS: Added Transfer File Steps Remover program.
Version 1.17 (August 2005)
UPDATE: Fixed "cannot find User Reports" error when schedule data dates are the same.
ALL: Fixed INI CONFIGURATION misfiling.
ALL: Internal separation of login configuration for future expansion.
BASELINE: Made Active Reports more accurate at guessing proper ID length.
UPDATE: Made Active Reports more accurate at guessing proper ID length.
ALL: Phrase "copied to clipboard" is only said once.
LONGPATH: Fixed Longest Path Initialization parameters problem.
Version 1.16 (July 2005)
UPDATE: Added Active Reports to jump straight to the schedule activity from the report.
BASELINE: Added Active Reports to jump straight to the schedule activity from the report.
Version 1.15 (June 2005)
UPDATE: Fixed hang in processing historical relationship lags section.
Version 1.14 (May 2005)
BASELINE: Added 6 CPM Settings checks plus cautions.
UPDATE: Added 7 CPM Settings checks plus cautions.
Version 1.13 (April 2005)
ALL: Bullet-proofed opening screen.
ALL: Removed SDK login and subsequent code to streamline and reduce the size of SAe
BASELINE: Added to Steps analysis.
LONGPATH: Fixed Cancel button.
Version 1.12 (March 2005)
ALL: Prevent hang-up on open of display of schedules to select
Version 1.11 (January 2005)
LONGPATH: Added more complete diagnostics.
LONGPATH: Removed semi-comma from SQL commands to prevent "Invalid Character" error with Oracle.
ALL: Updated to be compatible with P3e/c Version 5
Version 1.10 (December 2004)
UPDATE: Don't run CHANGE IN FLOAT GREATER THAN THE TIME IN THE UPDATE PERIOD Report if data date has not changed.
UPDATE: Don't run ACTIVIE ACTITIES WITHOUT PROGRESS Report if data date has not changed.
UPDATE: Added Longest Path flag to added relationships reports.
UPDATE: Added Longest Path flag to Modified Relationships reports.
ALL: Added System Administrator's manual to the distribution CD as a pdf file.
UPDATE: Don't perform Odd Float Check and Active Activities Without Progress if data date not changed.
UPDATE: Added Longest Path Flag to Added Relationship reports.
UPDATE: Added Longest Path Flag to Modified Relationship reports.
UPDATE: Added RELATIONSHIPS DELETED BEFORE TARGET DATE Report.
UPDATE: Added RELATIONSHIPS ADDED BEFORE TARGET DATA DATE Report.
UPDATE: Added MODIFIED RELATIONSHIP LAGS BEFORE THE TARGET DATA DATE Report.
UPDATE: Added various Warnings, Cautions, and Notes to Relationship Report Section.
Version 1.09 (November 2004)
UPDATE: Added cautions note to Active Activities without Status report.
LONGPATH: Improved error checking and reporting.
LONGPATH: Added automatic calendar extension if overrun.
Version 1.08 (October 2004)
UPDATE: Removed unneeded Changed WBS Check.
UPDATE: Improved Memo Check.
BASELINE: Improved Activity Code Check section.
BASELINE: Removed blank lines and added status tracking to Duplicate Descriptions Check.
Version 1.07 (September 2004)
LONGEST: Fixed problems with displaying answers.
BASELINE: Added Fractional Day Durations Report.
UPDATE: Added information notes to Fractional Duration checks.
ALL: Hide Login Settings if desired (and filled-in.)
ALL: Added Oracle OLE DB interface by Microsoft to login options.
Version 1.06 (August 2004)
BASELINE: Added option to skip integrity checks.
ALL: Perfected integration with MSSQL/MSDE or Oracle databases.
Version 1.05 (June 2004)
ALL: Converted over to INI-based parameter system for easier network installation.
ALL: Improved Database Connectivity and Configurability.
ALL: Show hidden "Save Login Settings" checkbox.
ALL: Install now automatically installs required Microsoft Data Access Components V2.6.
Version 1.04 (May 2004)
MASTER: Added Master Switch utility program to suite.
ALL: Added support for MSDN Database Server.
ALL: Improved Login Screen functionality.
Version 1.03 (December 2003)
ALL: Added 'save current screen font'.
ALL: Improved customization of window size and placement.
Version 1.02 (December 2003)
BASELINE: Added summary to Milestones coded as activities.
BASELINE: Fixed 'multiple rows in a singleton record' error.
ALL: Added P3e Version 4.0 compatibility.
ALL: Improved recovery on a single report error.
UPDATE: Added Modified WBS check.
Version 1.01 (December 2003)
UPDATE: Added As-Built float check
ALL: Final Beta Corrections: First Open Release
Version 1.00: Original Beta-Test, Released 31OCT03