Schedule Analyzer Upgrade Information

 
 
 
  Below is the entire update history of Schedule Analyzer for the Enterprise (SAe.) The current version is listed at the top. Registered, licensed Users are encouraged to look-up the version of their SAe software and reference the current updates here.
 
Key:
ALL: All SAe programs.
BASELINE: SAe Baseline Checker (released December 2003.)
DASHBOARD: SAe Dashboard (added May 2006.)
STEPS: File Transfer Steps Remover (added April 2005).
LOGGER: SAe Schedule Logger (added July 2007.)
LOGIC: SAe Logic League (created 2003 and added to SAe February 2008.)
LONGPATH: SAe Longest Path Software (released December 2003.)
MASTER: Master Switch utility program (added May 2004.)
RELATED: SAe Related Schedules (added January 2008.)
UPDATE: SAe Update Checker (released December 2003.)

CURRENT VERSION:
Version 2.70 (August 2010)
OVERVIEW: ADDED SORT FEATURE TO LONGEST PATH SUBSTANTIAL COMPLETION ACTIVITY.
ALL: Updated login to better remember non-local server names.
LONGPATH: Added sort by column to Substantial Completion selection screen.
Version 2.69 (August 2010)
OVERVIEW: ADDED UPDATE CHECKER CRITICAL ACTIVITIES BY AREA CODE REPORT
CALENDAR: Reversed the Form: and To: in Compare Saved.
UPDATE: Minor Percent Complete reporting modifications.
UPDATE: Prevent processing error while reporting on Activity Notes in an Oracle database.
UPDATE: Added the CRITICAL ACTIVITY COUNT BY ACTIVITY CODE Report
UPDATE: Updated Report Help to point to correct passages in the Help file.
Version 2.68 (14July 2010)
OVERVIEW: REPARED UPDATE CHECKER BLANK SCREEN
UPDATE: Fixed internal error causing only a blank screen to show.
Version 2.67 (09July 2010)
OVERVIEW: ADDED EXTERNAL CONSTRAINTS CHECKS
LOGGER: Minor enhancements in program user interface.
UPDATE: Added ability to ignore minor calendar name changes (just different number at teh end.)
ALL: Added Save as MS Word or Text file to the View Window.
BASELINE: Improved Notebook HTML translation.
BASELINE: Moved Agency Checks to the end of the analysis.
UPDATE: Moved Agency Checks to the end of the analysis.
UPDATE: Improved performance of Project WBS User-Defined field checks.
Version 2.66 (June 2010)
OVERVIEW: ADDED EXTERNAL CONSTRAINTS CHECKS
BASELINE: Improved formatting of BASELINE SCHEDULE CONSTRAINTS Report.
BASELINE: Added EXTERNAL CONSTRAINTS Report.
DASHBOARD: Added EXTERNAL CONSTRAINTS Report.
UPDATE: Added External Early Start Date to the database.
UPDATE: Added External Late Finish Date to the database.
UPDATE: Added External Date Constraints to Deleted Constraints Reports.
UPDATE: Added External Date Constraints to Added Constraints Reports.
UPDATE: Removed milestones and WBS activities from ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
BASELINE: Removed milestones for ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Removed milestones from ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
LOGON: Updated Help video.
BASELINE: Updated Help video.
UPDATE: Updated Help video.
Version 2.65 (June 2010)
OVERVIEW: UPGRADE TASK TAGS AND ACTIVE REPORTS. ADDED SAVE AS SPREADSHEET TO VIEW REPORTS
UPDATE: Removed Float column from AS-BUILT ACTIVITIES THAT HAVE BEEN DELETED SINCE LAST UPDATE Report.
Update: Fixed Error 5 issue in Notebooks section when report width was shorter than standard size.
BASELINE: Added Save to Spreadsheet in the Report View Window.
UPDATE: Added Save to Spreadsheet in the Report View Window.
DASHBOARD: Added Save to Spreadsheet in the Report View Window.
BASELINE: Improved Task Tag responsiveness.
UPDATE: Improved Task Tag responsiveness.
DASHBOARD: Improved Task Tag responsiveness.
BASELINE: Added ability to append Task Tags as opposed to just overwriting them.
UPDATE: Added ability to append Task Tags as opposed to just overwriting them.
DASHBOARD: Added ability to append Task Tags as opposed to just overwriting them.
BASELINE: Extensive timing improvements made for Active Reports.
UPDATE: Extensive timing improvements made for Active Reports.
DASHBOARD: Extensive timing improvements made for Active Reports.
Version 2.64 (May 2010)
OVERVIEW: FIXED ERROR CREATED IN VERSION 2.63 (ALL CUSTOMERS UPDATED.)
BASELINE: Fixed Run time error 13: Type Mismatch in Run Options screen.
UPDATE: Fixed Run time error 13: Type Mismatch in Run Options screen.
UPDATE: Improved handling of Activity Memo report for Oracle systems.
UPDATE: Improved handling of Activity Issues report for Oracle systems.
UPDATE: Fixed Unable to select Update Schedule after selecting an empty WBS.
Version 2.63 (May 2010)
OVERVIEW: OLDER P6 VERSIONS HOURS/DAY FACTOR ACCOMMODATED.
BASELINE: Bullet-proofed report start-up further.
UPDATE: Bullet-proofed report start-up further.
ALL: Added ability to turn off sound queues in Video Setup.
BASELINE: Added back in Hours/Day factor confirmation from Pre-Version 7 P6 systems.
UPDATE: Added back in Hours/Day factor confirmation from Pre-Version 7 P6 systems.
ALL: Task Tags now work if the Activity ID is numeric.
LONGPATH: Added ability to change Longest Path Value column label in P6.
LONGPATH: Update database updating routines to match P6v7 requirements.
Version 2.62 (April 2010)
OVERVIEW: MORE ORACLE DATABSE ACCOMODATION IMPROVEMETNS.
UPDATE: Added Oracle BLOB check in CPM Rules Check section.
BASELINE: Fixed Activity Integrity Checks #32, 33, & 39 for Oracle SQL date issue.
BASELINE: Fixed Oracle SQL MoveFirst problem (causing blank reports.)
UPDATE: Fixed Oracle SQL MoveFirst problem (causing blank reports.)
DASHBOARD: Added Save as Spreadsheet function.
BASELINE: Improved formatting of float values with decimals.
Version 2.61 (March 2010)
OVERVIEW: NEW BASELINE CHECKER REPORT AND UPGRADED DASHBOARD.
DASHBOARD: Major update to match wide reports.
DASHBOARD: Major error-proofing if report is missing sections.
BASELINE: Increased maximum Activity Title Length from 60 to 120.
UPDATE: Increased maximum Activity Title Length from 60 to 120.
BASELINE: Added fractional lag check to the ODD LAGS OR LEADS Report.
BASELINE: Added NEGATIVE LAGS USED Report.
DASHBOARD: Added NEGATIVE LAGS USED Report.
Version 2.60 (March 2010)
OVERVIEW: NEW UPDATE CHECKER REPORT.
UPDATE: Added ACTIVITIES THAT COULD HAVE FINISHED Report
DASHBOARD: Added ACTIVITIES THAT COULD HAVE FINISHED Report
DASHBOARD: Minor report enhancements.
ALL: Update Splash Screen
ALL: Updated teh Instashield software loaded settings.
Version 2.59 (March 2010)
OVERVIEW: UPGRADED DASHBOARD HANDLING.
BASELINE: Keep Baseline Checker running while Dashboard is working.
UPDATE: Keep Update Checker running while Dashboard is working.
Version 2.58 (February 2010)
OVERVIEW: UPGRADED DATE CALCULATOR.
ALL: Added Smart Copy Help Video.
UPDATE: Improved accuracy with ACTIVITIES WITH MODIFIED DURATION TYPES Report.
DATECALC: Multiple improvements to functionality.
Version 2.57 (February 2010)
OVERVIEW: CORRECTED FOR BLANK SCREEN AFTER LOGIN.
ALL: Corrected software production error introduced in Version 2.54.
Version 2.56 (November 2009)
OVERVIEW: IMPROVED REPORTS.
BASELINE: Added FS successor relationship to DANGLING ACTIVITIES WITH A SINGLE SS OR FF PREDECESSOR Report
BASELINE: Converted FRACTION OF A DAY DURATIONS Report to use P6v7 calendars.
Version 2.55 (January 2010)
OVERVIEW: IMPROVED REPORTS.
DASHBOARD: Changed File / Save process from an "Open" button to a "Save" button.
BASELINE: Converted Activity Duratin Histogram to use P6v7 calendars.
BASELINE: Converted One-day Activity durations report to use P6v7 calendars
Version 2.54 (December 2009)
OVERVIEW: IMPROVED GENERAL LOGIN HANDLING.
ALL: Internal error checking change for higher reliability.
All: Improved explanation for database connect failure due to incorrect settings.
ALL: Returned log-in error checking back to early set-up.
Version 2.52 (November 2009)
OVERVIEW: ALLOWED FOR RESET OF WINDOWS POSITIONING TO DEFALT LOCATIONS.
ALL: Added a Program Windows reset function.
Version 2.52 (November 2009)
OVERVIEW: IMPROVED ORACLE LOGIN.
ALL: Improved logon for Oracle installations.
BASELINE: Rounded all Total Floats as appropriate to nearest whole value for cleaner display.
BASELINE: Improved Constraints Section formatting & added activity status to complete constraint listing.
Version 2.51 (October2009)
OVERVIEW: RESTORED ACTIVE REPORTS FEATURE FOR P6v7.
ALL: Fixed Active Reports failure due to a P6, Version 7 change.
Version 2.50 (October 2009)
OVERVIEW: COMPLETED REVISION OF DURATIONS BASED UPON P6v7 CALENDAR FACTORS.
BASELINE: Added maximum list length to ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
BASELINE: Completed conversion of durations based upon P6v7 activity calendar conversion factors.
UPDATE: Improved Critical Summary report.
UPDATE: Prevented Error 6: Overflow on Report 146.
UPDATE: Completed conversion of durations based upon P6v7 activity calendar conversion factors.
Version 2.49 (September 2009)
OVERVIEW: UPGRADED TO MEET WINDOWS 7 REQUIREMENTS.
ALL: Updated internal screen controls for Windows 7 compatibility.
UPDATE: Spead-up building of resource database.
LONG PATH: Internal memory adjustment to support larger schedules.
Version 2.48 (September 2009)
OVERVIEW: UPGRADED TO MEET P6 v7 CHANGES TO THE DATABASE.
BASELINE: Updated User-Defined Fields checks to work with P6 v7 (new database change.)
UPDATE: Updated User-Defined Fields checks to work with P6 v7 (new database change.)
BASELINE: Updated UNUSUAL NUMBER OF MOBILIZATION ACTIVITIES FOUND Report.
BASELINE: Improved formatting of calendar holidays when multiple periods in a day were present.
CALENDAR: Added P6 v7 calendar hour conversion factors.
UPDATE: Modified Daily/Hourly Schedule Review programability.
BASELINE: Added Hour Conversion Factors to Calendar Summaries.
UPDATE: Spead-up and corrected bad SQL reads from Activity Cost Database.
Version 2.47 (September 2009)
OVERVIEW: ALLOWED FOR WIDER REPORTS AND LONGER ACTIVITY TITLES TO BE PRINTED.
BASELINE: Added ability to change the width of all reports, changing the amount of activity title displayed.
BASELINE: Quality checked the formatting of all reports.
BASELINE: Restored calendar checks.
BASELINE: Added Invalid Forecast Dates Report to DCMA 14-Point Checks Section.
UPDATE: Added ability to change the width of all reports, changing the amount of activity title displayed.
UPDATE: Added Invalid Forecast Dates Report to DCMA 14-Point Checks Section.
UPDATE: Moved numeric IDs to the right in reports.
DASHBORD: Added DCMA 14-point Checks Section.
Version 2.46 (September 2009)
OVERVIEW: ADDED DCMA 14-POINT CHECK TO UPDATE CHECKER.
ALL: Modified Project Open Screen to sort Projects by EPS like P6 does.
UPDATE: Added DCMA 14-Point Assessment Checks setion.
UPDATE: Modified internal procedures for calculating Maximum ID Length.
BASELINE: Fixed "User Requested Hault" error in calendar section when schedule had a "?" in the name.
Version 2.45 (August 2009)
OVERVIEW: ADDED SCHEDULE MATCH WHEN MULTIPLE SCHEDULES ARE SELECTED TO UPDATE CHECKER.
UPDATE: Spead-up ORPHANED ACTIVITIES Report.
UPDATE: Spead-up RELATIONSHIP ADDED WHEN ACTIVITY ADDED Report.
UPDATE: Improved accuracy in ADDED INVALID RELATIONSHIPS (DUE TO STATUS) Report.
UPDATE: Added schedule match capability when comparing groups of schedules at a time and improved accuracy.
UPDATE: Fixed missing target relationships issue.
BASELINE: Fixed listing of Primary Resource name in PRIMARY RESOURCE SUMMARY Report.
BASELINE: Fixed relationship type in INTER-PROJECT PREDECESSORS and SUCCESSORS Reports.
DASHBOARD: Fixed Added As-Built Activity Reporting.
Version 2.44 (August 2009)
OVERVIEW: UPGRADED UPDATE CHECKER'S ABILITY TO REVIEW MULTIPLE SCHEDULES.
UPDATE: Spead-up ORPHANED ACTIVITIES Report.
UPDATE: Spead-up RELATIONSHIP ADDED WHEN ACTIVITY ADDED Report.
UPDATE: Improved accuracy in ADDED INVALID RELATIONSHIPS (DUE TO STATUS) Report.
UPDATE: Added schedule match capability when comparing groups of schedules at a time and improved accuracy.
UPDATE: Fixed missing target relationships issue.
BASELINE: Fixed listing of Primary Resource name in PRIMARY RESOURCE SUMMARY Report.
BASELINE: Fixed relationship type in INTER-PROJECT PREDECESSORS and SUCCESSORS Reports.
DASHBOARD: Fixed Added As-Built Activity Reporting.
Version 2.44 (August 2009)
OVERVIEW: ADDED BASELINE CHECKER DCMA 14-POINT METRICS CHECK.
BASELINE: Added DCMA 14-Point Check.
BASELINE: Fixed the saving "Time Units are Organized by" setting.
BASELINE: Internal programming architecture changes for robustness.
UPDATE: Internal programming architecture changes for robustness.
Version 2.43 (August 2009)
OVERVIEW: UPDATE SOFTWARE INSTALLATION FOR WINDOWS 7.
ALL: Upgraded software loading system to be compatible with Windows 7.
Version 2.42 (July 2009)
OVERVIEW: FIXED A BASELINE CHECKER REPORT.
LONGEST PATH: We no longer try to reclaim 'unused fields' because they may be used but the title was not changed.
BASELINE: Fixed the ACTIVITIES WITH MULTIPLE LOGIC RELATIONSHIPS (NOT SS & FF PAIRS) Report.
Version 2.41 (June 2009)
OVERVIEW: ENHANCED SCHEDULE SELECTION PAGE.
ALL: Added combination box for login Server Name for multiple servers.
ALL: Update schedule selection screen for style and Windows 7.
LOGIC LEAGUE: Fixed Filter to remember past additions.
LOGIC LEAGUE: Fixed User Codes to remember past additions.
Version 2.40 (June 2009)
OVERVIEW: IMPROVED ACTIVITY MEMO COMPARISONS.
UPDATE: Allowed for super-large activity memos.
Version 2.39 (May 2009)
OVERVIEW: CREATED SEPERATE CALENDAR REVIWEING MODULE.
CALENDAR: Moved calendar viewing function from Baseline & Update Checker into seperate utility.
ALL: Fixed "Show Baselines" function.
Version 2.38 (May 2009)
OVERVIEW: IMPROVED ACTIVITY DESCRIPTION CHANGE DETECTION.
UPDATE: Improved accuracy of detection of activity description changes.
BASELINE: Calendar Report improvements.
ALL: Opening screen inactive while building list.
Version 2.37 (April 2009)
OVERVIEW: ADDED A NEW UPDATE CHECKER REPORT.
UPDATE: Added NEWLY COMPLETED ACTIVITIES WHICH FINISHED LATER THAN EXPECTED Report.
UPDATE: Error proofing for Run Time Error 28, out of stack space in ADDED AS-BUILT ACTIVITIES Report.
Version 2.36 (March 2009)
OVERVIEW: IMPROVED UPDATE CHECKER CONSTRAINTS SECTION.
UPDATE: Fixed skipping of Constraints Section when Activity Code Section was skipped.
UPDATE: Improved deleted constraints accuracy in odd situations.
UPDATE: Improved added constraints accuracy in odd situations.
BASELINE: Improved corrupted secondary constraints check.
Version 2.35 (February 2009)
OVERVIEW: IMPROVED OPEN SCHEDULE PAGE.
ALL: Display all projects in alphabetical order.
LONGPATH: Fixed CPM calculation error with completed activity with large positive lag.
LONGPATH: Fixed 1-hour error on initial activity CPM dates.
Version 2.34 (January 2009)
OVERVIEW: IMPROVED LONGEST PATH CPM ACCURACY.
BASELINE: Adjusted ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report to work with days as well as just hours.
LONGPATH: Caught rounding error in CPM calculations that could make LPV one hour too low.
LONGPATH: Allowed for all lag calendar settings to be used.
LONGPATH: Option to save generated calendars added.
LONGPATH: Option to save CPM calculations added.
LONGPATH: Re-write of calendar generation for speed and accuracy.
LONGPATH: Re-write of CPM forward pass for speed and accuracy.
UPDATE: Prevented reporting on completed activities in NEWLY ORPHANED ACTIVITIES Report.
UPDATE: Improved formatting of percent complete on reports.
Version 2.33 (December 2008)
OVERVIEW: IMPROVED CALENDAR REPORTS.
BASELINE: Improved the accuracy of Calendar Reports.
UPDATE: Improved the accuracy of Calendar Reports.
UPDATE: Fixed formatting of Memo Checks when memo was blank.
Version 2.32 (December 2008)
OVERVIEW: IMPROVED ERROR CHECKING FOR ACTIVITY PERCENT COMPLETE.
BASELINE: Prevented negative %-complete when RD > OD in ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Prevented negative %-complete when RD > OD in ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Corrected occasional formatting errors with NEW PERCENT COMPLETE THIS PERIOD Report.
UPDATE: Prevented negative %-complete in NEW PERCENT COMPLETE THIS PERIOD Report.
Version 2.31 (December 2008)
OVERVIEW: MAJOR INTERNAL MODIFICATION TO UPDATE CHECKER.
UPDATE: Fixed activity SQL ORDER error.
UPDATE: Fixed other causes for activity out of order issues.
UPDATE: Fixed activity steps SQL ORDER error.
UPDATE: Fixed activity codes SQL ORDER error.
UPDATE: Fixed activity constraints SQL ORDER error.
UPDATE: Fixed activity costs SQL ORDER error.
UPDATE: Fixed activity resources SQL ORDER error.
UPDATE: Improved ADDED RELATIONSHIPS Report.
UPDATE: Fixed internal Overflow Error while building Resource database.
UPDATE: Prevent SQL connection error while building resource database.
UPDATE: Sped-up Building Resource Database routine.
ALL: Positive program end when File / Cancel is selected in View.
Version 2.30 (November 2008)
OVERVIEW: IMPROVED TWO BASELINE RELATIONSHIP REPORTS.
BASELINE: Removed redundant rows in ACTIVITIES WITHOUT FINISH RELATIONSHIP Report.
BASELINE: Improved accuracy in SUBMITTALS WIHTOUT FINISH RELATIONSIPS Report.
Version 2.29 (November 2008)
OVERVIEW: MAINLY SCHEDULE OPEN DISPLAY ENHANCEMENTS.
UPDATE: Fixed same activity being reported as both Added & Deleted due to SQL ORDER error.
UPDATE: Fixed non-reporting on Costs when no Cost Accounts are defined but costs exist.
UPDATE: Removed the calendar compare section, because they overwrite each other.
ALL: Fixed cases where project name was incorrect (mainly an Oracle issue.)
ALL: Reorder the schedules in the list before WBS categories to match P6's orientation.
Version 2.28 (November 2008)
OVERVIEW: PREVENT ENDLESS LOOP WHILE SAVING REPORT
BASELINE: Fix endless loop while Checking Mobilization relationships.
UPDATE: Fix endless loop when opening the report.
Version 2.27 (November 2008)
OVERVIEW: IMPROVED ORACLE CONNECTION
ALL: Fixed Oracle Login-in glitch.
BASELINE: Corrected Duration Type Summary results.
ALL: Improved database server connectivity in slow environments.
Version 2.26 (September 2008)
OVERVIEW: ACTIVE REPORTS IMPROVED AND WSB SUMMARY TYPE ADDED
ALL: Improved Active Reports response to P6.
BASELINE: Included WBS Summary activities.
BASELINE: Excluded WBS Summary activities from missing predecessors and missing successors reports.
BASELINE: Excluded activities without successors from ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
UPDATE: Prevented Error 5 in Notebook Reports.
UPDATE: Added WBS activity type to reports.
Version 2.25 (September 2008)
OVERVIEW: MINOR FIXES AND IMPROVED RELIABILITY UPDATES
LONGPATH: Fixed calendar for working days on Saturday issue.
BASELINE: Fixed 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report.
BASELINE: Re-wrote ACTIVITIES WITHOUT PREDECESSORS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITHOUT SUCCESSORS Report to prevent Data Server Time-outs.
BASELINE: Re-wrote ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report to prevent Data Server Time-outs.
Version 2.24 (August 2008)
OVERVIEW: IMPROVED CITRIX INSTALLATION PERFORMANCE
BASELINE: Fixed occasional formatting problem with ALL OTHER LAGS OR LEADS USED Report.
ALL: Added command line parameter to override initialization file location.
Version 2.23 (August 2008)
OVERVIEW: IMPROVED VIEW PERFORMANCE WITH VERY LARGE SCHEDULES
ALL: Prevented View Screen from freezing-up with a very large report.
UPDATE: Fixed Error 9 on Day of the Week Reports.
Version 2.22 (August 2008)
OVERVIEW: ADDED UPDATE CHECKER REPORTS LABELING ACTUAL DATES WITH THEIR DAY OF THE WEEK
Baseline: Fixed Data Date and Project Name display in the header of the report.
UPDATE: Fixed Project Name in report header.
UPDATE: Added the NEW ACTUAL START DATE SORTED BY WORKDAY Report.
UPDATE: Added the NEW ACTUAL FINISH DATE SORTED BY WORKDAY Report.
Version 2.21 (August 2008)
OVERVIEW: MINOR ERROR CORRECTIONS
UPDATE: Fixed Activity Issue "maximum number listed" error.
BASELINE: Fix error in NON-OVERLAPPING LAGS Report.
Version 2.20 (August 2008)
OVERVIEW: CORRECTED OVER-REPORTING OF MILESTONE ACTIVITIES IN UPDATE CHECKER
Update: Corrected MISSING ACTUAL START DATES Report for milestones.
Update: Corrected NEW ACTUAL DATES EARLIER THAN TARGET DATE Report for milestones.
Update: Corrected NEW ACTUAL DATES LATER THAN UPDATE DATE Report for milestones.
Update: Corrected MISSING ACTUAL START DATES Report for milestones.
Update: Corrected NEW ACTUAL DATES EARLIER THAN TARGET DATE Report for milestones.
Update: Corrected NEW ACTUAL DATES LATER THAN UPDATE DATE Report for milestones.
BASELINE: Added a note warning about using Global Calendars.
Version 2.19 (July 2008)
OVERVIEW: ADDED MORE SUPPORT FOR LARGE NOTEBOOK LIBRARIES
UPDATE: Added more status reporting for Notebook checks.
UPDATE: Corrected NEW ACTUAL DATES WITH INCORRECT TIMES Report to properly account for milestone activities.
Version 2.18 (July 2008)
OVERVIEW: MINOR REPORT UPDATES AND BETTER ACTIVE REPORTS FUNCTIONALITY
ALL: Improved Active Reports response to P6 screen conditions.
BASELINE: Fixed the ACTIVITIES WITH TOO MUCH FLOAT Report.
UPDATE: Corrected float in CHANGE IN FLOAT GREATER THAN THE NUMBER OF DAYS IN THE UPDATE PERIOD Report.
Version 2.17 (July 2008)
OVERVIEW: FINAL CORRECTION FOR UPDATE CHECKER DEALING WITH NUMERIC ACTIVITY IDs
ALL: Added multiple database logon capability.
UPDATE: Final Numeric Activity ID adjustment. Version 2.16 is incorrect and should not be used.
UPDATE: Fixed a minor Calendar Report formatting error.
Version 2.16 (July 2008)
OVERVIEW: TEST PATCH FOR UPDATE CHECKER DEALING WITH NUMERIC ACTIVITY IDs
UPDATE: Attempt to correct for over-reporting in schedules with numeric Activity IDs.
Version 2.15 (July 2008)
OVERVIEW: ADDED NEW UPDATE CHECKER REPORT.
UPDATE: Added NEW ACTUAL DATES WITH INCORRECT TIMES Report.
DASHBOARD: Added NEW ACTUAL DATES WITH INCORRECT TIMES Report.
UPDATE: Updated Exclude Reports Section.
Version 2.14 (July 2008)
OVERVIEW: MINOR INTERNAL IMPROVEMENTS.
LOGIC: Changed SQL calls to comply with Oracle requirements.
UPDATE: Fixed Calendar Report.
Version 2.13 (June 2008)
OVERVIEW: ADDED SUMMARY OVERVIEW.
BASELINE: Added Summary overview section to the report.
Version 2.12 (May 2008)
OVERVIEW:ERROR-PROOFED CPM CHECK.
BASELINE: Caught incorrect reporting of CPM settings if CPM in the schedule had never been computed.
UPDATE: Caught incorrect reporting of CPM settings if CPM in the schedule had never been computed.
Version 2.11 (May 2008)
OVERVIEW: SPEED-UP UPDATE CHECKER PROCESSING.
UPDATE: Dramatically sped-up relationship database building and prevented data server thrashing.
Version 2.10 (May 2008)
OVERVIEW: FIXED UNCOMMON ERROR IN UPDATE CHECKER.
UPDATE: Fixed endless loop opening report if project name is odd and report run more than once.
Version 2.09 (April 2008)
OVERVIEW: SELECT SCHEDULES FASTER BY LIMITING SCHEDULES SHOWN.
LONGPATH: Sped-up Pre-Slack preparation section.
ALL: Limit the number of schedules displayed by selecting their OBS.
Version 2.08 (April 2008)
OVERVIEW: ADJUSTED TWO UPDATE CHECKER REPORTS.
UPDATE: Fixed ACTIVITIES WITH MODIFIED DURATION TYPES Report.
UPDATE: Fixed ACTIVITIES WITH MODIFIED PERCENT COMPLETE TYPES Report.
Version 2.07 (March 2008)
OVERVIEW: IMPROVED ERROR CHECKING IN LONGEST PATH.
LONGPATH: Added the program to the run menu (previously loaded but not visible.)
LONGPATH: Fixed condition where Longest Path Sequence Number = 32000 (Completed activities without dates.)
UPDATE: Fixed Error 3001 in Comparing Issue Notes section.
Version 2.06 (March 2008)
OVERVIEW: ALLOWED BASELINE CHECKER TO DEAL WITH POORLY-MADE MEGA-SCHEDULES.
BASELINE: Added limit to stop checking (as opposes to just stop reporting.)
Version 2.05 (February 2008)
OVERVIEW: COMPLETION OF DISPLAYING PROJECTS SPEEDUP.
LOGIC: Greatly speed-up start of Open Project screen.
MASTER: Greatly speed-up start of Open Project screen.
LOGIC: Greatly speed-up re-painting of Open Project screen with baseline schedules.
MASTER: Greatly speed-up re-painting of Open Project screen.
DASHBORD: Allowed user to change screen font and size.
Version 2.04 (February 2008)
OVERVIEW: BEGINNING OF SIGNIFIANTLY FASTER AT DISPLAYING PROJECTS.
BASELINE: Greatly speed-up start of Open Project screen.
LOGGER: Greatly speed-up start of Open Project screen.
LONGPATH: Greatly speed-up start of Open Project screen.
RELATED: Greatly speed-up start of Open Project screen.
UPDATE: Greatly speed-up start of Open Project screen.
BASELINE: Greatly speed-up re-painting of Open Project screen with baseline schedules.
LOGGER: Greatly speed-up re-painting of Open Project screen with baseline schedules.
LONGPATH: Greatly speed-up re-painting of Open Project screen with baseline schedules.
RELATED: Greatly speed-up re-painting of Open Project screen with baseline schedules.
UPDATE: Greatly speed-up re-painting of Open Project screen with baseline schedules.
Version 2.03 (February 2008)
OVERVIEW: DUPLICATED P6 OPEN PROJECT SCREEN.
BASELINE: Improved look of Open Project screen with color-coded hierarchy.
LOGGER: Improved look of Open Project screen with color-coded hierarchy.
LONGPATH: Improved look of Open Project screen with color-coded hierarchy.
RELATED: Improved look of Open Project screen with color-coded hierarchy.
UPDATE: Improved look of Open Project screen with color-coded hierarchy.
Version 2.02 (February 2008)
OVERVIEW: IMPROVED RELATED SCHEDULES PROGRAM.
DASHBOARD: More error-proofing on file open.
RELATED: Added Relationships and Lags to report.
RELATION: Prevented Run Time Error 3265.
BASELINE: Numerous spelling corrections.
UPDATE: Numerous spelling corrections.
Version 2.01 (January 2008)
OVERVIEW: MINOR CHANGES.
ALL: Prevented ORA-00911 error for Oracle installations.
LOGIC: Fixed video presentation.
ALL: More error protection from Internal Error 75 on login.
Version 2.00 (January 2008)
OVERVIEW: MOVED LOGIC LEAGUE TO THE SAe PACKAGE.
LOGIC: Added Logic League to Schedule Analyzer. Also made extensive user enhancements.
UPDATE: Added Average Float calculation.
UPDATE: Added ability to limit the number of lines in the ODD TOTAL FLOAT Report.
Version 1.62 (May 2007)
OVERVIEW: LAST VERSION 1 UPGRADE. FIXED TWO OPERATING ERRORS.
RELATED: Added relationship type and lag to report lines
Relation: Prevented Run Time Error 3265.
UPDATE: Prevented un-ending loop opening report with an unusual file name.
Version 1.61 (February 2007)
OVERVIEW: FIXED OPERATING ERRORS.
ALL: Fixed Oracle error number ORA-00911.
DASHBOARD: More error-proofing on file open.
ALL: Fixed program folder automatically opening on computer startup.
Version 1.60 (December 2007)
OVERVIEW: ADDED ISSUES AND ATTACHED DOCUMENTS SECTION FOR A TOTAL OF 13 NEW REPORTS.
BASELINE: Changed internal Memo collection to meet Oracle database restrictions.
UPDATE: Changed internal Memo collection to meet Oracle database restrictions.
BASELINE: Added EXPANDED REFERENCED DOCUMENT TYPE LAYOUT Report.
BASELINE: Added ATTACHED ACTIVITY DOCUMENTS Report.
BASELINE: Added: PROJECT DOCUMENT FILE Report.
DASHBOARD: Added ATTACHED ACTIVITY DOCUMENTS Report.
DASHBOARD: Added: PROJECT DOCUMENT FILE Report.
BASELINE: Improved COMPLETE PROJECT NOTES Report by removing HTML Tags
UPDATE: Added DELETED PROJECT DOCUMENTS Report.
UPDATE: Added ADDED PROJECT DOCUMENTS Report.
UPDATE: Added CHANGED PROJECT DOCUMENTS Report.
UPDATE: Added CHANGED PROJECT DOCUMENT LOCATION Report.
DASHBOARD: Added DELETED PROJECT DOCUMENTS Report.
DASHBOARD: Added ADDED PROJECT DOCUMENTS Report.
DASHBOARD: Added CHANGED PROJECT DOCUMENTS Report.
DASHBOARD: Added CHANGED PROJECT DOCUMENT LOCATION Report.
BASELINE: Added PROJECT ISSUES Report.
BASELINE: Added ACTIVITY ISSUES Report.
DASHBOARD: Added PROJECT ISSUES Report.
DASHBOARD: Added ACTIVITY ISSUES Report.
UPDATE: Added DELETED PROJECT ISSUES Report.
UPDATE: Added ADDED PROJECT ISSUES Report.
UPDATE: Added MODIFIED PROJECT ISSUE DATA Report.
UPDATE: Added MODIFIED PROJECT ISSUE NOTES Report.
DASHBOARD: Added DELETED PROJECT ISSUES Report.
DASHBOARD: Added ADDED PROJECT ISSUES Report.
DASHBOARD: Added MODIFIED PROJECT ISSUE DATA Report.
DASHBOARD: Added MODIFIED PROJECT ISSUE NOTES Report.
Version 1.59 (November 2007)
ALL: Fixed Line Edit: Cancel Button function while viewing reports.
ALL: Added View/ Copy Activity ID and Copy Full Activity description to menu.
ALL: Added Task Tag Help video.
ALL: Added Copy Activity Help video.
DASHBOARD: Improved INI Lower and Upper setting procedure.
DASHBOARD: Fixed ability to manually update Lower and Upper settings.
DASHBOARD: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
DASHBOARD: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
DASHBOARD: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
DASHBOARD: Added UDF Costs Reports.
DASHBOARD: Added UDF WBS Reports.
DASHBOARD: Added UDF ISSUES Reports.
DASHBOARD: Added UDF RISKS Reports.
DASHBOARD: Added UDF DOCUMENTS Reports.
LOGGER: Skip reports tagged to not contain Activity IDs (internal reliability enhancement.)
ALL: Don't run Active Reports routine if report is not based on Activity ID.
Version 1.58 (November 2007)
BASELINE: Added Saved Calendar creation to baseline check as well as with update check.
BASELINE: Added Calendar Reports function.
RELATED: Fixed No Column 6 error.
Version 1.57 (October 2007)
UPDATE: Added User-Defined Field (UDF) Costs Reports.
UPDATE: Added UDF WBS Reports.
UPDATE: Added UDF ISSUES Reports.
UPDATE: Added UDF RISKS Reports.
UPDATE: Added UDF DOCUMENTS Reports.
Version 1.56 (October 2007)
ALL: Modified Active Reports to not automatically slide to the left-most column.
ALL: Improved View screen printing procedures.
UPDATE: Added Calendar Reports and Compare Calendars functions.
UPDATE: Changed date in Saved Calendar title from data date to the date that the file was saved.
Version 1.55 (September 2007)
UPDATE: Added the ACTIVITIES WITH NEW ACTUAL DATES THIS PERIOD Report.
UPDATE: Added the NEW PERCENT COMPLETE THIS PERIOD Report.
BASELINE: Cleaned-up formatting of hourly holidays.
BASELINE: Speed-up the FINISH-TO-START LAGS USED Report.
BASELINE: Speed-up the NON-OVERLAPPING LAGS USED Report.
BASELINE: Speed-up the ODD LAGS OR LEADS USED Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT PREDECESSORS Report.
BASELINE: Speed-up the ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT SUCCESSORS Report.
BASELINE: Speed-up the ACTIVITIES WITHOUT A FINISH RELATIONSHIP Report.
BASELINE: Prevented hang in FRACTIONAL DAYS Report if database problems exist.
BASELINE: Prevented hang in ODD LAGS OR LEADS Report if database problems exist.
ALL: No longer automatically install MDAC on installation.
Version 1.54 (September 2007)
ALL: Speed improvements in displaying schedule listing.
ALL: Corrected default report directory.
ALL: Allowed manual review and adjustment of user directories.
Version 1.53 (August 2007)
ALL: Modified file locations to comply with Vista security requirements.
Version 1.52 (July 2007)
BASELINE: Greatly Speed-up execution of ACTIVITIES WITHOUT FINISH SUCCESSORS Report.
BASELINE: Added maximum line count to ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
ALL: Allowed for Database Administrator to prevent writing to the P5/P6 database.
BASELINE: Added Task Tags.
UPDATE: Added Task Tags.
Version 1.51 (July 2007)
LOGGER: Added Schedule Logger to the Schedule Analyzer suite.
ALL: Modified the default sever machine name and database to match new installs for P5.
ALL: Added Contractor to the list of login connections and removed the Version 3 Interbase option.
Version 1.50 (June 2007)
ALL: Changed over to use an external video player for Vista compatibility.
Version 1.49 (June 2007)
DATECALC: Added Ticker Tape, Save as Spreadsheet, and Print Functions.
DATECALC: Prevented Error 5 on loading Holidays.
BASELINE: Added Select Report function in View Report menu.
DASHBOARD: Added Select Report function in View Report menu.
UPDATE: Added Select Report function in View Report menu.
BASELINE: Redesigned and standardized View window with menus instead of buttons.
DASHBOARD: Redesigned and standardized View window with menus instead of buttons.
UPDATE: Redesigned and standardized View window with menus instead of buttons.
ALL: Improved saving video player settings.
Version 1.48 (June 2007)
ALL: Smart Copy now lists the title information in the second column and not the last.
ALL: Modified Smart Copy to put activity title in the second column.
UPDATE: Improved User-Defined Field check accuracy.
ALL: Modernized Help/About in support of HTML help conversion.
ALL: Converted over to HTML Help to support Vista installations.
MASTER: Added Help file.
BASELINE: Added maximum line limit to ACTIVITIES WITH TASK/DURATION TYPE MISMATCHES Report.
BASELINE: Corrected listing for "O-DUR" column in ACTIVITY ORIGINAL DURATIONS EQUAL TO ONE Report.
BASELINE: Added maximum line limit to TOPIC Check Reports.
BASELINE: Corrected misprint of activity ID in ACTIVITIES WITH TOO MUCH FLOAT Report.
BASELINE: Corrected misprint of predecessor activity ID in 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report.
BASELINE: Corrected summary line in 'NON-HAMMOCK TYPE' LOE RELATIONSHIPS Report
UPDATE: Reformat calendar report to fit the page better.
UPDATE: Additional Activity ID formatting to improve accuracy in over-detection of changes.
UPDATE: Improved Calendar Changes accuracy.
UPDATE: Improved UDF Task Reports accuracy with unusual task/UDF combinations.
DASHBOARD: Improved reporting when reports sections were skipped.
DASHBOARD: Improved error handling on displaying extremely large reports.
Version 1.47 (May 2007)
BASELINE: Formatted numeric Activity IDs correctly in Critical Path Summary Review.
BASELINE: Added more status indications while in-progress.
Version 1.46 (April 2007)
LONGPATH: Computation routines speeded-up.
LONGPATH: Calendar limits better handled and reported on.
Version 1.45 (March 2007)
LONGPATH: Added check for lag calendar and CPM calculation rule settings.
LONGPATH: Re-wrote CPM computation section.
ALL: Allowed multiple video players to be used.
ALL: Upgraded installer corrects for Vista loading problems.
Version 1.44 (March 2007)
UPDATE: Corrected problems when comparing numeric activity IDs.
Version 1.43 (March 2007)
UPDATE: Improved calendar precondition & pairing.
UPDATE: Improved User Defined Field Check for Project Records.
UPDATE: Added Cost User Defined Field checks.
Version 1.42 (February 2007)
ALL: Listed WBS in alphabetical sub-order
LONGPATH: Fixed unusual program hang during "Computing CPM."
ALL: Ensured 'clean end' to all background processes.
Version 1.41 (February 2007)
ALL: Database Version awareness increased from Version 9 to 99.
ALL: Added Project Last Updated to project select screen.
UPDATE: Fixed Percent Complete when Percent Complete Type is By Duration.
Version 1.40 (February 2007)
BASELINE: Added View print information help.
UPDATE: Added View print information help.
DASHBOARD: Added View print information help.
LONGPATH: Greatly Speed-up CPM/Slack/LPV calculation routines.
LONGPATH: Fixed time reported in Diagnostic Window.
Version 1.39 (January 2007)
BASELINE: Fixed error in relationship LOE check.
BASELINE: Fixed formatting problem in corrupt relationship check.
BASELINE: Fixed formatting problem in Baseline Schedules when activity id was very short.
UPDATE: Fixed formatting problem in Baseline Schedules when activity id was very short.
BASELINE: Fixed blank duplicate description report when too many exist to print all of them.
DASHBOARD: Made Video Help more prominent.
DASHBOARD: Added report name to title bar of program.
BASELINE: Improved Active Reports handling with P5.
UPDATE: Improved Active Reports handling with P5.
DASHBOARD: Improved Active Reports handling with P5.
Version 1.38 (November 2006)
UPDATE: Fixed reporting error with numeric Activity IDs.
BASELINE: Improved formatting of numeric Activity IDs.
BASELINE: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
DASHBOARD: Added ACTIVITIES WITH PREDECESSORS BUT NO START RELATIONSHIPS Report.
BASELINE: Reversed Predecessor & Successors in some reports.
Version 1.37 (October 2006)
BASELINE: fixed ACTIVITIES WITH TOO MUCH FLOAT Report.
ALL: Cosmetic update of Version Label in View Screen.
UPDATE: Fixed Error 1001 on main screen.
UPDATE: Improved User Interface on Main Screen.
UPATE: Updated help video to explain new user interface.
Version 1.36 (October 2006)
BASELINE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
UPDATE: Added ACTIVITIES WITH REMAINING DURATION / % COMPLETE MISMATCHES Report.
BASELINE: Added ACTIVITIES WITH TOO MUCH FLOAT Report.
BASELINE: Fixed V 1.33 formatting error when numeric IDs are used.
UPDATE: Fixed V 1.33 formatting error when numeric IDs are used.
Version 1.35 (September 2006)
BASELINE: Added Immediate Report Help.
UPDATE: Added Immediate Report Help.
ALL: Added Copy Help video.
ALL: Added Report Help video.
ALL: Added Smart Copy to View menu.
Version 1.34 (September 2006)
ALL: Prevent exit (error) before schedules are done being displayed.
ALL: Allowed for early escape before all schedules are loaded.
Version 1.33 (August 2006)
UPDATE: Fixed PLANNED ACTIVITIES THAT HAVE BEEN DELETED SINCE LAST UPDATE report.
UPDATE: Fixed PLANNED ACTIVITIES THAT HAVE BEEN ADDED SINCE LAST UPDATE report.
UPDATE: Improved ADDED ACTIVITIES WITH FRACTIONAL DURATIONS report
UPDATE: Improved FRACTIONAL DURATION CHANGE report.
UPDATE: Improved Cancel from printing recovery.
UPDATE: Automatically resize reports for optimum amount of space.
BASELINE: Automatically resize reports for optimum amount of space.
BASELINE: Fixed formatting error in ACTIVITIES WITH TASK/DURATION MISMATCHES report.
BASELINE: Fixed ACTIVITY DISTRIBUTION HISTOGRAM report when unrealistically early project finish used.
BASELINE: Added schedule designation to every activity in multi-schedule analyses.
UPDATE: Added schedule designation to every activity in multi-schedule analyses.
Version 1.32 (July 2006)
BASELINE: More responsiveness added to Administrative Section.
MASTER: Modified program for Oracle compatibility
Version 1.31 (June 2006)
UPDATE: Allow multiple schedules to be analyzed at the same time.
UPDATE: Recorded new Help Video to explain new functioning.
UPDATE: Improved formatting of holidays with hours in the Calendar Section.
BASELINE: Improved formatting of holidays with hours in the Calendar Section.
UPDATE: Improved accuracy NEW ACTUAL DATES LATER THAN UPDATE DATE report.
UPDATE: Fixed Added/Deleted Task Resource Budgets reports.
UPDATE: Added Finised Run Help message.
BASELINE: Added Finished Run Help message.
ALL: Through review and rewriting of all controls 'bubble help.'
ALL: New login help video.
BASELINE: New help video.
Version 1.30 (May 2006)
ALL: Fixed edit function in on-line reports.
ALL: Improved Tool-Tip Messages & Button Placement.
LONGPATH: Fixed Option Screen Help Button.
Version 1.29 (May 2006)
DASHBOARD: Added new program to Schedule Analyzer.
BASELINE: Added Dashboard access.
UPDATE: Added Dashboard access.
MASTER: Fixed Error 400 problem.
MASTER: Fixed Help File problem.
Version 1.28 (May 2006)
ALL: Versions 1.25 - 1.27 were flawed due to incorrect Windows registration. Fixed.
Version 1.27 (March 2006)
BASELINE: Re-written for speed improvements.
BASELINE: Broke-out slow system checks from other administrative checks.
UPDATE: Improved processing speed when looking up expanded descriptions.
Version 1.26 (March 2006)
UPDATE: Better error recovery; resume working at next report.
UPDATE: Improved headers on printed reports.
BASELINE: Allow multiple schedules to be analyzed at the same time.
BASELINE: Improved headers on printed reports.
BASELINE: Administrative Preference check improvements.
BASELINE: Calendar check improvements.
Version 1.25 (March 2006)
ALL: Improved error handling with first-time User Logins.
ALL: Upgraded internal display controls to V5.
BASELINE: Fixed "CLICK ON ANY FILE IN THE DIRECTORY FOR USER FILES" repeating error.
LONGPATH: Prevent hang on close.
MASTER: Prevent hang on close.
UPDATE: Added ability to suppress any report in the series.
UPDATE: Fixed "CLICK ON ANY FILE IN THE DIRECTORY FOR USER FILES" repeating error.
UPDATE: Added Suspend/Resume Dates to the database.
UPDATE: Added 8 new Suspend/Resume date checks.
UPDATE: Fixed ACTIVE ACTIVITIES WITH NO PROGRESS Report.
UPDATE: Better error recovery; resume working at next report.
UPDATE: Improved headers on printed reports.
Version 1.24 (March 2006)
BASELINE: Made "ACTUAL FINISH IS BEFORE PROJECT START DATE" report more accurate.
BASELINE: Better recovery from canceled print.
BASELINE: Brought Personalize User Settings to main menu.
BASELINE: Improve identification of reports directory error recovery.
UPDATE: Improve identification of reports directory error recovery.
Version 1.23 (February 2006)
BASELINE: Improved speed and completness of Database Integrety Checks
Version 1.22 (January 2006)
UPDATE: Eliminated Automation Error.
UPDATE: Eliminated Unable to load SQL Server OLEDB DLL error.
UPDATE: Improved processing speed on projects with deep hierarchies.
UPDATE: Fixed Units printout on ACTIVITY RESOURCE UNITS/TIMEPERIOD Report.
BASELINE: Eliminated Automation Error.
BASELINE: Eliminated Unable to load SQL Server OLEDB DLL error.
BASELINE: Improved processing speed on projects with deep hierarchies.
Version 1.21 (December 2005)
BASELINE: fixed printing error in NON-OVERLAPPING LAGS USED report.
BASELINE: Multiple status-reporting enhancements.
BASELINE: Multiple report formatting improvements.
BASELINE: Multiple speed improvements when database has bad data.
Version 1.20 (November 2005)
BASELINE: Cleaned-up Database Integrity Check when no errors are present.
BASELINE: Added Activity Duration Type summary.
UPDATE: DELETED & RE-ADDED ACTIVITY Report added.
Version 1.19 (October 2005)
UPDATE: Added INVALID ADDED RELATIONSHIP (DUE TO STATUS) Report.
Version 1.18 (August 2005)
STEPS: Added Transfer File Steps Remover program.
Version 1.17 (August 2005)
UPDATE: Fixed "cannot find User Reports" error when schedule data dates are the same.
ALL: Fixed INI CONFIGURATION misfiling.
ALL: Internal separation of login configuration for future expansion.
BASELINE: Made Active Reports more accurate at guessing proper ID length.
UPDATE: Made Active Reports more accurate at guessing proper ID length.
ALL: Phrase "copied to clipboard" is only said once.
LONGPATH: Fixed Longest Path Initialization parameters problem.
Version 1.16 (July 2005)
UPDATE: Added Active Reports to jump straight to the schedule activity from the report.
BASELINE: Added Active Reports to jump straight to the schedule activity from the report.
Version 1.15 (June 2005)
UPDATE: Fixed hang in processing historical relationship lags section.
Version 1.14 (May 2005)
BASELINE: Added 6 CPM Settings checks plus cautions.
UPDATE: Added 7 CPM Settings checks plus cautions.
Version 1.13 (April 2005)
ALL: Bullet-proofed opening screen.
ALL: Removed SDK login and subsequent code to streamline and reduce the size of SAe
BASELINE: Added to Steps analysis.
LONGPATH: Fixed Cancel button.
Version 1.12 (March 2005)
ALL: Prevent hang-up on open of display of schedules to select
Version 1.11 (January 2005)
LONGPATH: Added more complete diagnostics.
LONGPATH: Removed semi-comma from SQL commands to prevent "Invalid Character" error with Oracle.
ALL: Updated to be compatible with P3e/c Version 5
Version 1.10 (December 2004)
UPDATE: Don't run CHANGE IN FLOAT GREATER THAN THE TIME IN THE UPDATE PERIOD Report if data date has not changed.
UPDATE: Don't run ACTIVIE ACTITIES WITHOUT PROGRESS Report if data date has not changed.
UPDATE: Added Longest Path flag to added relationships reports.
UPDATE: Added Longest Path flag to Modified Relationships reports.
ALL: Added System Administrator's manual to the distribution CD as a pdf file.
UPDATE: Don't perform Odd Float Check and Active Activities Without Progress if data date not changed.
UPDATE: Added Longest Path Flag to Added Relationship reports.
UPDATE: Added Longest Path Flag to Modified Relationship reports.
UPDATE: Added RELATIONSHIPS DELETED BEFORE TARGET DATE Report.
UPDATE: Added RELATIONSHIPS ADDED BEFORE TARGET DATA DATE Report.
UPDATE: Added MODIFIED RELATIONSHIP LAGS BEFORE THE TARGET DATA DATE Report.
UPDATE: Added various Warnings, Cautions, and Notes to Relationship Report Section.
Version 1.09 (November 2004)
UPDATE: Added cautions note to Active Activities without Status report.
LONGPATH: Improved error checking and reporting.
LONGPATH: Added automatic calendar extension if overrun.
Version 1.08 (October 2004)
UPDATE: Removed unneeded Changed WBS Check.
UPDATE: Improved Memo Check.
BASELINE: Improved Activity Code Check section.
BASELINE: Removed blank lines and added status tracking to Duplicate Descriptions Check.
Version 1.07 (September 2004)
LONGEST: Fixed problems with displaying answers.
BASELINE: Added Fractional Day Durations Report.
UPDATE: Added information notes to Fractional Duration checks.
ALL: Hide Login Settings if desired (and filled-in.)
ALL: Added Oracle OLE DB interface by Microsoft to login options.
Version 1.06 (August 2004)
BASELINE: Added option to skip integrity checks.
ALL: Perfected integration with MSSQL/MSDE or Oracle databases.
Version 1.05 (June 2004)
ALL: Converted over to INI-based parameter system for easier network installation.
ALL: Improved Database Connectivity and Configurability.
ALL: Show hidden "Save Login Settings" checkbox.
ALL: Install now automatically installs required Microsoft Data Access Components V2.6.
Version 1.04 (May 2004)
MASTER: Added Master Switch utility program to suite.
ALL: Added support for MSDN Database Server.
ALL: Improved Login Screen functionality.
Version 1.03 (December 2003)
ALL: Added 'save current screen font'.
ALL: Improved customization of window size and placement.
Version 1.02 (December 2003)
BASELINE: Added summary to Milestones coded as activities.
BASELINE: Fixed 'multiple rows in a singleton record' error.
ALL: Added P3e Version 4.0 compatibility.
ALL: Improved recovery on a single report error.
UPDATE: Added Modified WBS check.
Version 1.01 (December 2003)
UPDATE: Added As-Built float check
ALL: Final Beta Corrections: First Open Release
Version 1.00: Original Beta-Test, Released 31OCT03