Sample Baseline
Checker Report - Lists Limited to First 10 Entries
SAe UPDATE CHECKER ============================ | Version 1.01 | ============================ Copyright by Ron Winter 2003 This report was prepared by Ron Winter Consulting LLC. Target Project: HwySouth Baseline 1 Analysis Date: 11-26-2003 at 4:54:05 PM Update Project: HwySouth Phase 1 - Southbound Analysis covers project status update from 25MAR02 to 25MAY02. All durations are measured in days. ========================== Administrative Checks =========================== Data Dates checked: OK. Project Dates checked: OK. --------------------------------------------------------------------------- Project Calendars Review. Added Calendars Calendar: 24/7 Workweek Schedule (non-labor) Calendar Type: Global Calendar Last Modified: 12MAY00 Work Days Sunday = Work day Work Hours: 00:00-23:59 Monday = Work day Work Hours: 00:00-23:59 Tuesday = Work day Work Hours: 00:00-23:59 Wednesday = Work day Work Hours: 00:00-23:59 Thursday = Work day Work Hours: 00:00-23:59 Friday = Work day Work Hours: 00:00-23:59 Saturday = Work day ============================= Activity Checks ============================== Target Project HwySouth Baseline 1 with 40 activities. Data Date = 25MAR02 Update Project HwySouth with 40 activities. Data Date = 25MAY02 Target Project Critical Float is 0 . Update Project Critical Float is 0 . 0 active activities have no float. 0 Actual Start Dates are mising. 0 Actual Finish Dates are mising. 0 added activities were found with fractional durations. 0 activities were found with modified fractional durations. 0 As-Built Activities were deleted. 0 In-Progress Activities were deleted. 0 Planned Activities were deleted. 0 As-Built Activities were added. 0 In-Progress Activities were added. 0 Planned Activities were added. ---------------------------------------------------------------------------- | ACTIVITIES WITH CHANGED ACTIVITY TYPES | | ACT OLD-TYPE NEW-TYPE TITLE | +----------------- -------- -------- --------------------------------------+ |P1N3225B Task Resource CONSTRUCT CONCRETE BARRIER AGAINST WAL| |P1NP100A Task Resource PROCUREMENT OF NOISE BARRIER POST & PA| ---------------------------------------------------------------------------- 2 Activity Types were changed. 0 activities have their Duration Types changed. ---------------------------------------------------------------------------- | ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS | | ACT TYPE OLD-D NEW-D TITLE | +----------------- -------- ----- ----- -----------------------------------+ |P1G100 Task 0 4 MOBILIZATION | |P1N2105B Task 186 201 INSTALL EROSION CONTROL DEVICES | ---------------------------------------------------------------------------- 2 Activity Original Durations were changed. NOTE: Original Durations may automatically change if the activity is a Level Of Effort type or if Expected Finish constraint is used. 0 Activity Types were changed. 0 activities have their Percent Complete Types changed. 0 activities have a float change greater than the update period. 0 activities have their descriptions changed. 0 activities have modified actual dates before the Target Data Date. ---------------------------------------------------------------------------- | NEW ACTUAL DATES LATER THAN UPDATE DATE (25MAY02) | | ACT START FINISH TITLE | +----------------- ------- ------- ----------------------------------------+ |P1G100 27MAY02 27MAY02 MOBILIZATION | ---------------------------------------------------------------------------- 1 activity has modified actual dates after the Update Data Date. CAUTION: The above dates are in error. Actual Dates cannot be after the data date. NOTE: Only the new, modified actual dates are listed above. A blank date may represent an unmodified actual date or one that existed earlier. 0 activities have modified actual start dates. 0 activities have modified actual finish dates. 0 active activities have no progress (0% Complete.) 0 activities have no progress this period. ---------------------------------------------------------------------------- | ACTIVITIES WITH DIMINISHING PROGRESS THIS PERIOD | | ACT T-RD U-RD T%CMP U%CMP TITLE | +----------------- ----- ----- ----- ----- --------------------------------+ |P1N2105B 186 201 0.0 0.0 INSTALL EROSION CONTROL DEVICES | ---------------------------------------------------------------------------- 1 activity has diminishing progress this period. CAUTION: There should be a definite reason why progress was negative. KEY FOR COLUMN ABBREVIATIONS: T-RD = Target Remaining Duration U-RD = Update Remaining Duration T%CMP = Target Percent Complete U%CMP = Update Percent Complete --------------------------------------------------------------------------- Activity Steps. No activities use Activity Steps. =========================== Activity Code Checks =========================== Activity Code Checks 0 activity codes were deleted. ---------------------------------------------------------------------------- | ADDED ACTIVITY CODES (ACTIVITY EXISTED EARLIER) | | ACT CATAGORY CODE-VALUE TITLE | +----------------- -------- -------------------- --------------------------+ |P1G098 CSI Code Sitework BEGIN PROJECT | |P1G098 Departme Construction Departm BEGIN PROJECT | |P1G098 Phase Foundation Construct BEGIN PROJECT | |P1G100 CSI Code Site Preparation MOBILIZATION | |P1G100 Departme Construction Departm MOBILIZATION | |P1G100 Phase Foundation Construct MOBILIZATION | |P1G100 Resp. Di Civil Engineering MOBILIZATION | |P1G105 CSI Code Site Preparation CLEAR SITE | |P1G105 Departme Construction Departm CLEAR SITE | |P1G105 Phase Foundation Construct CLEAR SITE | |P1G110 CSI Code Site Preparation GENERAL CONDITIONS | |P1G110 Departme Construction Departm GENERAL CONDITIONS | |P1G110 Phase Foundation Construct GENERAL CONDITIONS | |P1G200B CSI Code Site Preparation PROCUREMENT OF ESW/SL SIGN| |P1G200B Departme Construction Departm PROCUREMENT OF ESW/SL SIGN| |P1G200B Phase Foundation Construct PROCUREMENT OF ESW/SL SIGN| |P1N1140 CSI Code Site Preparation PLACE TEMP. MARKING TAPE | |P1N1140 Departme Construction Departm PLACE TEMP. MARKING TAPE | |P1N1140 Phase Foundation Construct PLACE TEMP. MARKING TAPE | |P1N1145 CSI Code Site Preparation PLACE TEMP. CONST. BARRIER| |P1N1145 Departme Construction Departm PLACE TEMP. CONST. BARRIER| |P1N1145 Phase Foundation Construct PLACE TEMP. CONST. BARRIER| |P1N1150 CSI Code Excavation EXCAVATE | |P1N1150 Departme Construction Departm EXCAVATE | |P1N1150 Phase Foundation Construct EXCAVATE | |P1N1170 CSI Code Excavation PLACE AGGREGATE & ASPHALT | |P1N1170 Departme Construction Departm PLACE AGGREGATE & ASPHALT | |P1N1170 Phase Foundation Construct PLACE AGGREGATE & ASPHALT | |P1N1180 CSI Code Sitework REMOVE TEMP. CONST. BARRIE| |P1N1180 Departme Construction Departm REMOVE TEMP. CONST. BARRIE| |P1N1180 Phase Foundation Construct REMOVE TEMP. CONST. BARRIE| |P1N1185 CSI Code Sitework PLACE 2 SURFACE COURSE | |P1N1185 Departme Construction Departm PLACE 2 SURFACE COURSE | |P1N1185 Phase Foundation Construct PLACE 2 SURFACE COURSE | |P1N1190 CSI Code Sitework DIVERT TRAFFIC ONTO TEMP. | |P1N1190 Departme Construction Departm DIVERT TRAFFIC ONTO TEMP. | |P1N1190 Phase Foundation Construct DIVERT TRAFFIC ONTO TEMP. | |P1N1195 CSI Code Sitework REMOVE TEMP. MARKING TAPE | |P1N1195 Departme Construction Departm REMOVE TEMP. MARKING TAPE | |P1N1195 Phase Foundation Construct REMOVE TEMP. MARKING TAPE | |P1N1200 CSI Code Sitework PLACE CONST. BARRIER & TEM| |P1N1200 Departme Construction Departm PLACE CONST. BARRIER & TEM| |P1N1200 Phase Foundation Construct PLACE CONST. BARRIER & TEM| |P1N1202 CSI Code Sitework CONSTRUCT TEMP. BENT #1 & | |P1N1202 Departme Construction Departm CONSTRUCT TEMP. BENT #1 & | |P1N1202 Phase Foundation Construct CONSTRUCT TEMP. BENT #1 & | |P1N1210 CSI Code Piped Utilities EXCAVATE RAMP & INSTALL 15| |P1N1210 Departme Construction Departm EXCAVATE RAMP & INSTALL 15| |P1N1210 Phase Foundation Construct EXCAVATE RAMP & INSTALL 15| |P1N1220 CSI Code Excavation PLACE AGGREGATE & ASPHALT | |P1N1220 Departme Construction Departm PLACE AGGREGATE & ASPHALT | |P1N1220 Phase Installation Phase PLACE AGGREGATE & ASPHALT | |P1N1230 CSI Code Excavation PLACE 2 SURFACE COURSE | |P1N1230 Departme Construction Departm PLACE 2 SURFACE COURSE | |P1N1230 Phase Installation Phase PLACE 2 SURFACE COURSE | |P1N1235 CSI Code Sitework REMOVE TEMP. CONSTR. BARRI| |P1N1235 Departme Construction Departm REMOVE TEMP. CONSTR. BARRI| |P1N1235 Phase Installation Phase REMOVE TEMP. CONSTR. BARRI| |P1N1240 CSI Code Sitework PLACE TEMP. STRIPING & DIV| |P1N1240 Departme Construction Departm PLACE TEMP. STRIPING & DIV| |P1N1240 Phase Installation Phase PLACE TEMP. STRIPING & DIV| |P1N2100 CSI Code Sitework PLACE CONST. BARRIER | |P1N2100 Departme Construction Departm PLACE CONST. BARRIER | |P1N2100 Phase Installation Phase PLACE CONST. BARRIER | |P1N2105B CSI Code Piped Utilities INSTALL EROSION CONTROL DE| |P1N2105B Departme Construction Departm INSTALL EROSION CONTROL DE| |P1N2105B Phase Installation Phase INSTALL EROSION CONTROL DE| |P1N2115A CSI Code Earthwork - Excavati GRUB & STRIP TOPSOIL | |P1N2115A Departme Construction Departm GRUB & STRIP TOPSOIL | |P1N2115A Phase Foundation Construct GRUB & STRIP TOPSOIL | |P1N2190 CSI Code Sitework INSTALL SIGN SUPPORT STRUC| |P1N2190 Departme Construction Departm INSTALL SIGN SUPPORT STRUC| |P1N2190 Phase Installation Phase INSTALL SIGN SUPPORT STRUC| |P1N2195 CSI Code Sitework ERECT SIGNS | |P1N2195 Departme Construction Departm ERECT SIGNS | |P1N2195 Phase Installation Phase ERECT SIGNS | |P1N2200 CSI Code Sitework INSTALL TEMP. SHEETING | |P1N2200 Departme Construction Departm INSTALL TEMP. SHEETING | |P1N2200 Phase Installation Phase INSTALL TEMP. SHEETING | |P1N2210 CSI Code Excavation EXCAVATE RETAINING WALL | |P1N2210 Departme Construction Departm EXCAVATE RETAINING WALL | |P1N2210 Phase Installation Phase EXCAVATE RETAINING WALL | |P1N2220 CSI Code Earthwork - Excavati CONSTRUCT FOOTING | |P1N2220 Departme Construction Departm CONSTRUCT FOOTING | |P1N2220 Phase Installation Phase CONSTRUCT FOOTING | |P1N2230 CSI Code Earthwork - Excavati CONSTRUCT RETAINING WALL | |P1N2230 Departme Construction Departm CONSTRUCT RETAINING WALL | |P1N2230 Phase Installation Phase CONSTRUCT RETAINING WALL | |P1N2240 CSI Code Earthwork - Excavati PLACE POROUS FILL BEHIND W| |P1N2240 Departme Construction Departm PLACE POROUS FILL BEHIND W| |P1N2240 Phase Installation Phase PLACE POROUS FILL BEHIND W| |P1N2250 CSI Code Earthwork - Excavati BACKFILL RETAINING WALL | |P1N2250 Departme Construction Departm BACKFILL RETAINING WALL | |P1N2250 Phase Installation Phase BACKFILL RETAINING WALL | |P1N2260 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N2260 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N2260 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N2270 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N2270 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N2270 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N2300 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N2300 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N2300 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N2320 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N2320 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N2320 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N3200 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N3200 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N3200 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N3220 CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N3220 Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N3220 Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1N3225B CSI Code Concrete CONSTRUCT CONCRETE BARRIER| |P1N3225B Departme Construction Departm CONSTRUCT CONCRETE BARRIER| |P1N3225B Phase Foundation Construct CONSTRUCT CONCRETE BARRIER| |P1NP100A CSI Code Indirect Costs PROCUREMENT OF NOISE BARRI| |P1NP100A Departme Purchasing Departmen PROCUREMENT OF NOISE BARRI| |P1NP100A Phase Installation Phase PROCUREMENT OF NOISE BARRI| |P1NP200C CSI Code Indirect Costs PROCUREMENT OF SIGN STRUCT| |P1NP200C Departme Purchasing Departmen PROCUREMENT OF SIGN STRUCT| |P1NP200C Phase Installation Phase PROCUREMENT OF SIGN STRUCT| ---------------------------------------------------------------------------- 121 activity codes were added. 0 activity codes were modified. =========================== Relationship Checks ============================ Intra-Project Relationship Checks Target Project: HwySouth Baseline 1 with 48 relationships. Update Project: HwySouth with 48 relationships. 0 relationships were deleted (activities still exist.) 0 relationships were deleted with activities. 0 relationships were newly orphaned with no successor relationships. 0 relationships were added (activities existed in both updates.) 0 relationships were added (activities existed in both updates.) 0 relationship lags were modified. ---------------------------------------------------------------------------- | ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP | | ACT TYPE FLOAT %-CMP TITLE | +----------------- -------- ----- ----- -----------------------------------+ |P1N1240 Task 392 0.0 PLACE TEMP. STRIPING & DIVERT TRAFF| |P1N2195 Task 381 0.0 ERECT SIGNS | |P1N2220 Task 0 0.0 CONSTRUCT FOOTING | |P1N2260 Task 0 0.0 CONSTRUCT CONCRETE BARRIER AGAINST | |P1N2270 Task 0 0.0 CONSTRUCT CONCRETE BARRIER AGAINST | |P1N2300 Task 0 0.0 CONSTRUCT CONCRETE BARRIER AGAINST | |P1N2320 Task 0 0.0 CONSTRUCT CONCRETE BARRIER AGAINST | |P1N3225B Resource 0 0.0 CONSTRUCT CONCRETE BARRIER AGAINST | ---------------------------------------------------------------------------- 8 activities have no finish relationships. CAUTION: The above activities are active and do not have any constraints on completion. Confirm that only Project Completion is limited by their completion or add a FS or FF relationship to the appropriate constrained activity. ============================ Constraint Checks ============================= Target Project: HwySouth Baseline 1 with 2 constraints. Update Project: HwySouth with 2 constraints. 0 Target Schedule contraint types were not recognized. 0 Update Schedule contraint types were not recognized. 0 constraints were deleted (activities still exist.) 0 constraints to deleted activities were found. 0 constraints were added to existing activities. 0 constraints were added to added activities. 0 constraints were modified. 0 constraint dates were modified. 0 Expected Finish Dates were added. 0 Expected Finish Dates were modified. 0 expired Expected Finish Dates were found. ========================== Project Expense Checks ========================== Target Project: HwySouth Baseline 1 with 5 Project Expenses. Update Project: HwySouth with 5 Project Expenses. 0 Budget Expenses were deleted. 0 Budget Expenses were added. 0 Budget Expenses were modified. TOTAL BUDGETED COST IS $ 73,600 0 Project Expenses were modified. 0 Negative Actual Expenses were found. 0 Diminishing Actual Expenses were found. 0 Actual greater then Bugeted Expenses were found. UPDATE TOTAL ACTUAL COST IS $ 61,600.00 TARGET TOTAL ACTUAL COST IS $ 61,600.00 ---------------------------------------------- CHANGE IN ACTUAL COST IS $ 0.00 TOTAL ACTUAL COST IS $ 61,600.00 ============================= Resource Checks ============================== Target Project: HwySouth Baseline 1 with 130 Task Resources. Update Project: HwySouth with 133 Task Resources. Key to Resource Types: Note: '~' = term truncated on the left. L = Labor C = Cost ---------------------------------------------------------------------------- | DELETED TASK RESOURCE BUDGETS Type | | ACT RESOURCE ROLE AMOUNT | TITLE | +----------------- -------------- -------- -------- - ---------------------+ ---------------------------------------------------------------------------- 0 Task Resourcess were deleted. ---------------------------------------------------------------------------- | ADDED TASK RESOURCE BUDGETS Type | | ACT RESOURCE ROLE AMOUNT | TITLE | +----------------- -------------- -------- -------- - ---------------------+ ---------------------------------------------------------------------------- 0 Task Resourcess were added. 0 Task Resource Budgets were modified. TOTAL BUDGETED COST IS $ 226,847 0 increasing Remaining Resources were found. TOTAL REMAINING COST IS $ 226,847 0 Activity Cost Accounts were changed. ---------------------------------------------------------------------------- | ACTIVITY RESOURCE LAG CHANGE | | ACT RESOURCE OLD L NEW L TITLE | +----------------- ---------------------- ----- ----- ---------------------+ |P1N2105B ~Highway Labor.LABOR-G 0 3 INSTALL EROSION CONTR| ---------------------------------------------------------------------------- 1 Resource Lag was changed. CAUTION: Changing the Resource Lag may change to overall duration of the actviity in a manner that is very hard to detect. ---------------------------------------------------------------------------- | ACTIVITY RESOURCE UNITS/TIMEPERIOD CHANGE | | ACT RESOURCE OLD NEW TITLE | +----------------- ---------------------- ----- ----- ---------------------+ |P1N2105B ~Highway Labor.LABOR-G 25 24 INSTALL EROSION CONTR| ---------------------------------------------------------------------------- 1 Resource Units/Timeperiod was changed. CAUTION: Changing the Resource Units/Timeperiod may change to overall duration of the activity in a manner that is very hard to detect. Verify that the work schedule has been changed correspondingly for this resource. 0 Activity Skill Levels were changed. 0 Cost Link Settings were changed. ---------------------------------------------------------------------------- | ACTIVITIES WITH CHANGED PRIMARY RESOURCES | | ACT OLD-RSOURCE NEW-RESOURCE TITLE | +----------------- ----------------- ---------------- ---------------------+ |P1N1202 (none assigned) ~ NonLabor.DOZER CONSTRUCT TEMP. BENT | |P1N1220 (none assigned) ~nLabor.SPREADER PLACE AGGREGATE & ASP| ---------------------------------------------------------------------------- 2 Activity Primary Resources were changed. NOTE: An Activity's primary resource is typically the resource that is responsible for coordinating an activity's work. Using Progress Reporter, the primary resource also updates the activity's start date, finish date, and expected end date. In addition, if an activity has any nonlabor resources, the primary resource may also be responsible for reporting the nonlabor resource's units as well. With the exception of nonlabor resources, all other resources are responsible for reporting their own hours for assigned activities. 0 Actual Start dates were changed. 0 Actual Finish dates were changed. 0 dates earlier than last update were added. 0 dates in the future were added. 0 dates were added. =============================== Memo Checks ================================ Target Project: HwySouth Baseline 1 with 1 Memos. Update Project: HwySouth with 1 Memos. 0 Memos were deleted. 0 Memos were added. 0 Memos were modified. ================================== Recap =================================== ---------------------------------------------------------------------------- | CRITICAL PATH SUMMARY REVIEW | | TARGET UPDATE TITLE/NOTES | +----------------- ----------------- --------------------------------------+ | P1G100 MOBILIZATION | |P1N1150 P1N1150 EXCAVATE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1G105 P1G105 CLEAR SITE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1G100 MOBILIZATION | | ** ORIGINAL DURATION WAS MODIFIED. **| | ** ACTUAL DATE LATER THAN DATA DATE. **| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** Added Activity Code Resp. Di **| | ** ADDED TASK LABOR RESOURCE. **| |P1G098 P1G098 BEGIN PROJECT | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1G110 P1G110 GENERAL CONDITIONS | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2100 P1N2100 PLACE CONST. BARRIER | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1185 P1N1185 PLACE 2 SURFACE COURSE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1140 P1N1140 PLACE TEMP. MARKING TAPE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1195 P1N1195 REMOVE TEMP. MARKING TAPE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| |P1N1145 P1N1145 PLACE TEMP. CONST. BARRIER | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1180 P1N1180 REMOVE TEMP. CONST. BARRIER | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1202 P1N1202 CONSTRUCT TEMP. BENT #1 & #2 | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ACTIVITY PRIMARY RESOURCE MODIFIED**| |P1N1190 P1N1190 DIVERT TRAFFIC ONTO TEMP. ROAD | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** DELETED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| |P1N1170 P1N1170 PLACE AGGREGATE & ASPHALT BASE COURSE | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N1200 P1N1200 PLACE CONST. BARRIER & TEMP. STRIPING | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| |P1N1210 P1N1210 EXCAVATE RAMP & INSTALL 15 RCP PIPE WI| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** DELETED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| | ** ADDED TASK LABOR RESOURCE. **| |P1N2115A P1N2115A GRUB & STRIP TOPSOIL | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2105B P1N2105B INSTALL EROSION CONTROL DEVICES | | ** ORIGINAL DURATION WAS MODIFIED. **| | ** DIMINISHING PROGRESS THIS PERIOD. **| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** RESOURCE LAG INCREASED BY 3 ** | | ** RESOURCE UNITS/ DECREASED BY 2** | |P1N2200 P1N2200 INSTALL TEMP. SHEETING | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2210 P1N2210 EXCAVATE RETAINING WALL | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2220 P1N2220 CONSTRUCT FOOTING | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| |P1N2230 P1N2230 CONSTRUCT RETAINING WALL | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2240 P1N2240 PLACE POROUS FILL BEHIND WALL | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2250 P1N2250 BACKFILL RETAINING WALL | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N2260 P1N2260 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| |P1N2270 P1N2270 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| |P1N2300 P1N2300 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| |P1N2320 P1N2320 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| |P1N3200 P1N3200 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N3220 P1N3220 CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| |P1N3225B P1N3225B CONSTRUCT CONCRETE BARRIER AGAINST WAL| | ** ACTIVITY TYPE WAS CHANGED. | | ** Added Activity Code CSI Code **| | ** Added Activity Code Departme **| | ** Added Activity Code Phase **| | ** ACTIVITY HAS NO FINISH RELATIONSHIP.| ---------------------------------------------------------------------------- 32 activities were found. ============================== End Of Report ===============================