Schedule Analyzer for the Enterprise

Copyright Ron Winter 2003

Sample Baseline Checker Report - Lists Limited to First 10 Entries


                            SAe UPDATE CHECKER
                       ============================
                       |        Version 1.01      |
                       ============================
                       Copyright by Ron Winter 2003

 This report was prepared by Ron Winter Consulting LLC.

 Target Project: HwySouth Baseline 1               Analysis Date: 11-26-2003 at 4:54:05 PM 
 Update Project: HwySouth

  Phase 1 - Southbound
 
 Analysis covers project status update from 25MAR02 to 25MAY02.
 All durations are measured in days.

========================== Administrative Checks ===========================
Data Dates checked: OK.
Project Dates checked: OK.
 ---------------------------------------------------------------------------
Project Calendars Review. 

Added Calendars

        Calendar: 24/7 Workweek Schedule (non-labor)
        Calendar Type: Global Calendar
            Last Modified: 12MAY00
            Work Days
                Sunday = Work day
                    Work Hours: 00:00-23:59
                Monday = Work day
                    Work Hours: 00:00-23:59
                Tuesday = Work day
                    Work Hours: 00:00-23:59
                Wednesday = Work day
                    Work Hours: 00:00-23:59
                Thursday = Work day
                    Work Hours: 00:00-23:59
                Friday = Work day
                    Work Hours: 00:00-23:59
                Saturday = Work day

============================= Activity Checks ==============================

 Target Project HwySouth Baseline 1 with 40 activities.  Data Date = 25MAR02
 Update Project HwySouth with 40 activities.  Data Date = 25MAY02

 Target Project Critical Float is  0 .
 Update Project Critical Float is  0 .

 0 active activities have no float.
 0 Actual Start Dates are mising.
 0 Actual Finish Dates are mising.
 0 added activities were found with fractional durations.
 0 activities were found with modified fractional durations.
 0 As-Built Activities were deleted.
 0 In-Progress Activities were deleted.
 0 Planned Activities were deleted.
 0 As-Built Activities were added.
 0 In-Progress Activities were added.
 0 Planned Activities were added.

----------------------------------------------------------------------------
| ACTIVITIES WITH CHANGED ACTIVITY TYPES                                   |
| ACT              OLD-TYPE NEW-TYPE TITLE                                 |
+----------------- -------- -------- --------------------------------------+
|P1N3225B          Task     Resource CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|P1NP100A          Task     Resource PROCUREMENT OF NOISE BARRIER POST & PA|
----------------------------------------------------------------------------
 2 Activity Types were changed.
 0 activities have their Duration Types changed.

----------------------------------------------------------------------------
| ACTIVITIES WITH MODIFIED ORIGINAL DURATIONS                              |
| ACT              TYPE     OLD-D NEW-D TITLE                              |
+----------------- -------- ----- ----- -----------------------------------+
|P1G100            Task         0     4 MOBILIZATION                       |
|P1N2105B          Task       186   201 INSTALL EROSION CONTROL DEVICES    |
----------------------------------------------------------------------------
 2 Activity Original Durations were changed.
    NOTE: Original Durations may automatically change if the activity is a
        Level Of Effort type or if Expected Finish constraint is used.
 0 Activity Types were changed.
 0 activities have their Percent Complete Types changed.
 0 activities have a float change greater than the update period.
 0 activities have their descriptions changed.
 0 activities have modified actual dates before the Target Data Date.

----------------------------------------------------------------------------
| NEW ACTUAL DATES LATER THAN UPDATE DATE (25MAY02)                        |
| ACT              START   FINISH  TITLE                                   |
+----------------- ------- ------- ----------------------------------------+
|P1G100            27MAY02 27MAY02 MOBILIZATION                            |
----------------------------------------------------------------------------
 1 activity has modified actual dates after the Update Data Date.
    CAUTION: The above dates are in error.  Actual Dates cannot be after the
        data date.
    NOTE: Only the new, modified actual dates are listed above.  A blank date
        may represent an unmodified actual date or one that existed earlier.
 0 activities have modified actual start dates.
 0 activities have modified actual finish dates.
 0 active activities have no progress (0% Complete.)
 0 activities have no progress this period.

----------------------------------------------------------------------------
| ACTIVITIES WITH DIMINISHING PROGRESS THIS PERIOD                         |
| ACT               T-RD  U-RD T%CMP U%CMP TITLE                           |
+----------------- ----- ----- ----- ----- --------------------------------+
|P1N2105B            186   201   0.0   0.0 INSTALL EROSION CONTROL DEVICES |
----------------------------------------------------------------------------
 1 activity has diminishing progress this period.
    CAUTION: There should be a definite reason why progress was negative.
    KEY FOR COLUMN ABBREVIATIONS:
        T-RD  = Target Remaining Duration
        U-RD  = Update Remaining Duration
        T%CMP = Target Percent Complete
        U%CMP = Update Percent Complete

 ---------------------------------------------------------------------------
Activity Steps. 

    No activities use Activity Steps.

=========================== Activity Code Checks ===========================

Activity Code Checks 
 0 activity codes were deleted.

----------------------------------------------------------------------------
| ADDED ACTIVITY CODES (ACTIVITY EXISTED EARLIER)                          |
| ACT              CATAGORY CODE-VALUE           TITLE                     |
+----------------- -------- -------------------- --------------------------+
|P1G098            CSI Code Sitework             BEGIN PROJECT             |
|P1G098            Departme Construction Departm BEGIN PROJECT             |
|P1G098            Phase    Foundation Construct BEGIN PROJECT             |
|P1G100            CSI Code Site Preparation     MOBILIZATION              |
|P1G100            Departme Construction Departm MOBILIZATION              |
|P1G100            Phase    Foundation Construct MOBILIZATION              |
|P1G100            Resp. Di Civil Engineering    MOBILIZATION              |
|P1G105            CSI Code Site Preparation     CLEAR SITE                |
|P1G105            Departme Construction Departm CLEAR SITE                |
|P1G105            Phase    Foundation Construct CLEAR SITE                |
|P1G110            CSI Code Site Preparation     GENERAL CONDITIONS        |
|P1G110            Departme Construction Departm GENERAL CONDITIONS        |
|P1G110            Phase    Foundation Construct GENERAL CONDITIONS        |
|P1G200B           CSI Code Site Preparation     PROCUREMENT OF ESW/SL SIGN|
|P1G200B           Departme Construction Departm PROCUREMENT OF ESW/SL SIGN|
|P1G200B           Phase    Foundation Construct PROCUREMENT OF ESW/SL SIGN|
|P1N1140           CSI Code Site Preparation     PLACE TEMP. MARKING TAPE  |
|P1N1140           Departme Construction Departm PLACE TEMP. MARKING TAPE  |
|P1N1140           Phase    Foundation Construct PLACE TEMP. MARKING TAPE  |
|P1N1145           CSI Code Site Preparation     PLACE TEMP. CONST. BARRIER|
|P1N1145           Departme Construction Departm PLACE TEMP. CONST. BARRIER|
|P1N1145           Phase    Foundation Construct PLACE TEMP. CONST. BARRIER|
|P1N1150           CSI Code Excavation           EXCAVATE                  |
|P1N1150           Departme Construction Departm EXCAVATE                  |
|P1N1150           Phase    Foundation Construct EXCAVATE                  |
|P1N1170           CSI Code Excavation           PLACE AGGREGATE & ASPHALT |
|P1N1170           Departme Construction Departm PLACE AGGREGATE & ASPHALT |
|P1N1170           Phase    Foundation Construct PLACE AGGREGATE & ASPHALT |
|P1N1180           CSI Code Sitework             REMOVE TEMP. CONST. BARRIE|
|P1N1180           Departme Construction Departm REMOVE TEMP. CONST. BARRIE|
|P1N1180           Phase    Foundation Construct REMOVE TEMP. CONST. BARRIE|
|P1N1185           CSI Code Sitework             PLACE 2 SURFACE COURSE    |
|P1N1185           Departme Construction Departm PLACE 2 SURFACE COURSE    |
|P1N1185           Phase    Foundation Construct PLACE 2 SURFACE COURSE    |
|P1N1190           CSI Code Sitework             DIVERT TRAFFIC ONTO TEMP. |
|P1N1190           Departme Construction Departm DIVERT TRAFFIC ONTO TEMP. |
|P1N1190           Phase    Foundation Construct DIVERT TRAFFIC ONTO TEMP. |
|P1N1195           CSI Code Sitework             REMOVE TEMP. MARKING TAPE |
|P1N1195           Departme Construction Departm REMOVE TEMP. MARKING TAPE |
|P1N1195           Phase    Foundation Construct REMOVE TEMP. MARKING TAPE |
|P1N1200           CSI Code Sitework             PLACE CONST. BARRIER & TEM|
|P1N1200           Departme Construction Departm PLACE CONST. BARRIER & TEM|
|P1N1200           Phase    Foundation Construct PLACE CONST. BARRIER & TEM|
|P1N1202           CSI Code Sitework             CONSTRUCT TEMP. BENT #1 & |
|P1N1202           Departme Construction Departm CONSTRUCT TEMP. BENT #1 & |
|P1N1202           Phase    Foundation Construct CONSTRUCT TEMP. BENT #1 & |
|P1N1210           CSI Code Piped Utilities      EXCAVATE RAMP & INSTALL 15|
|P1N1210           Departme Construction Departm EXCAVATE RAMP & INSTALL 15|
|P1N1210           Phase    Foundation Construct EXCAVATE RAMP & INSTALL 15|
|P1N1220           CSI Code Excavation           PLACE AGGREGATE & ASPHALT |
|P1N1220           Departme Construction Departm PLACE AGGREGATE & ASPHALT |
|P1N1220           Phase    Installation Phase   PLACE AGGREGATE & ASPHALT |
|P1N1230           CSI Code Excavation           PLACE 2 SURFACE COURSE    |
|P1N1230           Departme Construction Departm PLACE 2 SURFACE COURSE    |
|P1N1230           Phase    Installation Phase   PLACE 2 SURFACE COURSE    |
|P1N1235           CSI Code Sitework             REMOVE TEMP. CONSTR. BARRI|
|P1N1235           Departme Construction Departm REMOVE TEMP. CONSTR. BARRI|
|P1N1235           Phase    Installation Phase   REMOVE TEMP. CONSTR. BARRI|
|P1N1240           CSI Code Sitework             PLACE TEMP. STRIPING & DIV|
|P1N1240           Departme Construction Departm PLACE TEMP. STRIPING & DIV|
|P1N1240           Phase    Installation Phase   PLACE TEMP. STRIPING & DIV|
|P1N2100           CSI Code Sitework             PLACE CONST. BARRIER      |
|P1N2100           Departme Construction Departm PLACE CONST. BARRIER      |
|P1N2100           Phase    Installation Phase   PLACE CONST. BARRIER      |
|P1N2105B          CSI Code Piped Utilities      INSTALL EROSION CONTROL DE|
|P1N2105B          Departme Construction Departm INSTALL EROSION CONTROL DE|
|P1N2105B          Phase    Installation Phase   INSTALL EROSION CONTROL DE|
|P1N2115A          CSI Code Earthwork - Excavati GRUB & STRIP TOPSOIL      |
|P1N2115A          Departme Construction Departm GRUB & STRIP TOPSOIL      |
|P1N2115A          Phase    Foundation Construct GRUB & STRIP TOPSOIL      |
|P1N2190           CSI Code Sitework             INSTALL SIGN SUPPORT STRUC|
|P1N2190           Departme Construction Departm INSTALL SIGN SUPPORT STRUC|
|P1N2190           Phase    Installation Phase   INSTALL SIGN SUPPORT STRUC|
|P1N2195           CSI Code Sitework             ERECT SIGNS               |
|P1N2195           Departme Construction Departm ERECT SIGNS               |
|P1N2195           Phase    Installation Phase   ERECT SIGNS               |
|P1N2200           CSI Code Sitework             INSTALL TEMP. SHEETING    |
|P1N2200           Departme Construction Departm INSTALL TEMP. SHEETING    |
|P1N2200           Phase    Installation Phase   INSTALL TEMP. SHEETING    |
|P1N2210           CSI Code Excavation           EXCAVATE RETAINING WALL   |
|P1N2210           Departme Construction Departm EXCAVATE RETAINING WALL   |
|P1N2210           Phase    Installation Phase   EXCAVATE RETAINING WALL   |
|P1N2220           CSI Code Earthwork - Excavati CONSTRUCT FOOTING         |
|P1N2220           Departme Construction Departm CONSTRUCT FOOTING         |
|P1N2220           Phase    Installation Phase   CONSTRUCT FOOTING         |
|P1N2230           CSI Code Earthwork - Excavati CONSTRUCT RETAINING WALL  |
|P1N2230           Departme Construction Departm CONSTRUCT RETAINING WALL  |
|P1N2230           Phase    Installation Phase   CONSTRUCT RETAINING WALL  |
|P1N2240           CSI Code Earthwork - Excavati PLACE POROUS FILL BEHIND W|
|P1N2240           Departme Construction Departm PLACE POROUS FILL BEHIND W|
|P1N2240           Phase    Installation Phase   PLACE POROUS FILL BEHIND W|
|P1N2250           CSI Code Earthwork - Excavati BACKFILL RETAINING WALL   |
|P1N2250           Departme Construction Departm BACKFILL RETAINING WALL   |
|P1N2250           Phase    Installation Phase   BACKFILL RETAINING WALL   |
|P1N2260           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N2260           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N2260           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N2270           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N2270           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N2270           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N2300           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N2300           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N2300           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N2320           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N2320           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N2320           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N3200           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N3200           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N3200           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N3220           CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N3220           Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N3220           Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1N3225B          CSI Code Concrete             CONSTRUCT CONCRETE BARRIER|
|P1N3225B          Departme Construction Departm CONSTRUCT CONCRETE BARRIER|
|P1N3225B          Phase    Foundation Construct CONSTRUCT CONCRETE BARRIER|
|P1NP100A          CSI Code Indirect Costs       PROCUREMENT OF NOISE BARRI|
|P1NP100A          Departme Purchasing Departmen PROCUREMENT OF NOISE BARRI|
|P1NP100A          Phase    Installation Phase   PROCUREMENT OF NOISE BARRI|
|P1NP200C          CSI Code Indirect Costs       PROCUREMENT OF SIGN STRUCT|
|P1NP200C          Departme Purchasing Departmen PROCUREMENT OF SIGN STRUCT|
|P1NP200C          Phase    Installation Phase   PROCUREMENT OF SIGN STRUCT|
----------------------------------------------------------------------------
 121 activity codes were added.
 0 activity codes were modified.

=========================== Relationship Checks ============================

Intra-Project Relationship Checks 

 Target Project: HwySouth Baseline 1 with 48 relationships.
 Update Project: HwySouth with 48 relationships.

 0 relationships were deleted (activities still exist.)
 0 relationships were deleted with activities.
 0 relationships were newly orphaned with no successor relationships.
 0 relationships were added (activities existed in both updates.)
 0 relationships were added (activities existed in both updates.)
 0 relationship lags were modified.

----------------------------------------------------------------------------
| ACTIVE ACTIVITIES WITHOUT A FINISH RELATIONSHIP                          |
| ACT              TYPE     FLOAT %-CMP TITLE                              |
+----------------- -------- ----- ----- -----------------------------------+
|P1N1240           Task       392   0.0 PLACE TEMP. STRIPING & DIVERT TRAFF|
|P1N2195           Task       381   0.0 ERECT SIGNS                        |
|P1N2220           Task         0   0.0 CONSTRUCT FOOTING                  |
|P1N2260           Task         0   0.0 CONSTRUCT CONCRETE BARRIER AGAINST |
|P1N2270           Task         0   0.0 CONSTRUCT CONCRETE BARRIER AGAINST |
|P1N2300           Task         0   0.0 CONSTRUCT CONCRETE BARRIER AGAINST |
|P1N2320           Task         0   0.0 CONSTRUCT CONCRETE BARRIER AGAINST |
|P1N3225B          Resource     0   0.0 CONSTRUCT CONCRETE BARRIER AGAINST |
----------------------------------------------------------------------------
 8 activities have no finish relationships.
    CAUTION: The above activities are active and do not have any constraints
        on completion.  Confirm that only Project Completion is limited by
        their completion or add a FS or FF relationship to the appropriate
        constrained activity.

============================ Constraint Checks =============================

 Target Project: HwySouth Baseline 1 with 2 constraints.
 Update Project: HwySouth with 2 constraints.

 0 Target Schedule contraint types were not recognized.
 0 Update Schedule contraint types were not recognized.
 0 constraints were deleted (activities still exist.)
 0 constraints to deleted activities were found.
 0 constraints were added to existing activities.
 0 constraints were added to added activities.
 0 constraints were modified.
 0 constraint dates were modified.
 0 Expected Finish Dates were added.
 0 Expected Finish Dates were modified.
 0 expired Expected Finish Dates were found.

========================== Project Expense Checks ==========================

 Target Project: HwySouth Baseline 1 with 5 Project Expenses.
 Update Project: HwySouth with 5 Project Expenses.

 0 Budget Expenses were deleted.
 0 Budget Expenses were added.
 0 Budget Expenses were modified.


         TOTAL BUDGETED COST IS      $           73,600

 0 Project Expenses were modified.
 0 Negative Actual Expenses were found.
 0 Diminishing Actual Expenses were found.
 0 Actual greater then Bugeted Expenses were found.

         UPDATE TOTAL ACTUAL COST IS $        61,600.00
         TARGET TOTAL ACTUAL COST IS $        61,600.00
         ----------------------------------------------
         CHANGE IN ACTUAL COST IS    $             0.00

         TOTAL ACTUAL COST IS        $        61,600.00


============================= Resource Checks ==============================

 Target Project: HwySouth Baseline 1 with 130 Task Resources.
 Update Project: HwySouth with 133 Task Resources.

 Key to Resource Types:              Note: '~' = term truncated on the left.
    L = Labor
    C = Cost

----------------------------------------------------------------------------
| DELETED TASK RESOURCE BUDGETS                     Type                   |
| ACT              RESOURCE       ROLE       AMOUNT | TITLE                |
+----------------- -------------- -------- -------- - ---------------------+
----------------------------------------------------------------------------
 0 Task Resourcess were deleted.

----------------------------------------------------------------------------
| ADDED TASK RESOURCE BUDGETS                       Type                   |
| ACT              RESOURCE       ROLE       AMOUNT | TITLE                |
+----------------- -------------- -------- -------- - ---------------------+
----------------------------------------------------------------------------
 0 Task Resourcess were added.
 0 Task Resource Budgets were modified.

         TOTAL BUDGETED COST IS        $          226,847

 0 increasing Remaining Resources were found.
         TOTAL REMAINING COST IS       $          226,847

 0 Activity Cost Accounts were changed.

----------------------------------------------------------------------------
| ACTIVITY RESOURCE LAG CHANGE                                             |
| ACT              RESOURCE               OLD L NEW L TITLE                |
+----------------- ---------------------- ----- ----- ---------------------+
|P1N2105B          ~Highway Labor.LABOR-G     0     3 INSTALL EROSION CONTR|
----------------------------------------------------------------------------
 1 Resource Lag was changed.
    CAUTION: Changing the Resource Lag may change to overall duration of the
        actviity in a manner that is very hard to detect.

----------------------------------------------------------------------------
| ACTIVITY RESOURCE UNITS/TIMEPERIOD CHANGE                                |
| ACT              RESOURCE                 OLD   NEW TITLE                |
+----------------- ---------------------- ----- ----- ---------------------+
|P1N2105B          ~Highway Labor.LABOR-G    25    24 INSTALL EROSION CONTR|
----------------------------------------------------------------------------
 1 Resource Units/Timeperiod was changed.
    CAUTION: Changing the Resource Units/Timeperiod may change to overall
        duration of the activity in a manner that is very hard to detect.
        Verify that the work schedule has been changed correspondingly for
        this resource.
 0 Activity Skill Levels were changed.
 0 Cost Link Settings were changed.

----------------------------------------------------------------------------
| ACTIVITIES WITH CHANGED PRIMARY RESOURCES                                |
| ACT              OLD-RSOURCE       NEW-RESOURCE     TITLE                |
+----------------- ----------------- ---------------- ---------------------+
|P1N1202           (none assigned)   ~ NonLabor.DOZER CONSTRUCT TEMP. BENT |
|P1N1220           (none assigned)   ~nLabor.SPREADER PLACE AGGREGATE & ASP|
----------------------------------------------------------------------------
 2 Activity Primary Resources were changed.
    NOTE: An Activity's primary resource is typically the resource that is
        responsible for coordinating an activity's work. Using Progress
        Reporter, the primary resource also updates the activity's start 
        date, finish date, and expected end date. In addition, if an 
        activity has any nonlabor resources, the primary resource may also
        be responsible for reporting the nonlabor resource's units as well.
        With the exception of nonlabor resources, all other resources are 
        responsible for reporting their own hours for assigned activities.
 0 Actual Start dates were changed.
 0 Actual Finish dates were changed.
 0 dates earlier than last update were added.
 0 dates in the future were added.
 0 dates were added.

=============================== Memo Checks ================================

 Target Project: HwySouth Baseline 1 with 1 Memos.
 Update Project: HwySouth with 1 Memos.

 0 Memos were deleted.
 0 Memos were added.
 0 Memos were modified.

================================== Recap ===================================

----------------------------------------------------------------------------
| CRITICAL PATH SUMMARY REVIEW                                             |
| TARGET           UPDATE            TITLE/NOTES                           |
+----------------- ----------------- --------------------------------------+
|                  P1G100            MOBILIZATION                          |
|P1N1150           P1N1150           EXCAVATE                              |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1G105            P1G105            CLEAR SITE                            |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1G100                              MOBILIZATION                          |
|                                   ** ORIGINAL DURATION WAS MODIFIED.   **|
|                                   ** ACTUAL DATE LATER THAN DATA DATE. **|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** Added Activity Code Resp. Di      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|P1G098            P1G098            BEGIN PROJECT                         |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1G110            P1G110            GENERAL CONDITIONS                    |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2100           P1N2100           PLACE CONST. BARRIER                  |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1185           P1N1185           PLACE 2 SURFACE COURSE                |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1140           P1N1140           PLACE TEMP. MARKING TAPE              |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1195           P1N1195           REMOVE TEMP. MARKING TAPE             |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|P1N1145           P1N1145           PLACE TEMP. CONST. BARRIER            |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1180           P1N1180           REMOVE TEMP. CONST. BARRIER           |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1202           P1N1202           CONSTRUCT TEMP. BENT #1 & #2          |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ACTIVITY PRIMARY RESOURCE MODIFIED**|
|P1N1190           P1N1190           DIVERT TRAFFIC ONTO TEMP. ROAD        |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|P1N1170           P1N1170           PLACE AGGREGATE & ASPHALT BASE COURSE |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N1200           P1N1200           PLACE CONST. BARRIER & TEMP. STRIPING |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|P1N1210           P1N1210           EXCAVATE RAMP & INSTALL 15 RCP PIPE WI|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** DELETED TASK LABOR RESOURCE.      **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|                                   ** ADDED TASK LABOR RESOURCE.        **|
|P1N2115A          P1N2115A          GRUB & STRIP TOPSOIL                  |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2105B          P1N2105B          INSTALL EROSION CONTROL DEVICES       |
|                                   ** ORIGINAL DURATION WAS MODIFIED.   **|
|                                   ** DIMINISHING PROGRESS THIS PERIOD. **|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** RESOURCE LAG INCREASED BY 3   **    |
|                                   ** RESOURCE UNITS/ DECREASED BY 2**    |
|P1N2200           P1N2200           INSTALL TEMP. SHEETING                |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2210           P1N2210           EXCAVATE RETAINING WALL               |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2220           P1N2220           CONSTRUCT FOOTING                     |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
|P1N2230           P1N2230           CONSTRUCT RETAINING WALL              |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2240           P1N2240           PLACE POROUS FILL BEHIND WALL         |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2250           P1N2250           BACKFILL RETAINING WALL               |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N2260           P1N2260           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
|P1N2270           P1N2270           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
|P1N2300           P1N2300           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
|P1N2320           P1N2320           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
|P1N3200           P1N3200           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N3220           P1N3220           CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|P1N3225B          P1N3225B          CONSTRUCT CONCRETE BARRIER AGAINST WAL|
|                                   ** ACTIVITY TYPE WAS CHANGED.          |
|                                   ** Added Activity Code CSI Code      **|
|                                   ** Added Activity Code Departme      **|
|                                   ** Added Activity Code Phase         **|
|                                   ** ACTIVITY HAS NO FINISH RELATIONSHIP.|
----------------------------------------------------------------------------
 32 activities were found.
============================== End Of Report ===============================

Return to SAe Overview.