SAe RELATED SCHEDULES ============================ | Version 1.15 | ============================ Copyright(c) Ron Winter Consulting 2006-2012 Project: HwySouth, Phase 1 - Southbound Analysis Date: 07-26-2012 at 12:07:07 ============================================================================ The following projects and relationships are SUCCESSORS to Project HwySouth. Project (Baseline Schedule): HwyNorth - B2, Phase 2 - Northbound - Update April 2007 Predecessor Activity P1G110, GENERAL CONDITIONS Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B3, Phase 2 - Northbound - Update May 2007 Predecessor Activity P1G110, GENERAL CONDITIONS Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B4, Phase 2 - Northbound - Update June 2007 Predecessor Activity P1G110, GENERAL CONDITIONS Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B1, Phase 2 - Northbound - Original Baseline Predecessor Activity P1G110, GENERAL CONDITIONS Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project HwyNorth, Phase 2 - Northbound Predecessor Activity P1G110, GENERAL CONDITIONS Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B4, Phase 2 - Northbound - Update June 2007 Predecessor Activity P1N2210, EXCAVATE RETAINING WALL Successor Activity P2N2115B, REMOVE GUIDE RAIL: FS(0) Project HwyNorth, Phase 2 - Northbound Predecessor Activity P1N2210, EXCAVATE RETAINING WALL Successor Activity P2N2115B, REMOVE GUIDE RAIL: FS(0) Project (Baseline Schedule): HwyNorth - B1, Phase 2 - Northbound - Original Baseline Predecessor Activity P1N2210, EXCAVATE RETAINING WALL Successor Activity P2N2115B, REMOVE GUIDE RAIL: FS(0) Project (Baseline Schedule): HwyNorth - B2, Phase 2 - Northbound - Update April 2007 Predecessor Activity P1N2210, EXCAVATE RETAINING WALL Successor Activity P2N2115B, REMOVE GUIDE RAIL: FS(0) Project (Baseline Schedule): HwyNorth - B3, Phase 2 - Northbound - Update May 2007 Predecessor Activity P1N2210, EXCAVATE RETAINING WALL Successor Activity P2N2115B, REMOVE GUIDE RAIL: FS(0) Project (Baseline Schedule): HwyNorth - B4, Phase 2 - Northbound - Update June 2007 Predecessor Activity P1N3225B, CONSTRUCT CONCRETE BARRIER AGAINST WALL Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B3, Phase 2 - Northbound - Update May 2007 Predecessor Activity P1N3225B, CONSTRUCT CONCRETE BARRIER AGAINST WALL Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B2, Phase 2 - Northbound - Update April 2007 Predecessor Activity P1N3225B, CONSTRUCT CONCRETE BARRIER AGAINST WALL Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project (Baseline Schedule): HwyNorth - B1, Phase 2 - Northbound - Original Baseline Predecessor Activity P1N3225B, CONSTRUCT CONCRETE BARRIER AGAINST WALL Successor Activity P2G600, PROJECT COMPLETE: FS(0) Project HwyNorth, Phase 2 - Northbound Predecessor Activity P1N3225B, CONSTRUCT CONCRETE BARRIER AGAINST WALL Successor Activity P2G600, PROJECT COMPLETE: FS(0) 15 external relationships exist. This will cause problems with your schedule export showing different dates unless all related schedules are exported as a group. CAUTION: Some of your relationships involve Baseline Schedules. It is very odd to have active schedules related to 'inactive' Baseline Schedules. P6 does not list these relationships in the reports. Look for '(Baseline Schedule):' above to spot them. ---------------------------------------------------------------------------- The following RESOURCES are shared with Project HwySouth. Key: Project Resource, Number of Activities Project Bldg, Office Building Addition Finisher, # Acts = 5 Truck Crane, # Acts = 1 Project HwyNorth, Phase 2 - Northbound Asphalt Paver, 130 H.P., # Acts = 2 Foreman, # Acts = 15 Truck Driver - Heavy, # Acts = 1 General Laborer, # Acts = 5 Skilled Laborer, # Acts = 2 Equipment Operator - Light, # Acts = 1 Equipment Operator, # Acts = 11 Loader/Backhoe 80 H.P., # Acts = 8 Aggregate Spreader, # Acts = 1 Roller, Tandem, # Acts = 1 Roller, Steel Wheel, # Acts = 3 Truck - Flatbed, 3 Ton, # Acts = 1 Truck Crane, # Acts = 4 Dozer, 200 H.P., # Acts = 2 63 activities share resources with Project HwySouth This can pose a portability issue if resource leveling is being used. ---------------------------------------------------------------------------- The following BASE CALENDARS are shared with Project HwySouth. Key: Project Calendar, Number of Activities Project Lincoln Hospital, Lincoln Hospital Project Rehab Center Standard 5 Day Workweek, # Acts = 79 Project Proposed Project C-1, Tanqueray Heights Luxury Condominiums Standard 5 Day Workweek, # Acts = 110 Project Proposed Project HC1, Hampton Gardens Senior Communities (Design, Bid, Build) Standard 5 Day Workweek, # Acts = 126 Project Lofty Heights, 9 Pacific Drive - Lofty Heights Standard 5 Day Workweek, # Acts = 85 Project Bldg, Office Building Addition Standard 5 Day Workweek, # Acts = 19 Project DsgnAEB1000, Design for model AEB1000 S.R.S. Standard 5 Day Workweek, # Acts = 57 Project HwyNorth, Phase 2 - Northbound Standard 5 Day Workweek, # Acts = 16 Project Auto, Automated System Standard 5 Day Workweek, # Acts = 8 Project T&EInst, Tooling & Equipment Installation Standard 5 Day Workweek, # Acts = 14 Project Conv, Conveyor System Standard 5 Day Workweek, # Acts = 7 Project Architectural Design, Architectural Design Template for Mid Rise Commercial Office Standard 5 Day Workweek, # Acts = 57 Project PMA-GMP 6 -11, Pima Plant Upgrade GMP 6 100% - August Billing (19-AUG-11) Standard 5 Day Workweek, # Acts = 15 Project PMA-GMP 6-10, Pima Plant Upgrade GMP 6 100% - July Billing (22-JULY-11) Standard 5 Day Workweek, # Acts = 15 Project PMA-GMP 6-14, Pima Plant Upgrade GMP 6 100% - November Billing (25-NOV-11) Standard 5 Day Workweek, # Acts = 82 Project PMA-GMP 6 -13, Pima Plant Upgrade GMP 6 100% - October Billing (21-OCT-11) Standard 5 Day Workweek, # Acts = 83 Project PMA-GMP 6 -12, Pima Plant Upgrade GMP 6 100% - September Billing Final (23-SEPT-11) Standard 5 Day Workweek, # Acts = 15 788 activities share calendars with Project HwySouth Note: The default import option is to not update the calendar with new holiday data. This can leave the imported schedule with different holidays than the original schedule, causing dates to be different. The following RESOURCE CALENDARS are shared with Project HwySouth. Key: Project Resource Calendar, Number of Activitiy Resourcess Project Lincoln Hospital, Lincoln Hospital Project Rehab Center Standard 5 Day Workweek, # Acts = 25 Project Lofty Heights, 9 Pacific Drive - Lofty Heights Standard 5 Day Workweek, # Acts = 81 Project Bldg, Office Building Addition Standard 5 Day Workweek, # Acts = 80 Project HwyNorth, Phase 2 - Northbound Standard 5 Day Workweek, # Acts = 62 Project Auto, Automated System Standard 5 Day Workweek, # Acts = 65 Project Conv, Conveyor System Standard 5 Day Workweek, # Acts = 22 Project BL05, Ames TH 13 / 101 Baseline Schedule Revision 03 - Update 05 Standard 5 Day Workweek, # Acts = 262 Project BL07, Ames TH 13 / 101 Baseline Schedule Revision 03 - Update 07 Standard 5 Day Workweek, # Acts = 261 Project WC07, Consolidated Rental Car Facility (CRFC) - Update 07 (03-2-12) Standard 5 Day Workweek, # Acts = 1153 Project WC08, Consolidated Rental Car Facility (CRFC) - Update 08 (04-2-12) Standard 5 Day Workweek, # Acts = 1163 Project J2081-8, CDRP-Update Project Schedule ,Rev.01 Standard 5 Day Workweek, # Acts = 1842 Project J2081--1, CDR-Revised Project Schedule, Plan 4 - Submitted Standard 5 Day Workweek, # Acts = 1841 Project A033, A033 USAMRIID W912DR-09-C-0026 Standard 5 Day Workweek, # Acts = 1007 Project A034, A034 USAMRIID W912DR-09-C-0026 Standard 5 Day Workweek, # Acts = 1007 Project Scott-1, 12_04_2B_Update_6.2 Standard 5 Day Workweek, # Acts = 233 Project Scott-2, 12_05_2B_Update_6.2 Standard 5 Day Workweek, # Acts = 233 9337 activities share resource calendars with Project HwySouth Resource calendars are only important if you have resource-dependent activity durations. Note: The default import option is to not update the calendar with new holiday data. This can leave the imported schedule with different holidays than the original schedule, causing dates to be different. ---------------------------------------------------------------------------- The following documents are referenced by Project HwySouth. Cast in place concrete quote, revised on 28FEB03 Location: C:\Program Files\Primavera P3ec for Construction\Project M anager\Documents\Cast in Place Concrete Quote.htm Crane Equipment, revised on 28FEB03 Location: C:\Program Files\Primavera P3ec for Construction\Project M anager\Documents\Crane.bmp Specification, revised on 28FEB03 Location: C:\Program Files\Primavera P3ec for Construction\Project M anager\Documents\Specifications.doc 3 documents are referenced by this project and will not be exported.