SAe COMPARE P3 to P6 ============================ | Version 1.15 | ============================ Copyright© Ron Winter Consulting LLC 2012 NAME VERSION PROJECT TITLE ---- ---------------- ------------------------------------ P3 Schedule: 1911 DD: 9/1/01 Preliminary Aug01 Status - rec'd 9/7 P6 Schedule: 1911 Typical School Building =============================== PROJECT DATA =============================== Start Dates check. P3 Finish Date changed from 14JAN02 to 23JAN02. P3 Data Date changed from 01SEP01 to 13DEC99. All calendars are accounted for. All calendar standard working days match. Holidays in the P3 Calendar 1 are not found in the P6 Calendar 1911 - 1 - 5 DAY W/ HOLIDAY Missing P3 Calendar 1 Holidays: 1JAN00 1JAN05 1JAN06 1JAN10 4JUL99 4JUL04 4JUL09 4JUL10 25DEC98 25DEC99 25DEC04 25DEC05 25DEC10 Holidays in the P6 Calendar 1911 - 1 - 5 DAY W/ HOLIDAY are not found in the P3 Calendar 1 Missing P3 Calendar 1 Holidays: 31DEC99 31DEC04 02JAN06 05JUL99 05JUL04 03JUL09 24DEC99 24DEC04 26DEC05 24APR99 25APR99 Complete listing of all calendar holidays: P3 Calendar 1 Holidays: 01JAN99 01JAN00 01JAN01 01JAN02 01JAN03 01JAN04 01JAN05 01JAN06 01JAN07 01JAN08 01JAN09 01JAN10 04JUL99 04JUL00 04JUL01 04JUL02 04JUL03 04JUL04 04JUL05 04JUL06 04JUL07 04JUL08 04JUL09 04JUL10 25DEC98 25DEC99 25DEC00 25DEC01 25DEC02 25DEC03 25DEC04 25DEC05 25DEC06 25DEC07 25DEC08 25DEC09 25DEC10 24NOV94 25NOV94 29MAY95 04SEP95 23NOV95 24NOV95 27MAY96 02SEP96 28NOV96 29NOV96 26MAY97 01SEP97 27NOV97 28NOV97 25MAY98 07SEP98 26NOV98 27NOV98 31MAY99 06SEP99 25NOV99 26NOV99 18FEB00 29MAY00 03JUL00 04SEP00 23NOV00 24NOV00 28MAY01 03SEP01 22NOV01 23NOV01 24DEC01 31DEC01 15FEB02 24MAY02 27MAY02 05JUL02 30AUG02 02SEP02 28NOV02 29NOV02 14FEB03 23MAY03 26MAY03 29AUG03 01SEP03 27NOV03 28NOV03 26DEC03 02JAN04 28MAY04 31MAY04 P6 Calendar 1911 - 1 - 5 DAY W/ HOLIDAY Holidays: 01JAN99 31DEC99 01JAN01 01JAN02 01JAN03 01JAN04 31DEC04 02JAN06 01JAN07 01JAN08 01JAN09 05JUL99 04JUL00 04JUL01 04JUL02 04JUL03 05JUL04 04JUL05 04JUL06 04JUL07 04JUL08 03JUL09 24DEC99 25DEC00 25DEC01 25DEC02 25DEC03 24DEC04 26DEC05 25DEC06 25DEC07 25DEC08 25DEC09 24NOV94 25NOV94 29MAY95 04SEP95 23NOV95 24NOV95 27MAY96 02SEP96 28NOV96 29NOV96 26MAY97 01SEP97 27NOV97 28NOV97 25MAY98 07SEP98 26NOV98 27NOV98 31MAY99 06SEP99 25NOV99 26NOV99 18FEB00 29MAY00 03JUL00 04SEP00 23NOV00 24NOV00 28MAY01 03SEP01 22NOV01 23NOV01 24DEC01 31DEC01 15FEB02 24MAY02 27MAY02 05JUL02 30AUG02 02SEP02 28NOV02 29NOV02 14FEB03 23MAY03 26MAY03 29AUG03 01SEP03 27NOV03 28NOV03 26DEC03 02JAN04 28MAY04 31MAY04 24APR99 25APR99 CPM Scheduling Rule mismatch: P3=PROGRESS OVERRIDE, P6=RETAINED LOGIC P3 uses 'Contiguous Activities' setting, which is not available in P6. Float Calculation Method checks. Relationship Lag Calendar Rule checks. A total of 28 mismatches were found in this section. ============================== ACTIVITY DATA ============================== Activity AF-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Early Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity AF-03, INSTALL FOOT GRILLES @ ENTRY WAYS Early Finish Date mismatch: P3=07SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity AF-10, INSTALL RAILINGS - ATRIUM Early Finish Date mismatch: P3=17SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity AF-11, INSTALL VINYL WALL COVERING - ATRIUM Early Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Early Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity AF-15, STONE TILE - ATRIUM FLR 1 Early Start Date mismatch: P3=17SEP01 08:00, P6=25SEP01 08:00 Late Start Date mismatch: P3=15OCT01 08:00, P6=25SEP01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Late Finish Date mismatch: P3=09NOV01 17:00, P6=22OCT01 17:00 Activity AF-154, ELECTRICAL FIXTURES @ ATRIUM Early Start Date mismatch: P3=05SEP01 08:00, P6=24SEP01 08:00 Late Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Early Finish Date mismatch: P3=18SEP01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity AF-15A, STONE TILE - BASEMENT Early Start Date mismatch: P3=10SEP01 08:00, P6=18SEP01 08:00 Late Start Date mismatch: P3=08OCT01 08:00, P6=18SEP01 08:00 Early Finish Date mismatch: P3=14SEP01 17:00, P6=24SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=24SEP01 17:00 Activity AF-15B, STONE TILE - ATRIUM FLR 2 Early Start Date mismatch: P3=03OCT01 08:00, P6=11OCT01 08:00 Late Start Date mismatch: P3=08NOV01 08:00, P6=16NOV01 08:00 Early Finish Date mismatch: P3=23OCT01 17:00, P6=31OCT01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity AF-16, CARPETING - ATRIUM FLR 3 Late Start Date mismatch: P3=06NOV01 08:00, P6=12OCT01 08:00 Late Finish Date mismatch: P3=14NOV01 17:00, P6=22OCT01 17:00 Activity AF-17, INSTALL EXPANSION JOINTS - ATRIUM INTERIOR Early Finish Date mismatch: P3=07SEP01 17:00, P6=26OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity AF-18, APPLY MISC. INTERIOR SEALANTS Early Finish Date mismatch: P3=10SEP01 17:00, P6=29OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity AF-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=29OCT01 08:00, P6=06NOV01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity AF-19, INSTALL STOREFRONT/DOORS/HARDWARE/PANELS-ATRIUM Early Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity AF-195, AREA COMPLETE Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity AF-199, A/E PUNCHLIST Early Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Early Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity AF-20, PLACE CUT STONE TILE @ ATRIUM STAIR #3 Early Start Date mismatch: P3=24SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=22OCT01 08:00, P6=02OCT01 08:00 Early Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=15OCT01 17:00 Activity AF-20A, PLACE CUT STONE TILE @ ATRIUM STAIR #4 Early Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Late Start Date mismatch: P3=15NOV01 08:00, P6=27NOV01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity AF-25, PLACE CUT STONE TILE @ ATRIUM ELEVATORS Early Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Late Start Date mismatch: P3=13NOV01 08:00, P6=19OCT01 08:00 Early Finish Date mismatch: P3=09OCT01 17:00, P6=17OCT01 17:00 Late Finish Date mismatch: P3=14NOV01 17:00, P6=22OCT01 17:00 Activity AF-29, INSTALL STONE @ LOBBY BENCHES Early Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Late Start Date mismatch: P3=26NOV01 08:00, P6=16OCT01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=22OCT01 17:00 Activity AF-30, PAINT INTERIOR @ ATRIUM Early Finish Date mismatch: P3=04SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity AT040, HANG DRYWALL @ ATRIUM WEST Late Finish Date mismatch: P3=14JAN02 17:00, P6=04SEP01 17:00 Activity BM161, FORM 4 PROTECTION SLAB P3 Description=FORM 4" PROTECTION SLAB P6 Description=FORM 4 PROTECTION SLAB Activity BM170, PLACE 4 MEMBRANE PROTECTION SLAB - BASEMENT P3 Description=PLACE 4" MEMBRANE PROTECTION SLAB - BASEMENT P6 Description=PLACE 4 MEMBRANE PROTECTION SLAB - BASEMENT Activity BM234, POUR/CURE 2 1/2' MAT SLAB - BASEMENT ** Actual Start Date mismatch: P3=15APR00 08:00, P6=17APR00 08:00 Activity BM242, INSTALL 12 LINE/VAULTS (PERM DEWATERING) P3 Description=INSTALL 12" LINE/VAULTS (PERM DEWATERING) P6 Description=INSTALL 12 LINE/VAULTS (PERM DEWATERING) Activity C1-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=08NOV01 08:00, P6=12NOV01 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Early Finish Date mismatch: P3=21NOV01 17:00, P6=27NOV01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity C1-127, KNOCK DOWN FRAMES Late Start Date mismatch: P3=05OCT01 08:00, P6=11OCT01 08:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=16OCT01 17:00 Activity C1-130, IN-WALL ELECTRICAL CONDUIT * Original Duration mismatch: P3=8, P6=5 Percent complete mismatch: P3=37.5%, P6 Physical=0% Late Start Date mismatch: P3=26SEP01 08:00, P6=02OCT01 08:00 Late Finish Date mismatch: P3=02OCT01 17:00, P6=08OCT01 17:00 Activity C1-132, HANG DRYWALL - WALLS/PARTITIONS Late Finish Date mismatch: P3=04OCT01 17:00, P6=10OCT01 17:00 Activity C1-137, IN-WALL TELECOM Late Finish Date mismatch: P3=01OCT01 17:00, P6=05OCT01 17:00 Activity C1-139, WALL CLOSURE INSPECTIONS Late Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Activity C1-140, ELECTRICAL @ HARD LIDS Late Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Activity C1-142, HANG DRYWALL @ HARD LIDS Late Start Date mismatch: P3=27SEP01 08:00, P6=03OCT01 08:00 Late Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Activity C1-143, TAPE/FINISH DRYWALL - HARD LIDS Late Start Date mismatch: P3=02OCT01 08:00, P6=08OCT01 08:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=16OCT01 17:00 Activity C1-144, PULL ELECTRICAL WIRING / CONDUITS @ HARD LIDS Late Start Date mismatch: P3=09OCT01 08:00, P6=17OCT01 08:00 Late Finish Date mismatch: P3=18OCT01 17:00, P6=26OCT01 17:00 Activity C1-146, TAPE/FINISH DRYWALL - WALLS/PARTITIONS Early Finish Date mismatch: P3=19SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=18OCT01 17:00 Activity C1-147, PLUMBING FIXTURES Early Finish Date mismatch: P3=05SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity C1-148, PRIME PAINT - WALLS/HARD LIDS Late Start Date mismatch: P3=11OCT01 08:00, P6=17OCT01 08:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=22OCT01 17:00 Activity C1-150, CLG GRID Late Start Date mismatch: P3=16OCT01 08:00, P6=22OCT01 08:00 Late Finish Date mismatch: P3=18OCT01 17:00, P6=24OCT01 17:00 Activity C1-151, INSTALL FIRE EXTINGUISHER CABINETS Early Start Date mismatch: P3=10OCT01 08:00, P6=12OCT01 08:00 Late Start Date mismatch: P3=10DEC01 08:00, P6=18DEC01 08:00 Early Finish Date mismatch: P3=11OCT01 17:00, P6=15OCT01 17:00 Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity C1-154, O/H ELECTRICAL FIXTURES Late Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Late Finish Date mismatch: P3=25OCT01 17:00, P6=02NOV01 17:00 Activity C1-155, FINAL OVERHEAD INSPECTIONS/CORRECTIONS Early Start Date mismatch: P3=28SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=19OCT01 08:00, P6=29OCT01 08:00 Early Finish Date mismatch: P3=04OCT01 17:00, P6=08OCT01 17:00 Late Finish Date mismatch: P3=25OCT01 17:00, P6=02NOV01 17:00 Activity C1-156, O/H MECHANICAL DIFFUSERS Late Start Date mismatch: P3=19OCT01 08:00, P6=29OCT01 08:00 Late Finish Date mismatch: P3=23OCT01 17:00, P6=31OCT01 17:00 Activity C1-157, INSTALL BLACK OUT SHADES @ CONF CENTER Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Late Finish Date mismatch: P3=13DEC01 17:00, P6=21DEC01 17:00 Activity C1-160, CLG TILE Early Start Date mismatch: P3=05OCT01 08:00, P6=09OCT01 08:00 Late Start Date mismatch: P3=26OCT01 08:00, P6=05NOV01 08:00 Early Finish Date mismatch: P3=05OCT01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity C1-162, MECHANICAL / PLUMB TRIM & FINISHES Early Start Date mismatch: P3=08OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=29OCT01 08:00, P6=06NOV01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity C1-166, INTERIOR FRAMES/GLASS/GLAZE Early Start Date mismatch: P3=11OCT01 08:00, P6=15OCT01 08:00 Late Start Date mismatch: P3=02NOV01 08:00, P6=12NOV01 08:00 Early Finish Date mismatch: P3=17OCT01 17:00, P6=19OCT01 17:00 Late Finish Date mismatch: P3=08NOV01 17:00, P6=16NOV01 17:00 Activity C1-167, ELECTRICAL TRIM & FINISHES Early Start Date mismatch: P3=08OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=29OCT01 08:00, P6=06NOV01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity C1-168, ACOUSTAL PANELS Early Start Date mismatch: P3=11OCT01 08:00, P6=15OCT01 08:00 Late Start Date mismatch: P3=01NOV01 08:00, P6=09NOV01 08:00 Early Finish Date mismatch: P3=17OCT01 17:00, P6=19OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity C1-169, INSTALL PROJECTION SCREEN @ CONF CENTER Late Start Date mismatch: P3=25SEP01 08:00, P6=01OCT01 08:00 Late Finish Date mismatch: P3=26SEP01 17:00, P6=02OCT01 17:00 Activity C1-170, INSTALL GLASS SHELF Early Start Date mismatch: P3=15OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Early Finish Date mismatch: P3=16OCT01 17:00, P6=18OCT01 17:00 Late Finish Date mismatch: P3=13DEC01 17:00, P6=21DEC01 17:00 Activity C1-171, FIRE ALARM/FLS TRIM/FINISHES Early Start Date mismatch: P3=08OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=31OCT01 08:00, P6=08NOV01 08:00 Early Finish Date mismatch: P3=10OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity C1-172, HANG/SWING DOORS Early Start Date mismatch: P3=18OCT01 08:00, P6=22OCT01 08:00 Late Start Date mismatch: P3=09NOV01 08:00, P6=19NOV01 08:00 Early Finish Date mismatch: P3=23OCT01 17:00, P6=25OCT01 17:00 Late Finish Date mismatch: P3=14NOV01 17:00, P6=26NOV01 17:00 Activity C1-173, PULL WIRE/TIE/TRIM TELECOM Early Start Date mismatch: P3=08OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=31OCT01 08:00, P6=08NOV01 08:00 Early Finish Date mismatch: P3=10OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity C1-175, CARPETING/BASE Early Start Date mismatch: P3=11OCT01 08:00, P6=15OCT01 08:00 Late Start Date mismatch: P3=02NOV01 08:00, P6=12NOV01 08:00 Early Finish Date mismatch: P3=16OCT01 17:00, P6=18OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity C1-184, TOUCH-UP PAINT Early Start Date mismatch: P3=23OCT01 08:00, P6=25OCT01 08:00 Late Start Date mismatch: P3=13NOV01 08:00, P6=21NOV01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=30OCT01 17:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity C1-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=18OCT01 08:00, P6=22OCT01 08:00 Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Early Finish Date mismatch: P3=31OCT01 17:00, P6=02NOV01 17:00 Late Finish Date mismatch: P3=18DEC01 17:00, P6=28DEC01 17:00 Activity C1-194, SIGNAGE Early Start Date mismatch: P3=22OCT01 08:00, P6=24OCT01 08:00 Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Early Finish Date mismatch: P3=23OCT01 17:00, P6=25OCT01 17:00 Late Finish Date mismatch: P3=13DEC01 17:00, P6=21DEC01 17:00 Activity C1-195, AREA COMPLETE Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity C1-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=05SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=05NOV01 17:00, P6=13NOV01 17:00 Activity C1-199, A/E PUNCHLIST Early Start Date mismatch: P3=01NOV01 08:00, P6=05NOV01 08:00 Late Start Date mismatch: P3=19DEC01 08:00, P6=02JAN02 08:00 Early Finish Date mismatch: P3=07NOV01 17:00, P6=09NOV01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity C1-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=19OCT01 08:00, P6=23OCT01 08:00 Late Start Date mismatch: P3=09NOV01 08:00, P6=19NOV01 08:00 Early Finish Date mismatch: P3=22OCT01 17:00, P6=24OCT01 17:00 Late Finish Date mismatch: P3=12NOV01 17:00, P6=20NOV01 17:00 Activity C1-248, FINAL PAINT - WALLS/HARD LIDS Early Start Date mismatch: P3=08OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=08NOV01 08:00, P6=16NOV01 08:00 Early Finish Date mismatch: P3=10OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=12NOV01 17:00, P6=20NOV01 17:00 Activity CC012, INSTALL GLASS @ CONF CENTER Late Finish Date mismatch: P3=14JAN02 17:00, P6=09OCT01 17:00 Activity CRB#1-A, PARTITIONS AT BASEMENT ** Actual Finish Date mismatch: P3=21AUG01 17:00, P6=22AUG01 08:00 Activity CRB#1-B, PARTITIONS AT GROUND FLOOR WEST ** Actual Finish Date mismatch: P3=21AUG01 17:00, P6=22AUG01 08:00 Activity CRB#1-C, PARTITIONS AT 2ND FLOOR EAST Early Start Date mismatch: P3=04SEP01 08:00, P6=11SEP01 08:00 Activity CRB#1-D, PARTITIONS AT 3RD FLOOR EAST Early Start Date mismatch: P3=04SEP01 08:00, P6=13SEP01 08:00 Activity CRB#22, REMOVE 12x12 CB INST. NEW STORM DRAIN MANHOLE ** Actual Finish Date mismatch: P3=24OCT00 17:00, P6=25OCT00 08:00 Activity CRB#3, ADD MTL CASE OPENINGS @ BASEMENT LEVEL ** Actual Finish Date mismatch: P3=25OCT00 17:00, P6=26OCT00 08:00 Activity CRB#4-A, METAL ROOF @ ATRIUM ** Actual Finish Date mismatch: P3=10DEC00 17:00, P6=11DEC00 08:00 Activity CRB#4-B, METAL ROOF @ CONFERENCE CENTER ** Actual Finish Date mismatch: P3=20MAY01 17:00, P6=21MAY01 08:00 Activity CRB#7.2-M, TRIM - CRB #7.2 & 7.3 Late Start Date mismatch: P3=08JAN02 08:00, P6=14SEP01 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=20SEP01 17:00 Activity CRB#80-12, CRB #80 PRICING APPROVAL Late Finish Date mismatch: P3=14JAN02 17:00, P6=03JAN02 17:00 Activity CRB#80-20, REPRICING APPROVAL Early Finish Date mismatch: P3=06SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity CRB#80-22, ISSUE CHANGE ORDER Early Start Date mismatch: P3=07SEP01 08:00, P6=12SEP01 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity E1-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=15OCT01 08:00, P6=31OCT01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=09NOV01 17:00, P6=29NOV01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E1-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=10OCT00 17:00, P6=11OCT00 08:00 Activity E1-147, PLUMBING FIXTURES - ALL AREAS Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=14DEC01 17:00, P6=09OCT01 17:00 Activity E1-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity E1-158, MILLWORK/CASEWORK Early Finish Date mismatch: P3=11SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=09OCT01 17:00 Activity E1-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=25SEP01 17:00, P6=24SEP01 17:00 Activity E1-164, FLOORING/BASE Late Start Date mismatch: P3=19OCT01 08:00, P6=29OCT01 08:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity E1-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=12SEP01 17:00, P6=18SEP01 17:00 Late Finish Date mismatch: P3=03OCT01 17:00, P6=02OCT01 17:00 Activity E1-167, ELECTRICAL TRIM & FINISHES Early Finish Date mismatch: P3=04SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=24SEP01 17:00, P6=21SEP01 17:00 Activity E1-168, INSTALL KIOSK Early Start Date mismatch: P3=04SEP01 08:00, P6=11SEP01 08:00 Late Start Date mismatch: P3=24SEP01 08:00, P6=21SEP01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=03OCT01 17:00, P6=02OCT01 17:00 Activity E1-171, FIRE ALARM/FLS TRIM/FINISHES Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=24SEP01 17:00, P6=25SEP01 17:00 Activity E1-172, HANG/SWING DOORS Early Start Date mismatch: P3=07SEP01 08:00, P6=14SEP01 08:00 Late Start Date mismatch: P3=02OCT01 08:00, P6=01OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=15OCT01 17:00, P6=12OCT01 17:00 Activity E1-175, CARPETING/BASE Late Start Date mismatch: P3=08OCT01 08:00, P6=21SEP01 08:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=01OCT01 17:00 Activity E1-184, TOUCH-UP PAINT Early Start Date mismatch: P3=21SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=10OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=16OCT01 17:00 Activity E1-186, WORK TO COMPLETE LIST / CORRECTIONS Early Finish Date mismatch: P3=05OCT01 17:00, P6=23OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E1-188, INSTALL CORNER GUARDS Early Start Date mismatch: P3=25SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=15OCT01 08:00, P6=23OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E1-194, SIGNAGE Early Start Date mismatch: P3=26SEP01 08:00, P6=03OCT01 08:00 Late Start Date mismatch: P3=16OCT01 08:00, P6=24OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E1-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E1-199, A/E PUNCHLIST Early Start Date mismatch: P3=08OCT01 08:00, P6=24OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=30OCT01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity E1-208, INSTALL SOLID POLYMER FABRICATIONS Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=01OCT01 17:00 Activity E1-211, INSTALL ACCESS DOORS Early Start Date mismatch: P3=04SEP01 08:00, P6=06SEP01 08:00 Late Start Date mismatch: P3=27SEP01 08:00, P6=26SEP01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=27SEP01 17:00 Activity E1-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=19SEP01 08:00, P6=26SEP01 08:00 Late Start Date mismatch: P3=09OCT01 08:00, P6=08OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=09OCT01 17:00 Activity E1-216, INSTALL DROP BOXES Early Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity E2-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=22OCT01 08:00, P6=07NOV01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=16NOV01 17:00, P6=06DEC01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E2-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=17OCT00 17:00, P6=18OCT00 08:00 Activity E2-147, PLUMBING FIXTURES - ALL AREAS (EXCL. BATH) Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E2-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity E2-158, MILLWORK/CASEWORK Early Start Date mismatch: P3=18SEP01 08:00, P6=24SEP01 08:00 Late Start Date mismatch: P3=17OCT01 08:00, P6=25OCT01 08:00 Early Finish Date mismatch: P3=19SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=18OCT01 17:00, P6=26OCT01 17:00 Activity E2-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=13SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=01OCT01 17:00, P6=09OCT01 17:00 Activity E2-164, FLOORING/BASE Late Start Date mismatch: P3=25OCT01 08:00, P6=02NOV01 08:00 Late Finish Date mismatch: P3=30OCT01 17:00, P6=07NOV01 17:00 Activity E2-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity E2-168, ACOUSTICAL PANELS Early Start Date mismatch: P3=14SEP01 08:00, P6=20SEP01 08:00 Late Start Date mismatch: P3=03OCT01 08:00, P6=11OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=09OCT01 17:00, P6=17OCT01 17:00 Activity E2-170, INSTALL VISUAL DISPLAY BOARDS Early Finish Date mismatch: P3=24SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity E2-172, HANG/SWING DOORS Early Start Date mismatch: P3=24SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=10OCT01 08:00, P6=18OCT01 08:00 Early Finish Date mismatch: P3=05OCT01 17:00, P6=11OCT01 17:00 Late Finish Date mismatch: P3=23OCT01 17:00, P6=31OCT01 17:00 Activity E2-173, PULL WIRE/TIE/TRIM TELECOM Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=01OCT01 17:00, P6=09OCT01 17:00 Activity E2-174, CERAMIC TILE - BATH Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=21SEP01 17:00, P6=01OCT01 17:00 Activity E2-175, CARPETING/BASE Late Start Date mismatch: P3=15OCT01 08:00, P6=28SEP01 08:00 Late Finish Date mismatch: P3=23OCT01 17:00, P6=08OCT01 17:00 Activity E2-176, PLUMBING FIXTURES - BATH/KITCHEN Early Finish Date mismatch: P3=12SEP01 17:00, P6=18SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity E2-180, PLASTIC LAMINATE FABRICATIONS Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity E2-182, TOILET COMPARTMENTS & ACCESSORIES Early Finish Date mismatch: P3=06SEP01 17:00, P6=12SEP01 17:00 Late Finish Date mismatch: P3=02OCT01 17:00, P6=10OCT01 17:00 Activity E2-184, TOUCH-UP PAINT Early Start Date mismatch: P3=03OCT01 08:00, P6=09OCT01 08:00 Late Start Date mismatch: P3=19OCT01 08:00, P6=29OCT01 08:00 Early Finish Date mismatch: P3=09OCT01 17:00, P6=15OCT01 17:00 Late Finish Date mismatch: P3=25OCT01 17:00, P6=02NOV01 17:00 Activity E2-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=17SEP01 08:00, P6=03OCT01 08:00 Late Start Date mismatch: P3=01OCT01 08:00, P6=09OCT01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=30OCT01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity E2-188, INSTALL CORNER GUARDS Early Start Date mismatch: P3=05OCT01 08:00, P6=11OCT01 08:00 Late Start Date mismatch: P3=24OCT01 08:00, P6=01NOV01 08:00 Early Finish Date mismatch: P3=08OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=25OCT01 17:00, P6=02NOV01 17:00 Activity E2-194, SIGNAGE Early Start Date mismatch: P3=03OCT01 08:00, P6=09OCT01 08:00 Late Start Date mismatch: P3=23OCT01 08:00, P6=31OCT01 08:00 Early Finish Date mismatch: P3=04OCT01 17:00, P6=10OCT01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity E2-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E2-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=07SEP01 17:00, P6=13SEP01 17:00 Late Finish Date mismatch: P3=03OCT01 17:00, P6=11OCT01 17:00 Activity E2-199, A/E PUNCHLIST Early Start Date mismatch: P3=15OCT01 08:00, P6=31OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=19OCT01 17:00, P6=06NOV01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity E2-208, INSTALL SOLID POLYMER FABRICATIONS Early Start Date mismatch: P3=06SEP01 08:00, P6=12SEP01 08:00 Late Start Date mismatch: P3=05OCT01 08:00, P6=15OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=24OCT01 17:00 Activity E2-211, INSTALL ACCESS DOORS Early Start Date mismatch: P3=04SEP01 08:00, P6=06SEP01 08:00 Late Start Date mismatch: P3=05OCT01 08:00, P6=15OCT01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=08OCT01 17:00, P6=16OCT01 17:00 Activity E2-214, INSTALL APPLIANCES Early Start Date mismatch: P3=19SEP01 08:00, P6=25SEP01 08:00 Late Start Date mismatch: P3=05OCT01 08:00, P6=15OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=08OCT01 17:00, P6=16OCT01 17:00 Activity E2-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=26SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=16OCT01 08:00, P6=24OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E3-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=05NOV01 08:00, P6=21NOV01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=04DEC01 17:00, P6=20DEC01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E3-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=31OCT00 17:00, P6=01NOV00 08:00 Activity E3-147, PLUMBING FIXTURES - ALL AREAS (EXCL. BATH) Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=01OCT01 08:00, P6=09OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity E3-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E3-158, MILLWORK/CASEWORK Early Start Date mismatch: P3=28SEP01 08:00, P6=04OCT01 08:00 Late Start Date mismatch: P3=30OCT01 08:00, P6=07NOV01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=31OCT01 17:00, P6=08NOV01 17:00 Activity E3-162, MECHANICAL / PLUMB TRIM & FINISHES Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=20SEP01 08:00, P6=28SEP01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity E3-164, FLOORING/BASE Late Start Date mismatch: P3=06NOV01 08:00, P6=14NOV01 08:00 Late Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Activity E3-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=01OCT01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E3-167, ELECTRICAL TRIM & FINISHES Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=20SEP01 08:00, P6=28SEP01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity E3-168, ACOUSTICAL PANELS Early Start Date mismatch: P3=25SEP01 08:00, P6=01OCT01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=19OCT01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E3-170, INSTALL VISUAL DISPLAY BOARDS Early Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E3-171, FIRE ALARM/FLS TRIM/FINISHES Early Finish Date mismatch: P3=07SEP01 17:00, P6=13SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity E3-172, HANG/SWING DOORS Early Start Date mismatch: P3=28SEP01 08:00, P6=04OCT01 08:00 Late Start Date mismatch: P3=23OCT01 08:00, P6=31OCT01 08:00 Early Finish Date mismatch: P3=11OCT01 17:00, P6=17OCT01 17:00 Late Finish Date mismatch: P3=05NOV01 17:00, P6=13NOV01 17:00 Activity E3-173, PULL WIRE/TIE/TRIM TELECOM Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity E3-174, CERAMIC TILE - BATH Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity E3-175, CARPETING/BASE Late Start Date mismatch: P3=29OCT01 08:00, P6=12OCT01 08:00 Late Finish Date mismatch: P3=06NOV01 17:00, P6=22OCT01 17:00 Activity E3-176, PLUMBING FIXTURES - BATH/KITCHEN Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=01OCT01 08:00, P6=09OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity E3-180, PLASTIC LAMINATE FABRICATIONS Early Start Date mismatch: P3=04SEP01 08:00, P6=11SEP01 08:00 Late Start Date mismatch: P3=05OCT01 08:00, P6=15OCT01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=24OCT01 17:00 Activity E3-182, TOILET COMPARTMENTS & ACCESSORIES Early Finish Date mismatch: P3=17SEP01 17:00, P6=24SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity E3-184, TOUCH-UP PAINT Early Start Date mismatch: P3=09OCT01 08:00, P6=15OCT01 08:00 Late Start Date mismatch: P3=01NOV01 08:00, P6=09NOV01 08:00 Early Finish Date mismatch: P3=15OCT01 17:00, P6=19OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity E3-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=01OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=15OCT01 08:00, P6=23OCT01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=13NOV01 17:00 Late Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Activity E3-188, INSTALL CORNER GUARDS Early Start Date mismatch: P3=11OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=06NOV01 08:00, P6=14NOV01 08:00 Early Finish Date mismatch: P3=12OCT01 17:00, P6=18OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity E3-194, SIGNAGE Early Start Date mismatch: P3=12OCT01 08:00, P6=18OCT01 08:00 Late Start Date mismatch: P3=01NOV01 08:00, P6=09NOV01 08:00 Early Finish Date mismatch: P3=15OCT01 17:00, P6=19OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity E3-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity E3-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=06SEP01 17:00, P6=12SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity E3-199, A/E PUNCHLIST Early Start Date mismatch: P3=29OCT01 08:00, P6=14NOV01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=02NOV01 17:00, P6=20NOV01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity E3-208, INSTALL SOLID POLYMER FABRICATIONS Early Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=29OCT01 17:00, P6=06NOV01 17:00 Activity E3-211, INSTALL ACCESS DOORS Early Start Date mismatch: P3=04SEP01 08:00, P6=06SEP01 08:00 Late Start Date mismatch: P3=16OCT01 08:00, P6=24OCT01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E3-214, INSTALL APPLIANCES Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=16OCT01 08:00, P6=24OCT01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity E3-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=05OCT01 08:00, P6=11OCT01 08:00 Late Start Date mismatch: P3=25OCT01 08:00, P6=02NOV01 08:00 Early Finish Date mismatch: P3=08OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity EB-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=01OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=13NOV01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity EB-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=29SEP00 17:00, P6=30SEP00 08:00 Activity EB-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=18SEP01 17:00, P6=10SEP01 17:00 Activity EB-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=19SEP01 17:00, P6=26SEP01 17:00 Activity EB-168, CORNER GUARDS Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=19SEP01 17:00, P6=26SEP01 17:00 Activity EB-172, HANG/SWING DOORS Early Finish Date mismatch: P3=11SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=25SEP01 17:00, P6=02OCT01 17:00 Activity EB-184, TOUCH-UP PAINT Early Finish Date mismatch: P3=13SEP01 17:00, P6=28SEP01 17:00 Activity EB-186, WORK TO COMPLETE LIST / CORRECTIONS Early Finish Date mismatch: P3=21SEP01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity EB-194, SIGNAGE Early Start Date mismatch: P3=04SEP01 08:00, P6=18SEP01 08:00 Late Start Date mismatch: P3=20SEP01 08:00, P6=28SEP01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=21SEP01 17:00, P6=01OCT01 17:00 Activity EB-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity EB-199, A/E PUNCHLIST Early Start Date mismatch: P3=24SEP01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=28SEP01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity EB-285, INSTALL ACCORDION FIRE DOOR Early Finish Date mismatch: P3=18SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=02OCT01 17:00 Activity EL1-F, FIRE/LIFE/SAFETY @ ELEV Early Start Date mismatch: P3=04SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=15NOV01 08:00, P6=27NOV01 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity EL1-I, TEST/ADJUST ELEVATOR Early Start Date mismatch: P3=25SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=26NOV01 08:00, P6=04DEC01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity EL1-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity EL2-F, FIRE/LIFE/SAFETY @ ELEV Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=15NOV01 08:00, P6=27NOV01 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity EL2-I, TEST/ADJUST ELEVATOR Early Start Date mismatch: P3=25SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=26NOV01 08:00, P6=04DEC01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity EL2-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity EL3-F, FIRE/LIFE/SAFETY @ ELEV Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=15NOV01 08:00, P6=16NOV01 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=26NOV01 17:00 Activity EL3-I, TEST/ADJUST ELEVATOR Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=26NOV01 08:00, P6=04DEC01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity EL3-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST Late Finish Date mismatch: P3=30NOV01 17:00, P6=10DEC01 17:00 Activity FI#11, REV'S PER RFI# 95, 95.1 & 112 ** Actual Finish Date mismatch: P3=25SEP00 17:00, P6=26SEP00 08:00 Activity FI#12-04, DETAILING/MATERIAL PROCUREMENT PER F/I #12 ** Actual Start Date mismatch: P3=03JUL00 08:00, P6=05JUL00 08:00 Activity FI#13-04, DETAILING/MATERIAL PROCUREMENT PER F/I #13 ** Actual Start Date mismatch: P3=03JUL00 08:00, P6=05JUL00 08:00 Activity FI#14, REVISED PERIMETER DRAIN SYSTEM ** Actual Finish Date mismatch: P3=17JUL00 17:00, P6=18JUL00 08:00 Activity FI#4-06, TEMPORARY ACCESS ROAD WORK ** Actual Start Date mismatch: P3=18FEB00 08:00, P6=21FEB00 08:00 Activity FI#92-A, STOP WORK ON LANDSCAPE, PAVERS, SITEWORK ** Actual Finish Date mismatch: P3=08AUG01 17:00, P6=09AUG01 08:00 Activity FI#92-B, AWAITING APPROVD C.O. Late Finish Date mismatch: P3=17SEP01 17:00, P6=25SEP01 17:00 Activity FI#92-C, EXECUTE C.O. - LSCAPE/PAVERS/SITEWORK STOP WORK Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity FI92SU-015, DEMO ROAD/INSTALL BASE Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity FI92SU-045, STORM DRAIN TIE IN TO TRENCH DRAIN Late Finish Date mismatch: P3=09JAN02 17:00, P6=17JAN02 17:00 Activity FI92SW-020, CONCRETE PLANTERS Late Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Activity FI92SW-030, SITE SIDEWALKS Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity FI92SW-040, CURBS & GUTTERS Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity FI92SW-045, FINISH GRADE / AGGREGATE BASE Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity FI92SW-050, U/G IRRIGATION Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity FI92SW-071, PATCH A/C Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity FI92SW-080, IRRIGATION & LANDSCAPING Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity FI92SW-090, SITE FURNISHINGS Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity FI92SW-100, ELEC FIXTURES Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity FI92SW-112, INSTALL BIKE RACKS Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity FI92SW-114, INSTALL BENCHES Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity FI92SW-140, INSTALL PAVERS Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity FI92SW-141, INSTALL PAVERS OFF SITE Late Finish Date mismatch: P3=11JAN02 17:00, P6=21JAN02 17:00 Activity GL052, REBAR & A.B.'S @ F7R/F10 @ 9/D LINE FOOTINGS ** Actual Start Date mismatch: P3=17JUN00 08:00, P6=19JUN00 08:00 Activity ME101, INSTALL HVAC DUCTWORK Late Finish Date mismatch: P3=19OCT01 17:00, P6=24OCT01 17:00 Activity ME108, START UP / RUN TEST MECH EQ - MN MECH Late Start Date mismatch: P3=28DEC01 08:00, P6=26OCT01 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=08NOV01 17:00 Activity ME203, PIPE MECH EQ - LATERALS/VERTS CONF. RM Late Finish Date mismatch: P3=02NOV01 17:00, P6=07NOV01 17:00 Activity ME206, CONTROLS - CONF. RM Early Finish Date mismatch: P3=06SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity ME208, START UP / RUN TEST MECH EQ - CONF. RM Early Start Date mismatch: P3=24SEP01 08:00, P6=27SEP01 08:00 Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Early Finish Date mismatch: P3=05OCT01 17:00, P6=10OCT01 17:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity ME232, MANUF CHECK LIST - CONF. RM Early Start Date mismatch: P3=21SEP01 08:00, P6=26SEP01 08:00 Late Start Date mismatch: P3=02NOV01 08:00, P6=12NOV01 08:00 Early Finish Date mismatch: P3=21SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity MEP-01, BASEMENT/SUBSLAB MEP COOR. ** Actual Start Date mismatch: P3=18FEB00 08:00, P6=21FEB00 08:00 Activity ML-J, MATERIAL LIFT COMPLETE - AVAILABLE FOR FNL TEST ** Actual Finish Date mismatch: P3=06JUL01 17:00, P6=07JUL01 08:00 Activity OS-032, 10 WATER TIE-IN - N/E P3 Description=10" WATER TIE-IN - N/E P6 Description=10 WATER TIE-IN - N/E Activity OS-043, 12 SD TIE-IN - N/E P3 Description=12" SD TIE-IN - N/E P6 Description=12 SD TIE-IN - N/E Activity OS-060, 2 GAS TIE-IN - N/E P3 Description=2" GAS TIE-IN - N/E P6 Description=2 GAS TIE-IN - N/E Activity OS-100, INSTALL 10 WATER LINE P3 Description=INSTALL 10" WATER LINE P6 Description=INSTALL 10 WATER LINE Activity OS-143, 12 SD & CB @ UNIV. CIRCLE P3 Description=12" SD & CB @ UNIV. CIRCLE P6 Description=12 SD & CB @ UNIV. CIRCLE Activity OS-200, INSTALL 6 PERM DEWATER DISCHARGE P3 Description=INSTALL 6" PERM DEWATER DISCHARGE P6 Description=INSTALL 6 PERM DEWATER DISCHARGE Activity OS-300, INSTALL TELECOM @ CLASSROOM BLDG TO MH #2 Late Finish Date mismatch: P3=14JAN02 17:00, P6=21SEP01 17:00 Activity OS-400, INSTALL TELECOM @ LIBRARY TO MH #3 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=25SEP01 17:00 Activity OS-500, INSTALL TELECOM FROM MH #2 & #3 TO MH #5 Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity OS-999, OFF-SITE WORK COMPLETE Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity P090-A, RVW/FRWD METAL SHINGLES SHOP DRAWINGS ** Actual Start Date mismatch: P3=03JUL00 08:00, P6=05JUL00 08:00 Activity P260-A, RVW/FRWD FUEL OIL STORAGE TANK SHOP DRAWINGS ** Actual Start Date mismatch: P3=18FEB00 08:00, P6=21FEB00 08:00 ** Actual Finish Date mismatch: P3=18FEB00 17:00, P6=21FEB00 08:00 Activity P260-B, REVIEW & APPROVE FUEL OIL STORAGE TANK ** Actual Start Date mismatch: P3=18FEB00 08:00, P6=21FEB00 08:00 Activity PCO#201-D, CRB #82 PRICING Early Finish Date mismatch: P3=25SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=15JAN02 17:00 Activity PCO#201-F, EXECUTE C.O. FOR CRB #82 Early Start Date mismatch: P3=25SEP01 08:00, P6=01OCT01 08:00 Late Start Date mismatch: P3=08JAN02 08:00, P6=16JAN02 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity PCO#201-J, INSTALL PLATFORM/ACCESS LADDER PER CRB #82 Early Start Date mismatch: P3=18SEP01 08:00, P6=21SEP01 08:00 Late Start Date mismatch: P3=15NOV01 08:00, P6=27NOV01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity PCO#208-F, PRICING CRB #79 (T & M) Early Finish Date mismatch: P3=25SEP01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity PCO#208-I, FABRICATE & PROCURE STEEL PER F.I. #84 Late Finish Date mismatch: P3=28DEC01 17:00, P6=18DEC01 17:00 Activity PCO#208-K, DEMOLITION & MEP RELOCATION PER F.I. #84 Late Start Date mismatch: P3=02JAN02 08:00, P6=19DEC01 08:00 Late Finish Date mismatch: P3=08JAN02 17:00, P6=27DEC01 17:00 Activity PCO#208-L, INSTALL NEW STEEL PER F.I. #84 Late Start Date mismatch: P3=09JAN02 08:00, P6=28DEC01 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=04JAN02 17:00 Activity PCO#208-M, DEMO ROOFING PER F.I. #84 Percent complete mismatch: P3=33.3%, P6 Physical=0% Early Start Date mismatch: P3=04SEP01 08:00, P6=25SEP01 08:00 Late Start Date mismatch: P3=18DEC01 08:00, P6=28DEC01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=19DEC01 17:00, P6=02JAN02 17:00 Activity PCO#208-N, ROOFING PER F.I. #84 Early Start Date mismatch: P3=11SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=27DEC01 08:00, P6=08JAN02 08:00 Early Finish Date mismatch: P3=14SEP01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=03JAN02 17:00, P6=11JAN02 17:00 Activity PCO#208-O, FIREPROOFING PER F.I. #84 Early Start Date mismatch: P3=17SEP01 08:00, P6=08OCT01 08:00 Late Start Date mismatch: P3=04JAN02 08:00, P6=14JAN02 08:00 Early Finish Date mismatch: P3=18SEP01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=07JAN02 17:00, P6=15JAN02 17:00 Activity PCO#208-Q, PATCH FINISHES PER F.I. #84 Early Start Date mismatch: P3=19SEP01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=08JAN02 08:00, P6=16JAN02 08:00 Early Finish Date mismatch: P3=21SEP01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=10JAN02 17:00, P6=18JAN02 17:00 Activity PCO#208-T, INSTALL TUBE STEEL METAL DECK Early Start Date mismatch: P3=06SEP01 08:00, P6=27SEP01 08:00 Late Start Date mismatch: P3=20DEC01 08:00, P6=03JAN02 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=01OCT01 17:00 Late Finish Date mismatch: P3=26DEC01 17:00, P6=07JAN02 17:00 Activity PCO#37-B, AWAITING FINAL SCOPE/DESIGN REV'S FOR PRICING ** Actual Start Date mismatch: P3=29APR00 08:00, P6=01MAY00 08:00 Activity PCO#37-D, PRICING REVIEW - CRB#7 ** Actual Start Date mismatch: P3=10FEB01 08:00, P6=12FEB01 08:00 Activity PCO#39-B, AWAITING FINAL SCOPE/DESIGN REV'S FOR PRICING ** Actual Start Date mismatch: P3=29APR00 08:00, P6=01MAY00 08:00 Activity PH-167, ELECTRICAL TRIM & FINISHES @ PENTHOUSE Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=17OCT01 08:00 Early Finish Date mismatch: P3=19SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=25OCT01 17:00 Activity PH090, H/T/FINISH DRYWALL @ PENTHOUSE Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=11OCT01 17:00 Activity PH095, PRIME PAINT @ PENTHOUSE Early Start Date mismatch: P3=06SEP01 08:00, P6=12SEP01 08:00 Late Start Date mismatch: P3=08OCT01 08:00, P6=12OCT01 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=16OCT01 17:00 Activity PH104, ELECTRICAL EQUIP CONNECTIONS @ PENTHOUSE Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=25OCT01 17:00 Activity PH106, CONTROLS @ PENTHOUSE Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=25OCT01 17:00 Activity PH108, BUMP START HVAC EQ @ PENTHOUSE Early Start Date mismatch: P3=20SEP01 08:00, P6=26SEP01 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=26OCT01 08:00 Early Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=08NOV01 17:00 Activity PH132, MANUF CHECK LIST - PENTHOUSE EQ Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=27DEC01 08:00, P6=25OCT01 08:00 Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=25OCT01 17:00 Activity PL107, FLUSH/CLEAN PIPING - BSMNT PLUMB Early Start Date mismatch: P3=25SEP01 08:00, P6=01OCT01 08:00 Late Start Date mismatch: P3=17DEC01 08:00, P6=27DEC01 08:00 Early Finish Date mismatch: P3=08OCT01 17:00, P6=12OCT01 17:00 Late Finish Date mismatch: P3=03JAN02 17:00, P6=11JAN02 17:00 Activity PL108, START UP / RUN TEST PLUMBING EQ - BSMNT PLUMB Late Start Date mismatch: P3=12NOV01 08:00, P6=12OCT01 08:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=25OCT01 17:00 Activity PL206, CONTROLS - PH PLUMB Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity PL207, FLUSH/CLEAN PIPING - PH PLUMB Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=03DEC01 17:00 Activity PL208, START UP / RUN TEST PLUMBING EQ - PH PLUMB Early Start Date mismatch: P3=14SEP01 08:00, P6=20SEP01 08:00 Late Start Date mismatch: P3=26NOV01 08:00, P6=04DEC01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=07DEC01 17:00, P6=17DEC01 17:00 Activity PL232, MANUF CHECK LIST - PH PLUMB Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=21NOV01 08:00, P6=25OCT01 08:00 Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=21NOV01 17:00, P6=25OCT01 17:00 Activity PP128, PERMANENT POWER (AVAILABLE FOR DIST) ** Actual Finish Date mismatch: P3=27DEC00 17:00, P6=28DEC00 08:00 Activity RFI#214, SHOT PIN ATTACHMENT IN LIEU OF WELD ** Actual Finish Date mismatch: P3=07SEP00 17:00, P6=08SEP00 08:00 Activity RFI#67.1, U/G SEWER REV'S ** Actual Finish Date mismatch: P3=30OCT00 17:00, P6=31OCT00 08:00 Activity RP017, INSTALL EXPANSION JOINTS - WEST Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity SSE53, F/R/P TREADS @ STAIRS #4 Early Start Date mismatch: P3=04SEP01 08:00, P6=07SEP01 08:00 Late Start Date mismatch: P3=09OCT01 08:00, P6=07SEP01 08:00 Early Finish Date mismatch: P3=04SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=09OCT01 17:00, P6=07SEP01 17:00 Activity STAIR#1-E, FINAL PAINT @ STAIRWELL #1 Early Start Date mismatch: P3=04SEP01 08:00, P6=24SEP01 08:00 Late Start Date mismatch: P3=21DEC01 08:00, P6=15NOV01 08:00 Early Finish Date mismatch: P3=06SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=19NOV01 17:00 Activity STAIR#1-F, STAIRWELL #1 COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=19NOV01 17:00 Activity STAIR#2-E, FINAL PAINT @ STAIRWELL #2 Early Start Date mismatch: P3=04SEP01 08:00, P6=19SEP01 08:00 Late Start Date mismatch: P3=21DEC01 08:00, P6=12NOV01 08:00 Early Finish Date mismatch: P3=06SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=14NOV01 17:00 Activity STAIR#2-F, STAIRWELL #2 COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=19NOV01 17:00 Activity STAIR#2-H, TRAFFIC COATINGS @ STAIRWELL #2 Early Finish Date mismatch: P3=31AUG01 17:00, P6=19SEP01 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=14NOV01 17:00 Activity STAIR#3-A, ELECTRICAL @ STAIR #3 Early Start Date mismatch: P3=05SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=21SEP01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=18SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity STAIR#3-B, HANDRAILS @ STAIR #3 Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 08:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=26SEP01 17:00 Activity STAIR#3-E, FINAL PAINT @ STAIRWELL #3 Early Start Date mismatch: P3=11SEP01 08:00, P6=14SEP01 08:00 Late Start Date mismatch: P3=17OCT01 08:00, P6=27SEP01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=18SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity STAIR#3-F, STAIRWELL #3 COMPLETE Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity STAIR#4-B, HANDRAILS @ STAIR #4 Early Start Date mismatch: P3=05SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=10OCT01 08:00, P6=20SEP01 08:00 Early Finish Date mismatch: P3=11SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=26SEP01 17:00 Activity STAIR#4-E, FINAL PAINT @ STAIRWELL #4 Early Start Date mismatch: P3=12SEP01 08:00, P6=24SEP01 08:00 Late Start Date mismatch: P3=17OCT01 08:00, P6=27SEP01 08:00 Early Finish Date mismatch: P3=14SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity STAIR#4-F, STAIRWELL #4 COMPLETE Late Finish Date mismatch: P3=19OCT01 17:00, P6=01OCT01 17:00 Activity STAIR#5-B, HANDRAILS @ STAIR #5 Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=08JAN02 08:00, P6=13SEP01 08:00 Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=19SEP01 17:00 Activity STAIR#5-F, STAIRWELL #5 COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=02OCT01 17:00 Activity SU015, DEMO ROAD/INSTALL BASE Late Start Date mismatch: P3=18SEP01 08:00, P6=26SEP01 08:00 Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity SU032, 10 WATER MAINS P3 Description=10" WATER MAINS P6 Description=10 WATER MAINS Activity SU044, SET DRAINS & MAN HOLES Late Start Date mismatch: P3=10JAN02 08:00, P6=18JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity SU045, STORM DRAIN TIE IN TO TRENCH DRAIN Late Start Date mismatch: P3=08JAN02 08:00, P6=16JAN02 08:00 Late Finish Date mismatch: P3=09JAN02 17:00, P6=17JAN02 17:00 Activity SU046, 8 WATER MAINS P3 Description=8" WATER MAINS P6 Description=8 WATER MAINS Activity SU049, INSTALL & TEST SUMP PUMPS Late Finish Date mismatch: P3=10JAN02 17:00, P6=18JAN02 17:00 Activity SU060, SITE UTILITIES - 3 P.P./F.O./GAS P3 Description=SITE UTILITIES - 3" P.P./F.O./GAS P6 Description=SITE UTILITIES - 3 P.P./F.O./GAS Activity SU061, CROSSOVER TEMP TO PERM DEWATERING Late Start Date mismatch: P3=11JAN02 08:00, P6=21JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity SU999, SITE UTILITIES COMPLETE Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity SW-010, LAYOUT Late Start Date mismatch: P3=20SEP01 08:00, P6=28SEP01 08:00 Late Finish Date mismatch: P3=21SEP01 17:00, P6=01OCT01 17:00 Activity SW-020, CONCRETE PLANTERS Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Late Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Activity SW-030, SITE SIDEWALKS Late Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity SW-040, CURBS & GUTTERS Late Start Date mismatch: P3=01OCT01 08:00, P6=09OCT01 08:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity SW-045, FINISH GRADE / AGGREGATE BASE Late Start Date mismatch: P3=21NOV01 08:00, P6=03DEC01 08:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity SW-050, U/G IRRIGATION Late Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity SW-060, ROUGH SUBGRADE & AGGREGATE BASE Late Start Date mismatch: P3=24SEP01 08:00, P6=02OCT01 08:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity SW-070, PAVE & STRIPING Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Late Finish Date mismatch: P3=18DEC01 17:00, P6=28DEC01 17:00 Activity SW-071, PATCH A/C Late Start Date mismatch: P3=14JAN02 08:00, P6=22JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity SW-080, IRRIGATION & LANDSCAPING Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-090, SITE FURNISHINGS Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-100, ELEC FIXTURES Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-110, INSTALL FENCING Late Start Date mismatch: P3=19DEC01 08:00, P6=02JAN02 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-111, INSTALL BOLLARDS Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity SW-112, INSTALL BIKE RACKS Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity SW-113, INSTALL PARKING BUMPERS Late Start Date mismatch: P3=19DEC01 08:00, P6=02JAN02 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-114, INSTALL BENCHES Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity SW-120, SITEWORK PUNCHLIST & CORRECTIONS Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity SW-130, INSTALL WATERPROOFING @ ENTRANCES Late Start Date mismatch: P3=13DEC01 08:00, P6=21DEC01 08:00 Late Finish Date mismatch: P3=18DEC01 17:00, P6=28DEC01 17:00 Activity SW-140, INSTALL PAVERS Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity SW-141, INSTALL PAVERS OFF SITE Late Start Date mismatch: P3=09JAN02 08:00, P6=17JAN02 08:00 Late Finish Date mismatch: P3=11JAN02 17:00, P6=21JAN02 17:00 Activity SW-999, SITE IMPROVEMENTS COMPLETE Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity W1-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=08OCT01 08:00, P6=24OCT01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=02NOV01 17:00, P6=20NOV01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W1-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=10OCT00 17:00, P6=11OCT00 08:00 Activity W1-147, PLUMBING FIXTURES - ALL AREAS (EXCL. BATH) Early Finish Date mismatch: P3=06SEP01 17:00, P6=12SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity W1-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=06SEP01 17:00, P6=12SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity W1-158, MILLWORK/CASEWORK Early Start Date mismatch: P3=10SEP01 08:00, P6=14SEP01 08:00 Late Start Date mismatch: P3=03OCT01 08:00, P6=11OCT01 08:00 Early Finish Date mismatch: P3=11SEP01 17:00, P6=17SEP01 17:00 Late Finish Date mismatch: P3=04OCT01 17:00, P6=12OCT01 17:00 Activity W1-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=25SEP01 17:00, P6=03OCT01 17:00 Activity W1-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=13SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=26SEP01 17:00, P6=04OCT01 17:00 Activity W1-168, ACOUSTICAL PANELS Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=26SEP01 08:00, P6=04OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=02OCT01 17:00, P6=10OCT01 17:00 Activity W1-170, INSTALL VISUAL DISPLAY BOARDS Early Finish Date mismatch: P3=14SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity W1-172, HANG/SWING DOORS Early Start Date mismatch: P3=11SEP01 08:00, P6=19SEP01 08:00 Late Start Date mismatch: P3=26SEP01 08:00, P6=04OCT01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=02OCT01 17:00 Late Finish Date mismatch: P3=09OCT01 17:00, P6=17OCT01 17:00 Activity W1-175, CARPETING/BASE Late Start Date mismatch: P3=01OCT01 08:00, P6=14SEP01 08:00 Late Finish Date mismatch: P3=09OCT01 17:00, P6=24SEP01 17:00 Activity W1-176, PLUMBING FIXTURES - BATH Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity W1-184, TOUCH-UP PAINT Early Start Date mismatch: P3=21SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=05OCT01 08:00, P6=15OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=04OCT01 17:00 Late Finish Date mismatch: P3=11OCT01 17:00, P6=19OCT01 17:00 Activity W1-186, WORK TO COMPLETE LIST / CORRECTIONS Early Finish Date mismatch: P3=28SEP01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity W1-194, SIGNAGE Early Start Date mismatch: P3=26SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=10OCT01 08:00, P6=18OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=11OCT01 17:00, P6=19OCT01 17:00 Activity W1-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W1-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=06SEP01 17:00, P6=12SEP01 17:00 Late Finish Date mismatch: P3=19SEP01 17:00, P6=27SEP01 17:00 Activity W1-199, A/E PUNCHLIST Early Start Date mismatch: P3=01OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=05OCT01 17:00, P6=23OCT01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity W1-208, INSTALL SOLID POLYMER FABRICATIONS Early Finish Date mismatch: P3=07SEP01 17:00, P6=13SEP01 17:00 Late Finish Date mismatch: P3=02OCT01 17:00, P6=10OCT01 17:00 Activity W1-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=19SEP01 08:00, P6=25SEP01 08:00 Late Start Date mismatch: P3=03OCT01 08:00, P6=11OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=04OCT01 17:00, P6=12OCT01 17:00 Activity W1-285, INSTALL ACCORDION FIRE DOORS Early Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity W2-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=29OCT01 08:00, P6=14NOV01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=27NOV01 17:00, P6=13DEC01 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W2-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=17OCT00 17:00, P6=18OCT00 08:00 Activity W2-147, PLUMBING FIXTURES - ALL AREAS (EXCL. BATH) Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=03DEC01 08:00, P6=11DEC01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=14DEC01 17:00, P6=26DEC01 17:00 Activity W2-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity W2-158, MILLWORK/CASEWORK Early Start Date mismatch: P3=24SEP01 08:00, P6=28SEP01 08:00 Late Start Date mismatch: P3=23OCT01 08:00, P6=31OCT01 08:00 Early Finish Date mismatch: P3=25SEP01 17:00, P6=01OCT01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity W2-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=13SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity W2-164, FLOORING/BASE Late Start Date mismatch: P3=31OCT01 08:00, P6=08NOV01 08:00 Late Finish Date mismatch: P3=05NOV01 17:00, P6=13NOV01 17:00 Activity W2-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity W2-168, ACOUSTICAL PANELS Early Start Date mismatch: P3=14SEP01 08:00, P6=20SEP01 08:00 Late Start Date mismatch: P3=04OCT01 08:00, P6=12OCT01 08:00 Early Finish Date mismatch: P3=20SEP01 17:00, P6=26SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity W2-170, INSTALL VISUAL DISPLAY BOARDS Early Finish Date mismatch: P3=19SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity W2-172, HANG/SWING DOORS Early Start Date mismatch: P3=19SEP01 08:00, P6=25SEP01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=19OCT01 08:00 Early Finish Date mismatch: P3=02OCT01 17:00, P6=08OCT01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity W2-173, PULL WIRE/TIE/TRIM TELECOM Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity W2-175, CARPETING/BASE Late Start Date mismatch: P3=22OCT01 08:00, P6=05OCT01 08:00 Late Finish Date mismatch: P3=30OCT01 17:00, P6=15OCT01 17:00 Activity W2-176, PLUMBING FIXTURES - KITCHEN Early Start Date mismatch: P3=04SEP01 08:00, P6=10SEP01 08:00 Late Start Date mismatch: P3=03DEC01 08:00, P6=11DEC01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=14DEC01 17:00, P6=26DEC01 17:00 Activity W2-184, TOUCH-UP PAINT Early Start Date mismatch: P3=28SEP01 08:00, P6=04OCT01 08:00 Late Start Date mismatch: P3=25OCT01 08:00, P6=02NOV01 08:00 Early Finish Date mismatch: P3=04OCT01 17:00, P6=10OCT01 17:00 Late Finish Date mismatch: P3=31OCT01 17:00, P6=08NOV01 17:00 Activity W2-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=24SEP01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=08OCT01 08:00, P6=16OCT01 08:00 Early Finish Date mismatch: P3=19OCT01 17:00, P6=06NOV01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity W2-194, SIGNAGE Early Start Date mismatch: P3=03OCT01 08:00, P6=09OCT01 08:00 Late Start Date mismatch: P3=18OCT01 08:00, P6=26OCT01 08:00 Early Finish Date mismatch: P3=04OCT01 17:00, P6=10OCT01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity W2-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W2-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=07SEP01 17:00, P6=13SEP01 17:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity W2-199, A/E PUNCHLIST Early Start Date mismatch: P3=22OCT01 08:00, P6=07NOV01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=13NOV01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity W2-208, INSTALL SOLID POLYMER FABRICATIONS Early Finish Date mismatch: P3=21SEP01 17:00, P6=27SEP01 17:00 Late Finish Date mismatch: P3=22OCT01 17:00, P6=30OCT01 17:00 Activity W2-211, INSTALL ACCESS DOORS Early Start Date mismatch: P3=04SEP01 08:00, P6=06SEP01 08:00 Late Start Date mismatch: P3=04OCT01 08:00, P6=12OCT01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity W2-214, INSTALL APPLIANCES Early Start Date mismatch: P3=12SEP01 08:00, P6=18SEP01 08:00 Late Start Date mismatch: P3=04OCT01 08:00, P6=12OCT01 08:00 Early Finish Date mismatch: P3=13SEP01 17:00, P6=19SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity W2-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=26SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=11OCT01 08:00, P6=19OCT01 08:00 Early Finish Date mismatch: P3=27SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=12OCT01 17:00, P6=22OCT01 17:00 Activity W3-000, PUNCHLIST CORRECTIONS Early Start Date mismatch: P3=12NOV01 08:00, P6=06DEC01 08:00 Late Start Date mismatch: P3=28NOV01 08:00, P6=06DEC01 08:00 Early Finish Date mismatch: P3=11DEC01 17:00, P6=08JAN02 17:00 Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W3-100, DELIVER H.M FRAMES ** Actual Finish Date mismatch: P3=31OCT00 17:00, P6=01NOV00 08:00 Activity W3-145, COUNTER SUPPORTS Early Finish Date mismatch: P3=05SEP01 17:00, P6=11SEP01 17:00 Late Finish Date mismatch: P3=05OCT01 17:00, P6=15OCT01 17:00 Activity W3-147, PLUMBING FIXTURES - ALL AREAS (EXCL. BATH) Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=03DEC01 08:00, P6=11DEC01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=14DEC01 17:00, P6=26DEC01 17:00 Activity W3-151, INSTALL FIRE EXTINGUISHER CABINETS Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity W3-158, MILLWORK/CASEWORK Early Start Date mismatch: P3=26SEP01 08:00, P6=02OCT01 08:00 Late Start Date mismatch: P3=26OCT01 08:00, P6=05NOV01 08:00 Early Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity W3-162, MECHANICAL / PLUMB TRIM & FINISHES Early Finish Date mismatch: P3=13SEP01 17:00, P6=24SEP01 17:00 Late Finish Date mismatch: P3=29OCT01 17:00, P6=06NOV01 17:00 Activity W3-164, FLOORING/BASE Late Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Late Finish Date mismatch: P3=15NOV01 17:00, P6=27NOV01 17:00 Activity W3-166, INTERIOR FRAMES/GLASS/GLAZE Early Finish Date mismatch: P3=12SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity W3-167, ELECTRICAL TRIM & FINISHES Early Start Date mismatch: P3=04SEP01 08:00, P6=13SEP01 08:00 Late Start Date mismatch: P3=09OCT01 08:00, P6=17OCT01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=03OCT01 17:00 Late Finish Date mismatch: P3=29OCT01 17:00, P6=06NOV01 17:00 Activity W3-168, ACOUSTICAL PANELS Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=18OCT01 08:00, P6=26OCT01 08:00 Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=24OCT01 17:00, P6=01NOV01 17:00 Activity W3-170, INSTALL VISUAL DISPLAY BOARDS Early Finish Date mismatch: P3=19SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity W3-171, FIRE ALARM/FLS TRIM/FINISHES Early Finish Date mismatch: P3=07SEP01 17:00, P6=13SEP01 17:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=24OCT01 17:00 Activity W3-172, HANG/SWING DOORS Early Start Date mismatch: P3=18SEP01 08:00, P6=27SEP01 08:00 Late Start Date mismatch: P3=25OCT01 08:00, P6=02NOV01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=10OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity W3-173, PULL WIRE/TIE/TRIM TELECOM Early Finish Date mismatch: P3=04SEP01 17:00, P6=10SEP01 17:00 Late Finish Date mismatch: P3=16OCT01 17:00, P6=24OCT01 17:00 Activity W3-175, CARPETING/BASE Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Late Finish Date mismatch: P3=13NOV01 17:00, P6=21NOV01 17:00 Activity W3-176, PLUMBING FIXTURES - BATH/KITCHEN Early Start Date mismatch: P3=11SEP01 08:00, P6=17SEP01 08:00 Late Start Date mismatch: P3=03DEC01 08:00, P6=11DEC01 08:00 Early Finish Date mismatch: P3=24SEP01 17:00, P6=28SEP01 17:00 Late Finish Date mismatch: P3=14DEC01 17:00, P6=26DEC01 17:00 Activity W3-180, PLASTIC LAMINATE FABRICATIONS Early Start Date mismatch: P3=12SEP01 08:00, P6=19SEP01 08:00 Late Start Date mismatch: P3=15OCT01 08:00, P6=23OCT01 08:00 Early Finish Date mismatch: P3=18SEP01 17:00, P6=25SEP01 17:00 Late Finish Date mismatch: P3=19OCT01 17:00, P6=29OCT01 17:00 Activity W3-182, TOILET COMPARTMENTS & ACCESSORIES Early Start Date mismatch: P3=14SEP01 08:00, P6=21SEP01 08:00 Late Start Date mismatch: P3=17OCT01 08:00, P6=25OCT01 08:00 Early Finish Date mismatch: P3=25SEP01 17:00, P6=02OCT01 17:00 Late Finish Date mismatch: P3=26OCT01 17:00, P6=05NOV01 17:00 Activity W3-184, TOUCH-UP PAINT Early Start Date mismatch: P3=04OCT01 08:00, P6=10OCT01 08:00 Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Early Finish Date mismatch: P3=10OCT01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=09NOV01 17:00, P6=19NOV01 17:00 Activity W3-186, WORK TO COMPLETE LIST / CORRECTIONS Early Start Date mismatch: P3=08OCT01 08:00, P6=30OCT01 08:00 Late Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Early Finish Date mismatch: P3=02NOV01 17:00, P6=28NOV01 17:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity W3-194, SIGNAGE Early Start Date mismatch: P3=27SEP01 08:00, P6=08OCT01 08:00 Late Start Date mismatch: P3=01NOV01 08:00, P6=09NOV01 08:00 Early Finish Date mismatch: P3=28SEP01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=02NOV01 17:00, P6=12NOV01 17:00 Activity W3-195, AREA COMPLETE Late Finish Date mismatch: P3=27DEC01 17:00, P6=08JAN02 17:00 Activity W3-198, INSTALL ALUMINUM FRAMES/DOORS Early Finish Date mismatch: P3=05SEP01 17:00, P6=18SEP01 17:00 Late Finish Date mismatch: P3=17OCT01 17:00, P6=25OCT01 17:00 Activity W3-199, A/E PUNCHLIST Early Start Date mismatch: P3=05NOV01 08:00, P6=29NOV01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=09NOV01 17:00, P6=05DEC01 17:00 Late Finish Date mismatch: P3=27NOV01 17:00, P6=05DEC01 17:00 Activity W3-208, INSTALL SOLID POLYMER FABRICATIONS Early Finish Date mismatch: P3=03OCT01 17:00, P6=09OCT01 17:00 Late Finish Date mismatch: P3=13NOV01 17:00, P6=21NOV01 17:00 Activity W3-211, INSTALL ACCESS DOORS Early Start Date mismatch: P3=04SEP01 08:00, P6=06SEP01 08:00 Late Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Early Finish Date mismatch: P3=05SEP01 17:00, P6=07SEP01 17:00 Late Finish Date mismatch: P3=23OCT01 17:00, P6=31OCT01 17:00 Activity W3-214, INSTALL APPLIANCES Early Start Date mismatch: P3=13SEP01 08:00, P6=19SEP01 08:00 Late Start Date mismatch: P3=22OCT01 08:00, P6=30OCT01 08:00 Early Finish Date mismatch: P3=14SEP01 17:00, P6=20SEP01 17:00 Late Finish Date mismatch: P3=23OCT01 17:00, P6=31OCT01 17:00 Activity W3-215, INSTALL WINDOW COVERINGS Early Start Date mismatch: P3=20SEP01 08:00, P6=01OCT01 08:00 Late Start Date mismatch: P3=25OCT01 08:00, P6=02NOV01 08:00 Early Finish Date mismatch: P3=26SEP01 17:00, P6=05OCT01 17:00 Late Finish Date mismatch: P3=31OCT01 17:00, P6=08NOV01 17:00 Activity W3-284, FINAL PAINT Early Finish Date mismatch: P3=10SEP01 17:00, P6=14SEP01 17:00 Late Finish Date mismatch: P3=10OCT01 17:00, P6=18OCT01 17:00 Activity XF000, A/E PUNCHLIST & CORRECTIONS Early Start Date mismatch: P3=02OCT01 08:00, P6=28NOV01 08:00 Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Early Finish Date mismatch: P3=29OCT01 17:00, P6=27DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity XF010A, PLACE SUNSCREEN SUPPORTS - BOSTROM Late Start Date mismatch: P3=17SEP01 08:00, P6=25SEP01 08:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity XF030, MISC. EXTERIOR PAINT Late Finish Date mismatch: P3=02OCT01 17:00, P6=10OCT01 17:00 Activity XF039, FABRICATE SUNSCREEN Late Finish Date mismatch: P3=14SEP01 17:00, P6=24SEP01 17:00 Activity XF040, INSTALL SUNSCREENS Late Start Date mismatch: P3=17SEP01 08:00, P6=25SEP01 08:00 Late Finish Date mismatch: P3=28SEP01 17:00, P6=08OCT01 17:00 Activity XF050, EXTERIOR ELECTRICAL FIXTURES Late Start Date mismatch: P3=08JAN02 08:00, P6=13NOV01 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=19NOV01 17:00 Activity XF060, MISC. EXTERIOR FINISHES Late Start Date mismatch: P3=28DEC01 08:00, P6=06NOV01 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=19NOV01 17:00 Activity XF070, McCARTHY PUNCHLIST & CORRECTIONS Early Finish Date mismatch: P3=24SEP01 17:00, P6=16NOV01 17:00 Late Finish Date mismatch: P3=04DEC01 17:00, P6=12DEC01 17:00 Activity XF199, A/E PUNCHLIST Early Start Date mismatch: P3=25SEP01 08:00, P6=19NOV01 08:00 Late Start Date mismatch: P3=05DEC01 08:00, P6=13DEC01 08:00 Early Finish Date mismatch: P3=01OCT01 17:00, P6=27NOV01 17:00 Late Finish Date mismatch: P3=11DEC01 17:00, P6=19DEC01 17:00 Activity XF999, BUILDING EXTERIOR COMPLETE Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity XN007, INSTALL EXPANSION JOINTS - NORTH Late Finish Date mismatch: P3=14JAN02 17:00, P6=19NOV01 17:00 Activity XS007, INSTALL EXPANSION JOINTS - SOUTH Late Finish Date mismatch: P3=14JAN02 17:00, P6=19NOV01 17:00 Activity Z99, PROJECT COMPLETE Early Start Date mismatch: P3=15JAN02 08:00, P6=23JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity Z999, DEMOBILIZATION Early Start Date mismatch: P3=08JAN02 08:00, P6=16JAN02 08:00 Late Start Date mismatch: P3=08JAN02 08:00, P6=16JAN02 08:00 Early Finish Date mismatch: P3=14JAN02 17:00, P6=23JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ076, FINAL ELEVATOR - AGENCY TESTING Late Start Date mismatch: P3=03DEC01 08:00, P6=11DEC01 08:00 Late Finish Date mismatch: P3=07DEC01 17:00, P6=17DEC01 17:00 Activity ZZ090, FINAL HW/CHILLER WATER BALANCE Early Finish Date mismatch: P3=10SEP01 17:00, P6=16OCT01 17:00 Late Finish Date mismatch: P3=07NOV01 17:00, P6=15NOV01 17:00 Activity ZZ090A, FINAL HW/CHILLER WATER BALANCE - CONF. CNTR Late Start Date mismatch: P3=12NOV01 08:00, P6=20NOV01 08:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity ZZ100, FINAL AHU BALANCE Early Start Date mismatch: P3=09OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=08NOV01 08:00, P6=16NOV01 08:00 Early Finish Date mismatch: P3=05NOV01 17:00, P6=13NOV01 17:00 Late Finish Date mismatch: P3=07DEC01 17:00, P6=17DEC01 17:00 Activity ZZ101, COMPL CURSORY REVIEW SFM/LOCAL FM's Early Start Date mismatch: P3=15OCT01 08:00, P6=17OCT01 08:00 Late Start Date mismatch: P3=05NOV01 08:00, P6=13NOV01 08:00 Early Finish Date mismatch: P3=26OCT01 17:00, P6=30OCT01 17:00 Late Finish Date mismatch: P3=16NOV01 17:00, P6=28NOV01 17:00 Activity ZZ103, SFM/LOCAL FM's SIGN-OFF Early Start Date mismatch: P3=05DEC01 08:00, P6=07DEC01 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Early Finish Date mismatch: P3=18DEC01 17:00, P6=20DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ104, RUN TEST HVAC / LOAD TEST & THERMOSTATS Early Start Date mismatch: P3=15NOV01 08:00, P6=19NOV01 08:00 Late Start Date mismatch: P3=17DEC01 08:00, P6=27DEC01 08:00 Early Finish Date mismatch: P3=21NOV01 17:00, P6=27NOV01 17:00 Late Finish Date mismatch: P3=21DEC01 17:00, P6=04JAN02 17:00 Activity ZZ108, PREPARE/SUBMIT FINAL BALANCING REPORTS Early Start Date mismatch: P3=03DEC01 08:00, P6=05DEC01 08:00 Late Start Date mismatch: P3=26DEC01 08:00, P6=07JAN02 08:00 Early Finish Date mismatch: P3=14DEC01 17:00, P6=18DEC01 17:00 Late Finish Date mismatch: P3=10JAN02 17:00, P6=18JAN02 17:00 Activity ZZ109, PREPARE/SUBMIT PROJECT AS-BUILT's Early Start Date mismatch: P3=19NOV01 08:00, P6=21NOV01 08:00 Late Start Date mismatch: P3=12DEC01 08:00, P6=20DEC01 08:00 Early Finish Date mismatch: P3=11DEC01 17:00, P6=13DEC01 17:00 Late Finish Date mismatch: P3=07JAN02 17:00, P6=15JAN02 17:00 Activity ZZ110, BMCS INTEGRATION-CONTROL SYSTEMS TESTING Early Start Date mismatch: P3=15NOV01 08:00, P6=19NOV01 08:00 Late Start Date mismatch: P3=10DEC01 08:00, P6=18DEC01 08:00 Early Finish Date mismatch: P3=30NOV01 17:00, P6=04DEC01 17:00 Late Finish Date mismatch: P3=21DEC01 17:00, P6=04JAN02 17:00 Activity ZZ111, BMCS - EQUIPMENT CONSOLE HOOK-UP AND TESTING Early Finish Date mismatch: P3=17SEP01 17:00, P6=21SEP01 17:00 Late Finish Date mismatch: P3=07DEC01 17:00, P6=17DEC01 17:00 Activity ZZ112, FA/FLS - DUCT DETECTOR TESTING Early Start Date mismatch: P3=15NOV01 08:00, P6=19NOV01 08:00 Late Start Date mismatch: P3=10DEC01 08:00, P6=18DEC01 08:00 Early Finish Date mismatch: P3=30NOV01 17:00, P6=04DEC01 17:00 Late Finish Date mismatch: P3=21DEC01 17:00, P6=04JAN02 17:00 Activity ZZ116, CLOSEOUT DOCUMENTATION/OWNER TRAINING Early Start Date mismatch: P3=05DEC01 08:00, P6=07DEC01 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Early Finish Date mismatch: P3=18DEC01 17:00, P6=20DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ118, PRE-OCCUPANCY BLDG PURGES Early Start Date mismatch: P3=08NOV01 08:00, P6=12NOV01 08:00 Late Start Date mismatch: P3=19DEC01 08:00, P6=02JAN02 08:00 Early Finish Date mismatch: P3=30NOV01 17:00, P6=04DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ119, OWNER FILE FOR COMPLETION Early Start Date mismatch: P3=12DEC01 08:00, P6=09JAN02 08:00 Late Start Date mismatch: P3=28DEC01 08:00, P6=09JAN02 08:00 Early Finish Date mismatch: P3=27DEC01 17:00, P6=22JAN02 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ120, FINAL AHU AIR BALANCE - CONF CENTER Early Start Date mismatch: P3=29OCT01 08:00, P6=31OCT01 08:00 Late Start Date mismatch: P3=19NOV01 08:00, P6=29NOV01 08:00 Early Finish Date mismatch: P3=14NOV01 17:00, P6=16NOV01 17:00 Late Finish Date mismatch: P3=07DEC01 17:00, P6=17DEC01 17:00 Activity ZZ121, TELECOM SYSTEMS TESTING Early Start Date mismatch: P3=15NOV01 08:00, P6=19NOV01 08:00 Late Start Date mismatch: P3=10DEC01 08:00, P6=18DEC01 08:00 Early Finish Date mismatch: P3=18DEC01 17:00, P6=20DEC01 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ139, PUNCHLIST BACKCHECK Early Start Date mismatch: P3=10DEC01 08:00, P6=07JAN02 08:00 Late Start Date mismatch: P3=11JAN02 08:00, P6=21JAN02 08:00 Early Finish Date mismatch: P3=11DEC01 17:00, P6=08JAN02 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ415, INCLEMENT WEATHER DAYS DUE = 15 Early Start Date mismatch: P3=15JAN02 08:00, P6=23JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ421, FINAL CLEAN UP Early Start Date mismatch: P3=30NOV01 08:00, P6=26DEC01 08:00 Late Start Date mismatch: P3=19DEC01 08:00, P6=02JAN02 08:00 Early Finish Date mismatch: P3=20DEC01 17:00, P6=17JAN02 17:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 Activity ZZ99, CONTRACT COMPLETION - MUST FINISH BY Late Start Date mismatch: P3=14JAN02 08:00, P6=22JAN02 08:00 Late Finish Date mismatch: P3=14JAN02 17:00, P6=22JAN02 17:00 P6 TYPE 1 ERROR LISTING, WRONG COMPUTED DATES FOR 0-DURATION ACTIVITIES Activity AF-195, AREA COMPLETE (adjusted Early Finish dates) Activity C1-195, AREA COMPLETE (adjusted Early Finish dates) Activity CRB#1-C, PARTITIONS AT 2ND FLOOR EAST (adjusted Late Start dates) Activity CRB#1-D, PARTITIONS AT 3RD FLOOR EAST (adjusted Late Start dates) Activity E1-195, AREA COMPLETE (adjusted Early Finish dates) Activity E2-195, AREA COMPLETE (adjusted Early Finish dates) Activity E3-195, AREA COMPLETE (adjusted Early Finish dates) Activity EB-195, AREA COMPLETE (adjusted Early Finish dates) Activity EL1-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST (adjusted Early Finish dates) Activity EL2-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST (adjusted Early Finish dates) Activity EL3-J, ELEVATOR COMPLETE - AVAILABLE FOR FNL TEST (adjusted Early Finish dates) Activity OS-999, OFF-SITE WORK COMPLETE (adjusted Late Start dates) Activity OS-999, OFF-SITE WORK COMPLETE (adjusted Early Finish dates) Activity STAIR#1-F, STAIRWELL #1 COMPLETE (adjusted Early Finish dates) Activity STAIR#2-F, STAIRWELL #2 COMPLETE (adjusted Early Finish dates) Activity STAIR#3-F, STAIRWELL #3 COMPLETE (adjusted Early Finish dates) Activity STAIR#4-F, STAIRWELL #4 COMPLETE (adjusted Early Finish dates) Activity STAIR#5-F, STAIRWELL #5 COMPLETE (adjusted Early Finish dates) Activity SU999, SITE UTILITIES COMPLETE (adjusted Late Start dates) Activity SU999, SITE UTILITIES COMPLETE (adjusted Early Finish dates) Activity SW-999, SITE IMPROVEMENTS COMPLETE (adjusted Late Start dates) Activity SW-999, SITE IMPROVEMENTS COMPLETE (adjusted Early Finish dates) Activity W1-195, AREA COMPLETE (adjusted Early Finish dates) Activity W2-195, AREA COMPLETE (adjusted Early Finish dates) Activity W3-195, AREA COMPLETE (adjusted Early Finish dates) Activity XF999, BUILDING EXTERIOR COMPLETE (adjusted Early Finish dates) Activity Z99, PROJECT COMPLETE (adjusted Late Start dates) Activity Z99, PROJECT COMPLETE (adjusted Early Finish dates) Activity ZZ415, INCLEMENT WEATHER DAYS DUE = 15 (adjusted Late Start dates) Activity ZZ415, INCLEMENT WEATHER DAYS DUE = 15 (adjusted Early Finish dates) A total of 411 mismatches were found in this section. ============================ RELATIONSHIP DATA ============================ No comparison errors were found. ========================== ACTIVITY RESOURCE DATA ========================== P3 Activity: AF-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: AF-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: C1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: C1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-B, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-B, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-C, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-C, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-D, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#1-D, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#22, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#22, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#3, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#3, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#4-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#4-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#4-B, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: CRB#4-B, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E1-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E1-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E2-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E2-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E2-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E2-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E3-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E3-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E3-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: E3-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EB-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EB-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EB-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EB-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL1-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL1-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL2-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL2-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL3-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: EL3-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#11, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#11, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#14, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#14, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#92-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI#92-A, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SU-015, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SU-015, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SU-045, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SU-045, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-020, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-020, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-030, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-030, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-040, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-040, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-045, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-045, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-050, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-050, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-071, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-071, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-080, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-080, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-090, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-090, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-112, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-112, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-114, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-114, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-140, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-140, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-141, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: FI92SW-141, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: ML-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: ML-J, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: PP128, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: PP128, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: RFI#214, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: RFI#214, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: RFI#67.1, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: RFI#67.1, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#1-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#1-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#2-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#2-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#3-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#3-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#4-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#4-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#5-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: STAIR#5-F, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: SW-040, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: SW-045, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: SW-130, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: SW-140, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: SW-141, Resource: was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W1-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W1-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W1-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W2-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W2-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W2-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W2-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W3-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W3-100, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W3-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: W3-195, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: XF999, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. P3 Activity: XF999, Resource: 1 was not found in the P6 schedule. Note: P3 activity resource was assigned but values were equal to zero. A total of 115 mismatches were found in this section. ======================== ACTIVITY COST/EXPENSE DATA ======================== TASK EXPENSES No comparison errors were found. TASK RESOURCE COSTS P3 Activity/Resource/Cost P060-B/1/(missing) is missing from the P6 schedule. Note: P3 activity cost was assigned but values were equal to zero. P3 Activity/Resource/Cost P060-D/1/(missing) is missing from the P6 schedule. Note: P3 activity cost was assigned but values were equal to zero. P3 Activity/Resource/Cost P060-E/1/(missing) is missing from the P6 schedule. Note: P3 activity cost was assigned but values were equal to zero. P3 Activity/Resource/Cost SSW02/1/(missing) is missing from the P6 schedule. Note: P3 activity cost was assigned but values were equal to zero. A total of 4 mismatches were found in this section. ============================ ACTIVITY CODE DATA ============================ No comparison errors were found. ================================== RECAP ================================== Project Mismatches: 28 Activity Mismatches: 411 Relationship Mismatches: 0 Resource Mismatches: 115 Cost Mismatches: 4 Activity Code Mismatches: 0 ======================= P3 TO P6 COMPARISON COMPLETE =======================