Schedule Analyzer Forensic As-Built Float Calculator
P3 Schedule: C:\P3WIN\PROJECTS\1221
Dates Covered: 11NOV99 to 09DEC99
Note: Shaded Cells (not in bold) are also on the Longest Path.
Act ID Description 11-Nov-99 12-Nov-99 13-Nov-99 14-Nov-99 15-Nov-99 16-Nov-99 17-Nov-99 18-Nov-99 19-Nov-99 20-Nov-99 21-Nov-99 22-Nov-99 23-Nov-99 24-Nov-99 25-Nov-99 26-Nov-99 27-Nov-99 28-Nov-99 29-Nov-99 30-Nov-99 1-Dec-99 2-Dec-99 3-Dec-99 4-Dec-99 5-Dec-99 6-Dec-99 7-Dec-99 8-Dec-99 9-Dec-99
      2510 Roadside Signs Stage 1 27 16 15 15 15 14 13 12 11 10 10 2 1 11 0 0 0 0 0 0 0 0 0 0 0 0 0 1 2
      2480 AC Dike Stage 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
      2360 Structure Backfill OH Abut 0
      1590 Road Ex E6 Stage 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
      1330 OC Approach Fills 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
      1260 OC Abutments 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
      1220 OC F/W Review 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 12 12 12
       720 Import Borrow E3 38 27 27 27 27 27 27 27 27 27 27 19 19 30 20 20 21 21 21 22 23 24 24 24 24 24 24 25 26
       600 White Bock OH L&R Rails 0 0 0 0 0 0 0 0 0 0 0 0 0
       590 White Bock OH L&R Approach Slabs Stage 1 0 -11 -11 -11 -11 -11 -11 -11 -11 -11 -11 -11 -11 0
       570 White Bock OH R Release F/W 121 121 120 120 120 119 118 117 116
       530 White Bock OH L Release F/W 8 8 8 8 8 8
      1550 Road Ex E5 Stage 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
       540 White Bock OH L Settlement Period 154 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171
       580 White Bock OH R Settlement Period 160 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171 171
      2490 Striping & Markers Stage 1 0
      1280 OC F/W 5 5 5 5 5 12 12 12