Schedule Analyzer eForensic Upgrade Information

 
 
 
  Below is the entire update history of Schedule Analyzer for the Enterprise Forensic (eForensic). The current version is listed at the top. Registered, licensed Users are encouraged to look-up the version of their eForensic software and reference the current updates here.
 
Key:
ALL: All eForensic programs.
BENCHMARK: Greatly enhanced Out-of-Sequence and added the Duration Report and Lag Report (01JUN18).
CATALOGER: eForensic Schedule Cataloger (released November 2008.)
COMPARE: eForensic Compare P3 to P6 (added May 2010.)
CONFORMER: eForensic Conform Schedules (added March 2009).
CORRUPT: eForensic Corrupt Files (added March 2009.)
DATE CALC: eForensic Date Calculator (created 2003 and added to eForensic October 2008.)
HALF: eForensic Half-Step Schedule (added November 2011.)
INVESTIGATE: eForensic Record Investigator (added October 2008.)
MENU: Schedule Analyzer Enterprise Menu program (added August 2011.)
SEQUENCE: eForensic Out-of-Sequence Report (added January 2009.)
REBUILDER: eForensic Schedule Rebuilder (added April 2009.)
TRACE: eForensic Trace Logic (added July 2009.)
WORKDAY: eForensic Workday Calculator (added November 2008.)

 

Current Version CURRENT VERSION:
Version 2.28 (October 2023)
OVERVIEW: ADDED REPORT FEATURE TO OUT-OF-SEQUENCE REPORT
SEQUENCE: Added predecessor line to the list of out-of-sequence indirect activities.
Version 2.27 (April 2022)
OVERVIEW: SIMPLIFY HALF-STEP OPTIONS
HALFSTEP: Simplify options settings to make operation clearer.
Version 2.26 (April 2022)
OVERVIEW: IMPROVEMENTS TO HALF-STEP
HALFSTEP: Update options settings documentation in report.
HALFSTEP: Added Tool Tips to option settings in program setup.
HALFSTEP: Added Remaining Duration, Actual Start, and Actual Finish change valadation.
Version 2.25 (June 2021)
OVERVIEW: CAN TURN OFF VOICE PROMPTS
ALL: User can now turn off voice prompts.
BENCHMARK: Out-of-Sequence Report now explains if a calendar change made an early start appear to not be one.
Version 2.24 (April 2021)
OVERVIEW: ADDED SCREEN REFRESH
ALL: Added the File / Screen Refresh feature.
ALL: Updated splash screen.
Version 2.23 (March 2021)
OVERVIEW: MAJOR UPGRADE TO HALF-STEP OPTION SETTINGS
HALFSTEP: Corrected increasing remaining duration process.
CATALOG: Added full project name to all reports and catalogs.
CATALOG: Added external constraints to the list of cataloged items.
HALFSTEP: Added report on options statistics.
HALFSTEP: Improved the report formatting.
Version 2.22 (February 2021)
OVERVIEW: MAJOR UPGRADE TO HALF-STEP OPTION SETTINGS
HALFSTEP: Added twelve new option settings to organize around RP49R-03 MIP 3.4 requirements
HALFSTEP: Created new Half-Step Help Video.
Version 2.21 (January 2021)
OVERVIEW: FIXED HALF-STEP OPTION SETTINGS
HALFSTEP: Fixed error with Ignore Negatve Progress option setting in the Settings menu.
HALFSTEP: Fixed error with RD Change Neets Percent Complete Change option setting in the Settings menu.
Version 2.20 (November 2020)
OVERVIEW: ADDED NEW OPTION TO HALF-STEP
ALL: Updated the Admin manual to cover current Oracle logon options.
ALL: Fixed internal version control routines.
HALFSTEP: Added option to ignore negative progress.
HALFSTEP: Bullet-proofed quanity conversions.
Version 2.19 (July 2020)
OVERVIEW: INTERNAL DATE CONVERSION REPAIR
All: Cleaned-up text to date conversion process.
Version 2.18 (April 2020)
COMPARE P6 TO MICROSOFT PROJECT SCHEDULES
COMPARE P6: Added report to compare Microsoft Project (MSP) schedules to their P6 counterpart.
Version 2.17 (March 2020)
TWO BENCHMARK UPDATES
BENCHMARK: Added filter by activity code to Lag Analysis.
BENCHMARK: Added Milestone Report and statistics to Out-of-Sequence Report.
Version 2.16 (January 2020)
MAJOR INVESTIGATOR UPDATE
Removed MDAC 2.8 from loader redistributables.
INVESTIGATOR: Major update with adding records overview and project tampering check.
Version 2.15 (October 2019)
FIX FOR DURATION ANALYSIS IN BASELINE MODULE
BASELINE DURATION: Fixed report showing really low numbers for variations (missing data in the database).
BASELINE DURATION: Removed Smart Copy from edit menu in Report View.
Version 2.14 (September 2019)
ADDED MORE ABILITY FOR CORRUPT FILES TO FIX THE DAMAGE
CORRUPT: Added optional fix for missing relationship lag using Baseline schedules.
ALL: Bullet-proofed preventing screen opening outside of viewable area.
Version 2.13 (August 2019)
HALF-STEP IMPROVEMENTS
HALF: Allowed for increasing remaining duration.
HALF: Trim activity description to fit the width of the report.
CORRUPT: Added ORPHANED BASELINE SCHEDULES THAT ARE NOT VISIBLE Report
Version 2.12 (July 2019)
NEW CHECKS AND FIXES IN CORRUPT FILES
CORRUPT: Added NEXTKEY Table system check.
CORRUPT: Added repair option to NEXTKEY Table system check.
CORRUPT: Added repair option to POBS Table system check.
CORRUPT: Added Orphaned WBS Check
CORRUPT: Added repair Orphaned WBS check.
CORRUPT: Added view screen editing tools.
ALL: Newly formatted all Help videos.
ALL: Bullet-proofed timeout issues.
Version 2.11 (May 2019)
IMPROVMENT TO BENCHMARK MODULE
CORRUPT: Fixed non-responsive Reports View window.
Version 2.10 (May 2019)
SORT PROJECTS IN THE OPENING SCREEN ALL: Added ability to sort opening screen by any column. ALL: Completely collapse opening screen tree of schedules if Open Collapsed is set.
Version 2.09 (February 2019)
IMPROVMENT TO BENCHMARK MODULE
BENCHMARK: Fixed Lag report when grouping using successor activity codes.
CATALOGER: Fixed cataloging all XER files in a directory function.
Version 2.08 (January 2019)
SORT OPENING SCREEN PROJECTS LIKE P6
ALL: Improved listing of projects order.
CORRUPT: Corrected Project Integrity Check #21 project name printout and title.
CORRUPT: Added Orphaned Baseline Schedule Check.
Version 2.07 (December 2018)
ADDED CRITICALITY TO BENCHMARK LAG REPORT
BENCHMARK: Added critical activity flag to reports and stats.
BENCHMARK: Added critical relationship statistics.
BEMCHMARK: Improved baseline float look-up process.
BENCHMARK: Added Longest Path Value to critical lag determination.
Version 2.06 (November 2018)
MANY IMPROVMENTS TO BENCHMARK LAG REPORT
BENCHMARK: Large number of formatting improvements to Lag Report.
BENCHMARK: Added percent late to Lag Report statistics.
BENCHMARK: Added lag statistics to save spreadsheet function.
BENCHMARK: Corrected the number of late relationships stat in the Lag Report.
BENCHMARH: Added Spreadsheet Detail Charts for Lag Report.
BENCHMARK: Added make spreadsheet to the Lag Report.
BENCHMARK: Added Report Complete message boxes with help on further analyses.
Version 2.05 (October 2018)
NEW DAILY PROFILE CHARTS IN OUT-OF-SEQUENCE
TRACE: Prevented error message saying CPM not computed by excluding LOE & WBS activities from report.
BENCHMARK: Improved Charting of History Profile statistics in Out-of-Sequence.
BENCHMARK: Added Daily Percent of Out-of-Sequence to Total Activities chart to Out-of-Sequence.
BENCHMARK: Added Daily Ratio of Events to Out-of-Sequence chart to Out-of-Sequence.
TRACE: Made Quit tracing at completed activity the default option (for speed).
Version 2.04 (September 2018)
FIXED ACTIVITY TITLE REPORTING IN OUT-OF-SEQUENCE
BENCHMARK: Reformatted statistics section in Out-of-Sequence.
BENCHMARK: Fixed report width adjust routine.
BENCHMARK: Fixed Out-of-Sequence missing activity titles in reports.
Version 2.03 (August 2018)
ADDED HISTORICAL INDIRECT REPORTING TO OUT-OF-SEQUENCE
BENCHMARK: Extended Out-of-Sequence reporting to include all types, including Historical Indirect.
BENCHMARK: Fixed Out-of-Sequence "Calendar missing" error when schedules have Baseline Schedules.
Version 2.02 (July 2018)
ADDED COMPLETE FLOAT REPORTING TO OUT-OF-SEQUENCE
BENCHMARK: Out-of-Sequence re-format Total Float reporting.
BENCHMARK: Out-of-Sequence add Baseline Schedule Total Float look-up.
BENCHMARK: Out-of-Sequence add filter by total float option.
HALF-STEP: Added check and correction if Task Type was Resource to prevent OD change.
Version 2.01 (July 2018)
INTRODUCED TOTAL FLOAT REPORTING IN OUT-OF-SEQUENCE
HALFSTEP: Cosmetic fixes to diagnostic report.
BENCHMARK: Out-of-Sequence only reports schedule name if more than one schedule is selected.
BENCHMARK: Out-of-Sequence stops double-counting some Indirect OOS.
BENCHMARK: Out-of-Sequence add P6's Active Direct & Indirects OOS count.
BENCHMARK: Out-of-Sequence add Total Float reporting.
Version 2.00 (June 2018)
BRAND-NEW BENCHMARKING TOOLS INTRODUCED
BENCHMARK: Added new As-Built Duration & Float benchmarking report.
BENCHMARK: Added new As-Built lag variation report.
BENCHMARK: Combined Out-of-Sequence Report with new Duration and Lag Reports.
MENU: Updated to include Benchmark.
REBUILD: New, updated video with added features.
Version 1.46 (May 2017)
IMPROVED INDIRECT OUT-OF-SEQUENCE REPORTING
SEQUENCE: Corrected spread duration of Indirect Profile Days.
SEQUENCE: Corrected Profile to accommodate that we do not count Indirect OOS sequences (assume 1 per indirect Act).
SEQUENCE: Added work days to Indirect OOS analysis.
SEQUENCE: Added Work Days Early to the Indirect Out-of-Sequence Activities Report.
SEQUENCE: Improved formatting of Indirect Out-of-Sequence Report.
SEQUENCE: Improved the formatting of Currently Active OOS Report.
SEQUENCE: Improved explanation of Report Size Overflow in the output.
Version 1.45 (April 2017)
ADDED INTERPROJECT OUT-OF-SEQUENCE CHECKS
REBUILD: Allow multiple projects that are interlinked to run at the same time.
SEQUENCE: Added interproject OOS statistics.
SEQUENCE: Correct spread duration of Profile Days.
Version 1.44 (April 2017)
OUT-OF-SEQUENCE REPORTER CAN NOW HAVE UNLIMITED REPORT LENGTHS
SEQUENCE: Added Lag Analysis feature.
MENU: Fixed Half Step video play.
SEQUENCE: Fixed blank saved report when report overflow was active.
SEQUENCE: Can now save unlimited report lengths.
SEQUENCE: Report formatting improvements.
CATALOGER: Fixed INI location error
SEQUENCE: Only profile working days.
Version 1.43 (February 2017)
ADDED NEW STATISTICS AND FEATURES TO OUT-OF-SEQUENCE REPORT
ALL: New Splash Screen.
SEQUENCE: Added Summary Totals for Reason Types at the end of the report.
SEQUENCE: Added reporting on the number of currently active out-of-sequence events (predecessor does not have an Actual Finish).
SEQUENCE: Added Current Activity notice.
SEQUENCE: Added current out-of-sequence activity listing to summary.
SEQUENCE: Added Task Tags feature to identify OOS activities in P6 schedule.
SEQUENCE: Added Chart Out-of-Sequence Schedule History feature.
SEQUENCE: Added Filter Report by Activity Code feature.
SEQUENCE: Added Filter Report to exclude small early starts from the report.
SEQUENCE: Changed lag conversion factor to predecessor's calendar setting.
SEQUENCE: Added a filter to only report on active out-of-sequence events as of a certain date.
ALL: Better login error reporting.
ALL: Added Oracle login Integrated Security settings.
SEQUENCE: Added Indirect Out-of-Sequence Report.
SEQUENCE: Added Retained Logic check.
SEQUENCE: Protected from error where report width is less that the minimum print width.
SEQUENCE: Prevented report overflow error.
SEQUENCE: Split up report into 4 optional areas.
ALL: Fixed calendar growing too large.
Version 1.42 (November 2017)
SPEED-UP THE LOADING OF SCHEDULES
ALL: Speed up the initial loading of schedules to analyze.
ALL: Fix command line parameter passing for automatic Limit By OBS operation.
Version 1.41 (October 2017)
ADDED THREE NEW REPORTS TO CORRUPT FILES CHECKER
CORRUPT: Added check for Activity ID longer than allowed.
CORRUPT: Added check for Cost Account ID longer than allowed.
CORRUPT: Added check for Role ID longer than allowed.
Version 1.40 (October 2017)
IMPROVED REPORTING FORMAT FOR OUT OF SEQUENCE REPORTER
SEQUENCE: Improved report format and printed actual dates when available.
Version 1.39 (September 2017)
NEW USABILITY FEATURES FOR OUT OF SEQUENCE REPORTER
SEQUENCE: Added help in saving analysis after complete.
SEQUENCE: Improved error reporting when the relationship is corrupt.
SEQUENCE: Improved the formatting of the saved report.
SEQUENCE: Prevent closing View screen before the report is completely generated.
COMPARE: Prevent closing View screen before the report is completely generated.
CONFORMER: Prevent closing View screen before the report is completely generated.
HALFSTEP: Prevent closing View screen before the report is completely generated.
REBUILD: Prevent closing View screen before the report is completely generated.
RELATED: Prevent closing View screen before the report is completely generated.
Version 1.38 (May 2017)
ADDED NEW CORRUPT FILES FEATURE
ALL: Improved handling of forced program closure issues.
WORKDAY: Added new feature to draw wall calendars in Excel spreadsheets.
Version 1.37 (January 2017)
ADDED NEW CORRUPT FILES FEATURE
REBUILD: Added "Use Project Start Date" as the new Data Date button.
CORRUPT: Added duplicate project name check
Version 1.36 (December 2016)
ADDED NEW CORRUPT FILES FEATURES
CORRUPT: Return to main screen after the report is closed.
CORRUPT: Two new reports if Global/Project ID mismatch with Activity Codes.
CORRUPT: Two new reports if Global/Project ID mismatch with Calendars.
Version 1.35 (November 2016)
ADDED NEW CONFORMER AND CORRUPT FILES FEATURES
SEQUENCE: Improved accuracy to detect odd cases.
REBUILDER: Fixed 24-Hour calendar projected start calculation.
TRACER: Fixed 24-Hour calendar projected start calculation.
SEQUENCE: Fixed 24-Hour calendar projected start calculation.
WORKDAYS: Fixed 24-Hour calendar projected start calculation.
REBUILDER: New calendar string conversion due to new P6 Version 8.4 change in calendar formatting.
TRACER: New calendar string conversion due to new P6 Version 8.4 change in calendar formatting.
SEQUENCE: New calendar string conversion due to new P6 Version 8.4 change in calendar formatting.
WORKDAYS: New calendar string conversion due to new P6 Version 8.4 change in calendar formatting.
ALL: Added Smart Copy to View editor functions.
CONFORMER: Added Reports View button.
CONFORMER: Changed CHANGE IN ACTIVITY ORIGINAL DURATIONS OVER TIME Report to days.
CONFORMER: Changed report file extension from .txt to .SAF to better identity Conformer reports.
CORRUPT: Added check for Table PROJWBS status code token field.
CORRUPT: Added option to only display active projects.
Version 1.34 (October 2016)
BETTER STATISTICS IN OUT-OF-SEQUENCE REPORT
SEQUENCE: Corrected misspelling in report title.
SEQUENCE: Corrected end of report statistics to list number of activities and not instances.
ALL: Added Help guidance in Calendar Adjust settings.
ALL: Added Convert text report file to MS Word file in View window.
Version 1.33 (September 2016)
ADDED EXTRA CHECK TO HALF-STEP
HALF-STEP: Remove any Expected Finish dates from the modified schedule.
CONFORMER: Gave report file a .TXT file extension and made each run with a unique file name.
CONFORMER: Allow to not report on actuals on the data date when checking for actuals in the future.
Version 1.32 (August 2016)
IMPROVED COMPARE P3 TO P6
REBUILDER: Bad calendar fix.
CORRUPT: Added Database Name to report.
COMPARE: Fixed print function.
CONFORMER: Fixed print function.
HALFSTEP: Fixed print function.
REBUILDER: Fixed print function.
SEQUENCE: Fixed print function.
COMPARE: Fixed editor functions.
CONFORMER: Fixed editor functions.
HALFSTEP: Fixed editor functions.
REBUILDER: Fixed editor functions.
SEQUENCE: Fixed editor functions.
COMPARE: Fixed program hang when an extraordinary number of holidays are present.
COMPARE: Fixed failure to print activity line when P3 calendars were missing.
COMPARE: Fixed over-reporting.
Version 1.31 (July 2016)
IMPROVED CORRUPT FILES CHECKER
CATALOGER: Added Save function back into report view screen.
CORRUPT: Added Save function back into report view screen.
CORRUPT: Check for a legal file name.
CORRUPT: Remove false positives for primary resource without assignments for milestones.
CORRUPT: Remember where view windows was last time.
CORRUPT: Prevented report screen overflow error.
Version 1.30 (July 2016)
IMPROVED CORRUPT FILES CHECKER
ALL: Updated splash screen.
CORRUPT: Simplified the report viewing screen.
CORRUPT: Eliminated a Project Integrity Check that was a false-positive.
CORRUPT: Fixed over-reporting of 13. Check Activity Resource Assignment for: Assignment with resource Price/Time or Overtime Factor out of sync
CORRUPT: Added labeling database version to report.
CORRUPT: Added Report #65 to the after Schedule Integrity Check section.
Version 1.29 (February 2016)
FIXED TWO RUN TIME ERRORS
CORRUPT: Fixed Error: Incorrect syntax near ' '.
REBUILD: Fixed error where Oracle XER File was not recognized.
Version 1.28 (January 2016)
IMPROVED HALF-STEP ACCURACY
HALFSTEP: Added Settings option to update Remaining Duration even if Percent Complete did not change.
INVESTIGATOR: Fixed missing sae_AReports.avi error.
Version 1.27 (November 2015)
REMOVED CALENDAR READING ERROR
REBUILDER: Corrected problem reading new format of P6 calendar string.
WORKDAY: Corrected problem reading new format of P6 calendar string.
Version 1.26 (November 2015)
SIGNIFICANT IMPROVEMENTS TO CORRUPT FILES MODULE.
CORRUPT: fixed error in reading TASK table's control_upates_flag.
CORRUPT: Fixed ability to print View page.
CORRUPT: Added 70+ checks found in the P6 Version 7 Integrity Check (removed in P6 Version 8.)
Version 1.25 (September 2015)
UPDATED ALL SOFTWARE TO WORK UNDER WINDOWS 10.
CORRUPT: Added POBS Table check.
ALL: Updated system software to be compatible with Windows 10.
Version 1.24 (August 2015)
NUMEROUS CALENDAR ENHANCEMENTS FOR REBUILDER.
ALL: Added Limit by OBS as a command line parameter for large systems.
INVESTIGATOR: Added Limit Schedules by OBS feature.
REBUILDER: Display the name of the calendar being built.
REBUILDER: Fixed formatting of ACTIVITY RESOURCES WITH ACTUALS AFTER THE NEW DATA DATE Report.
REBUILDER: Warn user if Finish Late Hours setting is too high, leading to long build times and memory problems.
REBUILDER: Correct Actual Duration calculation error if finish on a weekend.
REBUILDER: Correct negative lag duration calculation.
Version 1.23 (March 2015)
ADDED LATE STARTS OPTION TO AS-PLANNED/AS-BUILT FEATURE.
REBUILDER: Added option to create Late Starts with the As-Planned/As-Built Options.
ALL: Updated system software for Windows 8 issues.
COMPARE: Significant improvements and error traps from grossly out of sync schedules added.
Version 1.22 (July 2014)
MANY ENHANCEMENTS TO TRACE LOGIC MODULE.
HALFSTEP: Prevented adding schedule origin information to every WBS element in the project.
ALL: Corrected display of Baseline Schedule Data dates on Main Screen.
HALFSTEP: Screen remembers last open status for next time.
CONFORMER: Allow report to be longer than 32,000 lines.
HALF-STEP: Allow report to be longer than 32,000 lines.
TRACE: Outline based on Activity ID and not project.
TRACE: Can save very large traces and quickly re-load them later.
TRACE: Can now pause trace and review current layout.
TRACE: Added option to stop tracing at first completed activity in a string.
TRACE: Added option to stop tracing at a given level.
TRACE: Improved export to Word and to text file presentation.
TRACE: Improved export to spreadsheet presentation.
Version 1.21 (June 2014)
CAN NOW SELECT SCHEDULES WITH THE EPS STARTING COLLAPSED FOR BREVITY.
CORRUPT: Added task planned duration, driving path token, can control updates tokens to list of data that is checked.
ALL: Added Show EPS in closed condition in startup options.
Version 1.20 (April 2014)
CHANGED INSTALLATION TO ACCOMODATE 64-BIT COMPUTERS.
ALL: Default install is moved out of program files directory.
CATALOG: Save file now works with MS Office Version 3013.
CATALOG: Now works properly with Oracle Databases.
CONFORM: Now works properly with Oracle Databases.
Version 1.19 (February 2014)
OPERATIONAL FIX FOR ONE CUSTOMER RELEASE.
Fixed initialization parameter test setting introduced in February 2014.
Version 1.18 (November 2013)
SMALL PRINTING ADJUSTMENT.
ALL: Fixed minute printing error.
Version 1.17 (April 2013)
ADDED A NEW TABLE TO CHECK FOR CORRUPT FILES.
HALFSTEP: Add check for "Recalculate Actual Units and Cost when duration % complete changes for project" project calculations setting set to unchecked.
REBUILD: Add check for "Recalculate Actual Units and Cost when duration % complete changes for project" project calculations setting set to unchecked.
ALL: Fixed Free Memory readout for 64-bit computers.
CORRUPT: Added Administrative Preferences to the tables being checked.
Version 1.16 (February 2013)
UPDATED SOFTWARE TO RUN ON WINDOWS 8 COMPUTERS.
SEQUENCE: Improved capture rate on unstarted predecessor activities.
SEQUENCE: Added Statistics Section.
ALL: Changed white project names on Cyan background to black lettering for readability.
ALL: Configured for Windows 8.
TRACER: Made operations much more user-interruption aware.
Version 1.15 (August 2012)
ADDED TWO NEW FUNCTIONS TO CATALOGER.
ALL: Improved Login screen functionality and error handling.
CATALOGER: Re-organized menus for better functionality.
CATALOGER: Added Enumerate Critical Path for all Baseline Schedules attached to any schedule.
RELATED: Fixed reporting on successor extra-schedule relationships.
COMPARE: Improved usability and bullet-proofed for missing setup information.
COMPARE: Allowed for P3 reoccurring dates to be processed.
COMPARE: Improvements to Calendars & Resource checks.
ALL: On Open Schedule screen, adjust Data Date if it is earlier than Planned Start.
CATALOGER: Added Schedules using Resources reports.
COMPARE: Added progress meter to each section.
COMPARE: Explained resource error in case of no assignments better.
COMPARE: Fixed over-reporting in Cost Section.
Version 1.14 (April 2012)
ADDED AS-PLANNED/AS-BUILT OPTION TO SCHEDULE REBUILDER.
REBUILD: Added As-Built Actual Duration option.
REBUILD: Added As-Built Early Start option.
Version 1.13 (February 2012)
IMPROVEMENTS TO RELATED SCHEDULES MODULE.
RELATED: Fixed Show Baselines function.
RELATED: Added ability to not report on baseline schedule issues.
REBUILD: Added conversion of actual activity resource status along with activity status.
Version 1.12 (November 2011)
ADDED HALF-STEP SCHEDULE.
HALF: Added Half-Step to eForensic.
MENU: Added Half-Step Schedule to the menu.
ALL: Fixed incorrect project short name or full name in 1% of Oracle cases.
REBUILD: Upgraded date handling for Oracle databases.
REBUILD: Prevented holidays beyond end of calendar from causing error.
REBUILD: Create report separately from diagnostics (speeds-up operation.)
REBUILD: Add View button.
MENU: Added Schedule Rebuilder & Half-Step Schedule Result Reports to Backup/Restore.
Version 1.11 (October 2011)
COMPARE P3 TO P6 BUG FIXES.
COMPARE: Extensive re-write to fix numerous errors.
Version 1.10 (August 2011)
ADDED MENU PROGRAM.
ALL: Improved Login diagnostics.
MENU: Added Menu Program with file backup and new Welcome Video.
RELATED: Added Related Schedules module.
Version 1.10 (August 2011)
ORACLE G11 (P6 R8.1) UPGRADE FIXES.
REBUILD: Corrected new Percent Complete calculation for in-progress activities.
REBUILD: Improved resource updating.
ALL: Speed-up scheduling display list by double.
ALL: Added Oracle R8 login.
ALL: Fixed R8 database version change format issue.
DATECALC: Version 4.25 upgrades.
Version 1.08 (March 2011)
MINOR BUG FIXES.
REBUILD: Fixed failure to run glitch.
CONFORMER: Fixed Error 9 glitch at start.
ALL: Improved error message when logon is dropped.
Version 1.07 (December 2010)
CONVERTED ALL PROGRAMS TO READ XER AS WELL AS XML FILES
REBUILDER: Added XML option for Oracle Holidays.
SEQUENCE: Added XML option for Oracle Holidays.
WORKDAY: Added XML option for Oracle Holidays.
COMPARE: Added XML option for Oracle Holidays.
REBUILDER: Speed-up calendar creation process.
SEQUENCE: Speed-up calendar creation process.
WORKDAY: Speed-up calendar creation process.
TRACER: Speed-up calendar creation process.
TRACER: Added XML option for Oracle Holidays.
DATECALC: Fixed workdays error for time periods less than 1 week.
CATALOGER: Added XML option for cataloging.
Version 1.06 (September 2010)
MADE eFORENSIC RUN UNDER ORACLE DATABASES
CATALOG: Wrapped the XER file's name at the top of a XER print-out for readability.
CATALOG: Added Report Width setting to program.
REBUILD: Wrapped the report file's name at the bottom of the results print-out for readability.
SEQUENCE: Further bullet-proofing when reading Base Calendars.
SEQUENCE: Fixed unusual problem of missing actual date in historical activities.
SEQUENCE: Added Oracle calendar building and relationship lag calendar check.
TRACER: Added Oracle calendar building and relationship lag calendar check.
PROGRESS: Added Oracle calendar building and relationship lag calendar check (pre-introduction).
REBUILDER: Added Oracle XER calendar building routine.
WORKDAY: Added Oracle XER calendar building routine.
Version 1.05 (June 2010)
ENHANCED COMPARE P3 TO P6
COMPARE: Added Verbose Option for the explanation of the mismatch.
Version 1.04 (May 2010)
ADDED COMPARE P3 TO P6 PROGRAM
CATALOGER: Corrected blank CPM Settings when more than one project in an XER file.
CATALOGER: Fixed the date at the top of the Catalog Spreadsheet.
COMPARE: Added Compare P3 to P6 program.
Version 1.03
UPDATED REBUILDER FOR RESOURCES
ALL: Updated Splash Screen
REBUILD: Added Activity Resources after the Data Date check and deletion.
Version 1.02
INTERNAL ERROR CHECK ENHANCEMENTS
ALL: Enhancement to existing internal error checking routines.
ALL: Added the midnight Timer delay fix.
DATECALC: Multiple improvements to functionality.
Version 1.01
OVERVIEW: INTERNAL UPGRADE
ALL: Update internal schedule display control to Version 6.5.
Version 1.00 (October 2008)
OVERVIEW: ORIGINAL ALPHA TEST
Original Alpha-Test, Begun OCT-08
Cataloger/Investigator/Work Day Calendar converted from SAe package and enhanced.
P6 Backup Reader [Handout] added on 10OCT08
Cataloger added on 12NOV08
Out-of-Sequence Report added on 05JAN09
Conformer added on 10MAR09
Corrupt Files added on 27MAR09
Rebuilder added on 30APR09
Trace added on 30JUL09